PSC 112.02(4)(b) (b) Peripheral construction such as relaying or switching facilities made necessary at other system substations or terminations remote from the project area itself.
PSC 112.02(4)(c) (c) Related operating and maintenance charges for building remodeling projects and replacements and modifications at generating plants.
PSC 112.02(5) (5) “kV" means kilovolt, or 1,000 volts.
PSC 112.02(6) (6) “kW" means kilowatt, or 1,000 watts.
PSC 112.02(7) (7) “Municipality" means a town, village, city, or county.
PSC 112.02(8) (8) “Transmission line" means an electric line, designed and operated at 40 kV or higher voltage.
PSC 112.02(9) (9) “Transmission system" means electric lines and associated facilities, designed and operated at 40 kV or higher voltage, that transmit power from generating plants to and between distribution systems.
PSC 112.02 History History: Cr. Register, November, 1995, No. 479, eff. 12-1-95; CR 07-044: am. (1) Register May 2008 No. 629, eff. 6-1-08.
PSC 112.03 PSC 112.03New service in a municipality. No electric utility may begin construction, install or place in operation any physical facilities for furnishing retail electric service in a municipality in which the utility has not rendered retail electric service, without the commission's prior approval under s. PSC 112.07.
PSC 112.03 History History: Cr. Register, November, 1995, No. 479, eff. 12-1-95.
PSC 112.04 PSC 112.04Interconnection projects. No electric utility may begin construction, install or place in operation an initial interconnection with the transmission system of another electric utility, with which it has no existing transmission interconnections, without the commission's prior approval under s. PSC 112.07. Any subsequent interconnection by mutual agreement with the same electric utility does not require commission approval except as provided in s. PSC 112.05. The electric utility shall, however, report each subsequent interconnection to the commission at least 90 days before it begins construction. The report shall include a description of the project, its location, the estimated gross cost, and a discussion of the need. Electric utilities may, without commission authorization, establish temporary or emergency interconnections between their systems by mutual agreement, but shall promptly report such interconnections to the commission within 10 days of the date established and the date discontinued.
PSC 112.04 History History: Cr. Register, November, 1995, No. 479, eff. 12-1-95.
PSC 112.05 PSC 112.05Construction of electric utility facilities.
PSC 112.05(1)(1) No electric utility may begin construction, install or place in operation any of the following facilities whose estimated gross cost exceeds the applicable amount specified in sub. (3), without prior commission approval under s. PSC 112.07:
PSC 112.05(1)(a) (a) A generating plant or unit.
PSC 112.05(1)(b) (b) A replacement, modification or addition at a generating plant. This paragraph applies to projects or combinations of projects where the same replacement, modification or addition is known to be required at more than one unit at the same plant over a reasonably short period of time and the total cost of the combined work exceeds the applicable amount specified in sub. (3). This paragraph also applies to the initial construction of major new waste disposal facilities for the plant, even if not located at or adjacent to the existing plant site. This paragraph does not apply to replacements, modifications or repairs to a hydroelectric dam or related civil works to comply with dam safety or similar regulatory requirements, if the capacity or operation of the generating facilities is not significantly changed.
PSC 112.05(1)(c) (c) A project for constructing or rebuilding a transmission line, including necessary terminations and related new substation or substation additions. This paragraph does not apply to the relocation or modification of a segment of an existing transmission line, if the utility is ordered to relocate or modify the line to accommodate highway or airport construction, nor to the reconstruction or restoration of a segment of an existing transmission line made necessary by storm damage.
PSC 112.05(1)(d) (d) A new substation or switching station.
PSC 112.05(1)(e) (e) An addition to or replacement at an existing substation or switching station.
PSC 112.05(1)(f) (f) A distribution system extension, conversion to a higher voltage or conversion from overhead to underground construction.
PSC 112.05(1)(g) (g) A new building or any addition to or remodeling of an existing building. This paragraph applies to the purchase of an existing building by a utility for conversion to utility use.
PSC 112.05(1m)(a)(a) No public utility may begin a project to construct or rebuild a transmission line whose length exceeds 10 miles and whose cost is less than the applicable amount specified in sub. (3) without first filing a report under par. (b) and securing commission approval under par. (c). The report and commission approval are not required for projects entirely within existing electric utility transmission line right of way.
PSC 112.05(1m)(b) (b) The utility shall file the report required under this subsection at least 90 days before it intends to begin construction or rebuilding. The report shall include a description of the project, its location and proposed route or routes, the estimated cost and a discussion of the need for the project.
PSC 112.05(1m)(c) (c) After reviewing the report, the commission may do any of the following:
PSC 112.05(1m)(c)1. 1. Approve the project by acknowledging, in writing, receipt of the report and accepting it for filing.
PSC 112.05(1m)(c)2. 2. Direct, in writing, that the project shall not proceed until specific approval is granted under s. 196.49, Stats.
