LRB-3918/1
MDK:jld:jf
2011 - 2012 LEGISLATURE
March 15, 2012 - Introduced by Representative Honadel. Referred to Committee
on Energy and Utilities.
AB730,1,4 1An Act to amend 196.491 (3) (a) 1., 196.491 (3) (a) 2., 196.491 (3) (a) 3. a. and
2196.491 (3) (a) 3. b. of the statutes; relating to: certificates of public
3convenience and necessity and permits for certain electric generating facilities
4and high-voltage transmission lines.
Analysis by the Legislative Reference Bureau
With certain exceptions, current law prohibits a person from constructing a
large electric generating facility or high-voltage transmission line unless the Public
Service Commission (PSC) has granted the person a certificate of public convenience
and necessity (CPCN). Current law defines a "large electric generating facility" as
a facility designed for nominal operation at a capacity of 100 megawatts or more and
a "high-voltage transmission line" as an electric transmission line exceeding one
mile in length that is designed for operation at a nominal voltage of 100 kilovolts or
more. Within 30 days after an application for a CPCN is filed, the PSC must
determine whether the application is complete. If the PSC determines that an
application is incomplete, the PSC must notify the applicant, who is allowed to refile
the application. If the PSC fails to determine that an application is complete within
30 days after filing, current law provides that the application is considered to be
complete. This bill clarifies that an application is considered to be complete if the
PSC fails to determine that the application is complete within 30 days after filing or
refiling of the application.
Current law also requires the PSC, within ten days after an application for a
CPCN is filed, to submit copies of the application to the clerk of each city, village, and

town in which the proposed large electric generating facility or high-voltage
transmission line is to be located and to the main public library in each such county.
This bill requires instead that the PSC must submit the copies within ten days after
the PSC determines that the application is complete or after the application is
considered to be complete. In addition, current law requires an applicant for a CPCN
for a high-voltage transmission line to submit a detailed project plan to the
Department of Natural Resources (DNR) at least 60 days prior to filing the CPCN
application. This bill eliminates the requirement to submit the plan to DNR.
Current law also provides that, if an applicant for a CPCN is also required to
obtain one or more permits from DNR, the applicant must use a procedure for
submitting only one application to DNR for all of the required DNR permits
(combined permit procedure), rather than submitting separate applications to DNR
for each permit. However, the combined permit procedure does not apply if the only
DNR permit the applicant is required to obtain is a storm water discharge permit.
Current law specifies two deadlines for DNR to complete action on the permit
applications. The first deadline is that DNR must complete action within 120 days
after the date on which the permit application is complete or considered to be
complete. Like the PSC, current law requires DNR to determine whether an
application is complete within 30 days after filing, allows an applicant to refile an
application that is incomplete, and specifies that, if DNR fails to determine that an
application is complete within 30 days after filing or refiling, the application is
considered to be complete. The second deadline is that DNR must complete action
on the permit application within 30 days after the PSC issues its decision on the
CPCN application. This bill provides that, if the combined permit procedure applies
to an applicant, the second deadline applies to DNR, and not the first deadline.
The people of the state of Wisconsin, represented in senate and assembly, do
enact as follows:
AB730, s. 1 1Section 1. 196.491 (3) (a) 1. of the statutes is amended to read:
AB730,3,22 196.491 (3) (a) 1. Except as provided in sub. (3b), no person may commence the
3construction of a facility unless the person has applied for and received a certificate
4of public convenience and necessity under this subsection. An application for a
5certificate issued under this subsection shall be in the form and contain the
6information required by commission rules and shall be filed with the commission not
7less than 6 months prior to the commencement of construction of a facility. Within
810 days after filing an application under this subdivision, the commission shall send

1a copy of the application to the clerk of each municipality and town in which the
2proposed facility is to be located and to the main public library in each such county.
AB730, s. 2 3Section 2. 196.491 (3) (a) 2. of the statutes is amended to read:
AB730,3,164 196.491 (3) (a) 2. The commission shall determine whether an application filed
5under subd. 1. is complete and, no later than 30 days after the application is filed,
6notify the applicant about the determination. If the commission determines that the
7application is incomplete, the notice shall state the reason for the determination. An
8applicant may supplement and refile an application that the commission has
9determined to be incomplete. There is no limit on the number of times that an
10applicant may refile an application under this subdivision. If the commission fails
11to determine whether an application is complete within 30 days after the application
12is filed or refiled, the application shall be considered to be complete. Within 10 days
13after the commission determines that an application is complete or the application
14is considered to be complete, the commission shall send an electronic copy of the
15complete application to the clerk of each municipality and town in which the
16proposed facility is to be located and to the main public library in each such county.
AB730, s. 3 17Section 3. 196.491 (3) (a) 3. a. of the statutes is amended to read:
AB730,4,418 196.491 (3) (a) 3. a. At least 60 days before a person files an application under
19subd. 1., the person shall provide the department with an engineering plan if the
20facility is a large electric generating facility or a detailed project plan if the facility
21is a high-voltage transmission line
. The engineering or project plan shall show the
22location of the facility, a description of the facility, including the major components
23of the facility that have a significant air, water or solid waste pollution potential, and
24a brief description of the anticipated effects of the facility on air quality, water
25quality, wetlands, solid waste disposal capacity, and other natural resources. Within

130 days after a person provides an engineering or project plan, the department shall
2provide the person with a listing of each department permit or approval which, on
3the basis of the information contained in the engineering or project plan, appears to
4be required for the construction or operation of the facility.
AB730, s. 4 5Section 4. 196.491 (3) (a) 3. b. of the statutes is amended to read:
AB730,4,206 196.491 (3) (a) 3. b. Within 20 days after the department provides a listing
7specified in subd. 3. a. to a person, the person shall apply for the permits and
8approvals identified in the listing. The department shall determine whether an
9application under this subd. 3. b. is complete and, no later than 30 days after the
10application is filed, notify the applicant about the determination. If the department
11determines that the application is incomplete, the notice shall state the reason for
12the determination. An applicant may supplement and refile an application that the
13department has determined to be incomplete. There is no limit on the number of
14times that an applicant may refile an application under this subd. 3. b. If the
15department fails to determine whether an application is complete within 30 days
16after the application is filed, the application shall be considered to be complete. The
17Except as provided in s. 30.025 (4), the department shall complete action on an
18application under this subd. 3. b. for any permit or approval that is required prior
19to construction of a facility within 120 days after the date on which the application
20is determined or considered to be complete.
AB730, s. 5 21Section 5. Initial applicability.
AB730,4,2322 (1) The treatment of section 196.491 (3) (a) 2. and 3. b. of the statutes first
23applies to applications filed or refiled on the effective date of this subsection.
AB730,4,2424 (End)
Loading...
Loading...