LRB-0488/1
MDK:kjf:pg
2005 - 2006 LEGISLATURE
July 7, 2005 - Introduced by Representatives Black, Sherman, Molepske and
Berceau, cosponsored by Senator Risser. Referred to Committee on Energy
and Utilities.
AB545,1,11 1An Act to repeal 196.491 (2) (a) 3m.; to renumber 196.491 (2) (a) 3g. and
2196.491 (2) (a) 3r., 4., 7., 9., 10., 11., 12. and 13.; to renumber and amend
3196.491 (2) (a) (intro.) and 196.491 (2) (a) 3.; to amend 196.491 (title), 196.491
4(1) (d), 196.491 (2) (title), 196.491 (2) (ag), 196.491 (2) (b) (intro.), 196.491 (2) (b)
510., 196.491 (2) (e), 196.491 (2) (f), (g) and (gm), 196.491 (3) (d) 2., 196.491 (3)
6(dm) and 196.491 (3) (g); and to create 196.03 (7), 196.491 (2) (ac) (intro.),
7196.491 (2) (ac) 3e., 196.491 (2) (ac) 11. to 14., 196.491 (2) (ae), 196.491 (3) (d)
83g. and 196.491 (3e) of the statutes; relating to: strategic energy plans
9regarding electricity, certificates of public convenience and necessity for electric
10generation and transmission facilities, approval of electric power purchase
11contracts, and granting rule-making authority.
Analysis by the Legislative Reference Bureau
As described below, this bill does all of the following: 1) changes the
requirements for the Public Service Commission (PSC) to prepare a strategic energy
assessment; 2) changes the requirements for the PSC to grant certificates of public
convenience and necessity (CPCNs) for electric generating facilities and

high-voltage transmission lines; 3) requires the PSC to approve certain power
purchase contracts; and 4) prohibits electric utilities from recovering certain costs
in rates.
Strategic energy assessments. Under current law, every two years, the PSC
must prepare a strategic energy assessment that evaluates the adequacy and
reliability of the state's current and future electrical supply. The assessment must
describe large electric generating facilities and high-voltage transmission lines that
electric utilities plan to construct within three years. Current law defines a "large
electric generating facility" as a facility with a capacity of 100 megawatts or more.
Current law requires the PSC to assess the following in the assessment: 1) the
adequacy and reliability of purchased generation capacity and energy; 2) the
regional bulk-power market; 3) certain effects of competition; and 4) the sufficiency
and price of electric capacity and energy. The assessment must also describe the
following: 1) plans for assuring the ability to transfer electric power into the state;
2) the projected demand for electric energy; 3) activities to discourage inefficient and
excessive power use; and 4) existing and planned generating facilities that use
renewable sources of energy. In addition, the assessment must consider the public
interest in economic development, public health and safety, protection of the
environment, and diversification of sources of energy supplies.
This bill changes the name of the strategic energy assessment to a strategic
energy plan, and requires the PSC to prepare a plan every year or every two years.
As under current law, the plan must evaluate the adequacy and reliability of the
state's current and future electrical supply. However, the bill specifies that the
future periods that must be considered are the next five and ten years. The plan must
include all of the components described above that must be included in an
assessment under current law. In addition, the plan must describe wholesale
merchant plants that any person plans to construct within the next five and ten
years. Current law defines "wholesale merchant plant" to mean electric generating
equipment and associated facilities that do not provide service to retail customers
and that are operated by a public utility affiliate or a person that is not a public
utility.
Also, the bill requires the PSC's plan to do the following in evaluating the
energy supply over the next five years: 1) describe the power purchase contracts into
which electric utilities propose to enter; 2) explain how each electric utility will
satisfy reliability needs at the least cost; 3) identify the specific resources and
facilities that each electric utility will use to satisfy system load and reserve
requirements; and 4) identify the reasonable needs of the public for an adequate
supply of electric energy. In evaluating the energy supply over the next ten years,
the PSC's plan must do the following: 1) evaluate the projected trends for generation,
transmission, load, and conservation; 2) forecast the performance of electricity
markets; 3) evaluate the economic impacts, projected costs (including costs of
externalities), and environmental impacts of the current system for supplying
electricity and of alternatives to that system; and 4) determine the mix of resources
and facilities necessary to satisfy the projected demand for electricity. Regarding the
mix of resources, the PSC must consider renewable and nonrenewable resources,

traditional and nontraditional sources of electric generation, and alternatives to
electric generation. Regarding alternatives, the PSC must consider investments in
energy conservation to the maximum extent that is reasonable.
