LRB-1630/1
JPC:kms
2023 - 2024 LEGISLATURE
February 14, 2023 - Introduced by Senators Cowles and Cabral-Guevara,
cosponsored by Representatives Goeben and Gustafson. Referred to
Committee on Government Operations, Elections and Consumer Protection.
SB50,1,3 1An Act relating to: expenditure of $201,197.70 from the general fund for
2payment of a claim against the state made by Pheifer Brothers Construction
3Co., Inc.
Analysis by the Legislative Reference Bureau
This bill directs the expenditure of $201,197.70 from the general fund in
payment of a claim against the Department of Transportation by Pheifer Brothers
Construction Co., Inc. The claimant entered into a contract with DOT to perform
work on the 2019 Ahnapee River Bridge project in Kewaunee County associated with
DOT project 4409-12-71. The claimant asserted that the subsurface conditions
differed from the conditions indicated in the bidding documents and that the
claimant incurred significant additional costs as a result. The claimant claimed
$201,197.70 for the cost of making multiple design changes to the project due to the
differing subsurface conditions. DOT denies the claimant's assertion that there were
differing subsurface conditions; asserts that the design changes were made at the
claimant's request in order to facilitate fulfillment of the contract; and argues that
additional compensation would be contrary to both the contract and the Wisconsin
Constitution. On March 22, 2022, the Claims Board denied the claim because it
concluded that the claimant has raised questions of fact with respect to the
subsurface conditions of the project that are better evaluated by a court of law (see
2021 Senate Journal, p. 944-45).

For further information see the state fiscal estimate, which will be printed as
an appendix to this bill.
The people of the state of Wisconsin, represented in senate and assembly, do
enact as follows:
SB50,1 1Section 1. Claim against the state.
SB50,2,82 (1) There is directed to be expended from the appropriation under s. 20.505 (4)
3(d) $201,197.70 in payment of a claim against the state brought by Pheifer Brothers
4Construction Co., Inc., Neenah, WI 54956, as reimbursement for work performed on
5department of transportation project 4409-12-71. Acceptance of this payment
6releases this state and its officers, employees, and agents from any further liability
7resulting from work performed by the claimant on department of transportation
8project 4409-12-71.
SB50,2,99 (End)