PSC 112.05(1m)(c)3. 3. Approve the project by taking no action within 90 days of receiving the utility's written report.
PSC 112.05(1m)(d) (d) This subsection does not apply to a project that requires a certificate of public convenience and necessity under s. 196.491 (3), Stats.
PSC 112.05(2) (2) A Wisconsin electric utility proposing to construct, install or place in operation any of the utility facilities listed in sub. (1) in another state in which it serves shall notify the commission at least 60 days before beginning construction. The notification shall include a description of the project, its location, the estimated cost, a discussion of need, permits or approvals required by the other state or local governments, and the approximate jurisdictional allocation of the cost between Wisconsin and the other state. Notwithstanding sub. (3), if a significant portion of the cost of the project will be allocated to Wisconsin for ratemaking purposes, the commission may require that the utility submit an application under s. PSC 112.06, for commission authorization prior to construction, installation or operation.
PSC 112.05(3)(a)(a) Cost thresholds for projects requiring commission review and approval under this section are those specified in s. 196.49 (5g) (ar), Stats., as revised under par. (b).
PSC 112.05(3)(b) (b) Beginning on May 1, 2014, and on May 1 of each successive even-numbered year thereafter, the commission shall adjust the cost thresholds in s. 196.49 (5g) (ar), Stats., to reflect changes to the cost of electric utility construction based on the cost index numbers published in the “Handy-Whitman Index of Public Utility Construction Costs, Cost Trends of Electric Utility Construction — North Central Region for Total Transmission Plant".
PSC 112.05(3)(c) (c) The commission shall notify all electric utilities of the resulting adjusted cost limits by May 15 of each even-numbered year and shall publicize the adjusted cost limits on the commission's website. If the Handy-Whitman Index is no longer available, an equivalent successor index may be used which is generally recognized by the electric industry and acceptable to the commission.
PSC 112.05 Note Note: The commission maintains or has access to the Handy-Whitman Index of Public Utility Construction Costs and this reference or a copy may be reviewed by contacting the commission's offices.
PSC 112.05 History History: Cr. Register, November, 1995, No. 479, eff. 12-1-95; am. (1m) (a), (2) and (3), Register, October, 1998, No. 514, eff. 11-1-98; CR 14-053: renum. (3) (a) (intro.) to (3) (a) and am., r. (3) (a) 1. to 3., am. (3) (b), cr. (3) (c) Register April 2015 No. 712, eff. 5-1-15; correction in (3) (a), (b) made under s. 13.92 (4) (b) 7., Stats., Register January 2017 No. 733.
PSC 112.06 PSC 112.06Applications for commission authorization.
PSC 112.06(1)(1)Prior to filing an application. Before filing an application for commission authorization under s. 196.49, Stats., the applicant shall do all of the following:
PSC 112.06(1)(a) (a) Notify the department and the commission of its intent to seek commission authorization.
PSC 112.06(1)(b) (b) Consult with commission staff, in cooperation with staff from the department, on the scope of the proposed project, the alternatives that must be considered in the application, and additional information that the commission will require as part of the commission authorization application.
PSC 112.06(1m) (1m) An electric utility seeking authorization from the commission for a project under s. PSC 112.03, 112.04 or 112.05 shall submit an application to the commission including all of the following, where applicable:
PSC 112.06 Note Note: Section PSC 111.53 prescribes the contents of an application for commission approval to construct, install or place in operation a bulk or large electric generating facility and s. PSC 111.55 prescribes the contents of an application for commission approval to construct, install or place in operation a high-voltage transmission line, including related substation construction.
PSC 112.06(1m)(a) (a) A description of the project, including:
PSC 112.06(1m)(a)1. 1. Facility design, size, capacity and voltage.
PSC 112.06(1m)(a)2. 2. Line design, size and material.
PSC 112.06(1m)(a)3. 3. Line length and right-of-way width required.
PSC 112.06(1m)(a)4. 4. The size of the plant's or site's developed area.
PSC 112.06(1m)(a)5. 5. The approximate construction schedule.
PSC 112.06(1m)(b) (b) The gross cost and proposed method of financing the project.
PSC 112.06(1m)(c) (c) The purpose and necessity of the project with supporting data.
PSC 112.06(1m)(d) (d) The effect of the project on cost of operation and on the quality and reliability of service.
PSC 112.06(1m)(e) (e) A description of and the cost of any property being replaced.
PSC 112.06(1m)(f) (f) A description of and the gross cost of alternative methods, locations or routes which the electric utility considered for accomplishing the purpose of the project with a statement of the reasons for rejecting these alternatives.
PSC 112.06(1m)(g) (g) Environmental information including, where applicable:
PSC 112.06(1m)(g)1. 1. A map or drawing of the affected part of the existing electric system clearly showing the location of the proposed sites or routes of the proposed facilities and any alternate sites or routes considered.