Under current law, the PSC must comply with certain requirements for
preparing a strategic energy assessment in draft form, holding hearings on the draft,
and issuing a final version of the assessment. The bill does not affect these
requirements, except to refer to a plan, rather than to an assessment.
CPCNs. Under current law, a person may not construct a large electric
generating facility or high-voltage transmission line unless the PSC has issued a
CPCN for the facility. However, certain construction activities relating to existing
high-voltage transmission lines do not require a CPCN. As noted above, a "large
electric generating facility" under current law is defined as a facility with a capacity
of 100 megawatts or more.
The bill prohibits the PSC from issuing a CPCN unless a large electric
generating facility or transmission line satisfies a reasonable need of the public for
an adequate supply of electric energy that is identified in the most recent strategic
energy plan prepared by the PSC. In addition, the bill prohibits the PSC from issuing
a CPCN for a wholesale merchant plant unless the plant satisfies the same need.
Current law also requires the PSC to make a finding regarding reasonable need, but
does not relate the requirement to the strategic energy assessment. Also, under
current law, wholesale merchant plants are exempt from the requirement regarding
need.
The bill also prohibits the PSC from issuing a CPCN unless a facility or line does
not have higher costs or greater environmental impacts than other facilities and
lines identified in the most recent strategic energy plan prepared by the PSC.
In addition, under current law, if the PSC does not make a final determination
on an application for a CPCN within 180 days after an application is completed, or
within a court-approved extension of up to an additional 180 days, the PSC is
considered to have issued a CPCN. Under this bill, the PSC must make a final
determination within 360 days after an application is completed. No court approval
is required for the PSC to take the entire 360 days. In addition, the bill eliminates
the requirement that, if the PSC does not meet the deadline, the PSC is considered
to have issued the CPCN.
Power purchase contracts. The bill requires an electric utility to obtain the
PSC's approval before entering into a contract for the purchase of electric power. The
PSC must promulgate rules for such approvals. In addition, the PSC may not
approve such a contract unless the contract satisfies a reasonable need of the public
for an adequate supply of electric energy that is identified in the most recently
prepared strategic energy plan. These requirements do not apply to a municipal
electric utility or a cooperative association.
Prohibition on recovering certain costs in rates. The bill prohibits the
PSC from allowing an electric utility to recover in rates charged to customers any
costs associated with a large electric generating facility, high-voltage transmission
line, or power purchase contract unless the PSC has previously identified the facility,
line, or contact in a strategic energy plan. However, the prohibition does not apply

if the utility demonstrates to the PSC's satisfaction that an unforeseen emergency
prevented such identification.
For further information see the state and local fiscal estimate, which will be
printed as an appendix to this bill.
The people of the state of Wisconsin, represented in senate and assembly, do
enact as follows:
AB545, s. 1 1Section 1. 196.03 (7) of the statutes is created to read:
AB545,4,82 196.03 (7) The commission may not authorize a public utility to recover in rates
3charged to customers any costs associated with a facility, as defined in s. 196.491 (1)
4(e), or a power purchase contract unless the commission has previously identified the
5facility or power purchase contract in a strategic energy plan under s. 196.491 (2) (ac)
61. or 11. This subsection does not apply if the public utility demonstrates to the
7satisfaction of the commission that an unforeseen emergency has prevented the
8previous identification of the facility or power purchase contract.
AB545, s. 2 9Section 2. 196.491 (title) of the statutes is amended to read:
AB545,4,11 10196.491 (title) Strategic energy assessment plan; electric generating
11facilities and transmission lines.
AB545, s. 3 12Section 3. 196.491 (1) (d) of the statutes is amended to read:
AB545,4,1713 196.491 (1) (d) "Electric utility" means any public utility, as defined in s.
14196.01, which is involved in the generation, distribution and sale of electric energy,
15and any corporation, company, individual or association, and any cooperative
16association, which owns or operates, or plans within the next 3 5 or 10 years to
17construct, own or operate, facilities in the state.
AB545, s. 4 18Section 4. 196.491 (2) (title) of the statutes is amended to read:
AB545,4,1919 196.491 (2) (title) Strategic energy assessment plan.
AB545, s. 5
1Section 5. 196.491 (2) (a) (intro.) of the statutes is renumbered 196.491 (2) (a)
2and amended to read:
AB545,5,63 196.491 (2) (a) The commission shall prepare a an annual or biennial strategic
4energy assessment plan that evaluates the adequacy and reliability of the state's
5current and future electrical supply. The strategic energy assessment shall do all of
6the following:
and the state's future electrical supply over the next 5 and 10 years.
AB545, s. 6 7Section 6. 196.491 (2) (a) 3. of the statutes is renumbered 196.491 (2) (ac) 1.
8and amended to read:
AB545,5,119 196.491 (2) (ac) 1. Identify and describe the large electric generating facilities
10and high-voltage transmission lines on which an each electric utility plans to
11commence construction within 3 years during the 5-year period.
AB545, s. 7 12Section 7. 196.491 (2) (a) 3g. of the statutes is renumbered 196.491 (2) (ac) 3m.
AB545, s. 8 13Section 8. 196.491 (2) (a) 3m. of the statutes is repealed.
AB545, s. 9 14Section 9. 196.491 (2) (a) 3r., 4., 7., 9., 10., 11., 12. and 13. of the statutes are
15renumbered 196.491 (2) (ac) 3s., 4., 5., 6., 7., 8., 9. and 10.
AB545, s. 10 16Section 10. 196.491 (2) (ac) (intro.) of the statutes is created to read:
AB545,5,1917 196.491 (2) (ac) (intro.) In evaluating the state's future electrical supply over
18the next 5 years, the commission shall do each of the following in a plan under par.
19(a):
AB545, s. 11 20Section 11. 196.491 (2) (ac) 3e. of the statutes is created to read:
AB545,5,2221 196.491 (2) (ac) 3e. Identify and describe wholesale merchant plants on which
22any person plans to commence construction within the 5-year period.
AB545, s. 12 23Section 12. 196.491 (2) (ac) 11. to 14. of the statutes are created to read:
AB545,5,2524 196.491 (2) (ac) 11. Identify and describe the power purchase contracts that
25each electric utility proposes to enter into during the 5-year period.
AB545,6,2
112. Explain how each electric utility will satisfy reliability needs at the least
2cost.
AB545,6,63 13. Identify the specific resources and facilities that each electric utility will use
4to satisfy system load and reserve requirements. A resource or facility may not be
5identified unless it is consistent with the mix of resources and facilities determined
6by the commission in par. (ae) 6.
AB545,6,97 14. Identify the reasonable needs of the public for an adequate supply of electric
8energy that an electric utility must show for purposes of satisfying subs. (3) (d) 2. and
9(3e).
AB545, s. 13 10Section 13. 196.491 (2) (ae) of the statutes is created to read:
AB545,6,1311 196.491 (2) (ae) In evaluating the state's future electrical supply over the next
1210 years, the commission shall perform the acts described in par. (ac) 3m. to 10. and
13do each of the following in a plan under par. (a):
AB545,6,1714 1. Identify and describe large electric generating facilities and high-voltage
15transmission lines, other than those facilities and lines identified and described
16under par. (ac) 1., on which each electric generating facility plans to commence
17construction during the 10-year period.
AB545,6,2018 2. Identify and describe wholesale merchant plants, other than those plants
19identified and described under par. (ac) 3e., on which any person plans to commence
20construction within the 10-year period.