PSC 112.06(1m)(g)2. 2. The proximity to designated flood plains or flood prone areas.
PSC 112.06(1m)(g)3. 3. For facilities that produce magnetic fields, including lines and substations, estimates of magnetic field strengths near the facility and the proximity of the site or route to nearby residences, work places, hospitals, nursing homes, schools, day care centers, parks and playgrounds.
PSC 112.06(1m)(g)4. 4. Information concerning applicable environmental factors for affected lands, such as land use or zoning, forest lands, rivers, streams, wetlands, endangered or threatened species and historical or archaeological resources.
PSC 112.06(1m)(g)5. 5. A listing of permits or approvals required by other units of government.
PSC 112.06(1m)(g)6. 6. Any other environmental screening information that the commission staff requests.
PSC 112.06(1m)(h) (h) For building projects, information on energy efficiency or conservation features, including:
PSC 112.06(1m)(h)1. 1. The whole building heat loss in Btu/square foot of the building envelope.
PSC 112.06(1m)(h)2. 2. The type and R-value of insulating material used for walls, ceilings, roofs, doors and windows.
PSC 112.06(1m)(h)3. 3. The type of heating and cooling system selected and the annual end-use energy estimate in Btu/square foot/year for space heating, space cooling, and any process use.
PSC 112.06(1m)(h)4. 4. The type and source of fuel or fuels selected.
PSC 112.06(1m)(h)5. 5. The type of lighting system selected and the annual end-use energy estimate for lighting.
PSC 112.06(1m)(i) (i) A designation of public utilities, municipalities, cooperative associations and others principally affected by the project and a statement as to which, if any, the applicant has notified.
PSC 112.06(1m)(j) (j) Any other information necessary to understand the project or information requested by the commission staff.
PSC 112.06(2) (2) The applicant shall file an original and 2 copies of each application. If the commission notifies the applicant that additional copies are required, the applicant shall promptly furnish them. If the original filing contains special material, such as commercial maps and aerial photographs, any required additional copies of the application may contain photocopies or other reproductions of these special materials.
PSC 112.06 History History: Cr. Register, November, 1995, No. 479, eff. 12-1-95; CR 07-044: renum. (1) to be (1m), cr. (1) Register May 2008 No. 629, eff. 6-1-08.
PSC 112.07 PSC 112.07Processing of applications by the commission.
PSC 112.07(1)(1) If upon consideration of the application, together with any supplemental information and objections, the commission finds that the public convenience and necessity require the project as proposed and the project complies with s. 196.49 (3) (b), Stats., the commission may authorize the project without public hearing but with modifications and conditions it considers necessary.
PSC 112.07(2) (2) Except as provided in sub. (1), the commission shall hold a public hearing on the application and grant or deny the application, in whole or in part, subject to any conditions the commission finds are necessary to protect the public interest or promote the public convenience and necessity.
PSC 112.07 History History: Cr. Register, November, 1995, No. 479, eff. 12-1-95.
PSC 112.073 PSC 112.073Notification of additional work areas. After the commission has issued an authorization under s. 196.49, Stats., the applicant shall, before establishing any lay down area, staging area or access route that was not identified and described in the project application, notify the commission of the location of the lay down area, staging area or access route, and demonstrate that the use of the lay down area, staging area or access route will not affect any threatened or endangered species, historic resources, wetlands, waterways or other sensitive resources.
PSC 112.073 History History: CR 07-044: cr. Register May 2008 No. 629, eff. 6-1-08.
PSC 112.075 PSC 112.075Emergency work. In case of emergency, an electric utility may begin necessary work without complying with ss. PSC 112.06 and 112.07. The utility shall do all of the following:
PSC 112.075(1) (1) Notify the commission of its actions within 48 hours of commencement of the work.
PSC 112.075(2) (2) Furnish the commission the information required under s. PSC 112.06 within 30 days of commencement of the work.
PSC 112.075 History History: CR 07-044: cr. Register May 2008 No. 629, eff. 6-1-08.
PSC 112.08 PSC 112.08Extensions of electric service under s. 196.495, Stats.
PSC 112.08(1)(1) In addition to any other conditions established by law or commission order, the measurement of an extension's length under s. 196.495 (1) (b), Stats., shall be from an existing local service distribution line that is, or has been, actually used in rendering local service to a customer. A street light or security light is not a principal building or facility under s. 196.495 (1) (b), Stats.
PSC 112.08(2) (2) The commission shall enforce any written territorial agreement filed by 2 utilities, a utility and a cooperative association, or 2 cooperative associations to avoid duplication of facilities, if:
PSC 112.08(2)(a) (a) The agreement governs the extension of electric distribution lines and the right to serve customers; and
PSC 112.08(2)(b) (b) The commission has approved the agreement as being in the public interest.
PSC 112.08 History History: Cr. Register, November, 1995, No. 479, eff. 12-1-95.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.