Relating to: strategic energy assessments, certification requirements applicable to certain projects proposed by public utilities, certificates of public convenience and necessity for certain electric generating facilities and high-voltage transmission lines, independent system operator or transmission owner of electric transmission system, certain out-of-state retail electric sales, ownership and operation of wholesale merchant plants, service standards for electric generation, transmission or distribution facilities, regional transmission planning and granting rule-making authority. (FE) relating to: strategic energy assessments, certification requirements applicable to certain projects proposed by public utilities, certificates of public convenience and necessity for certain electric generating facilities and high-voltage transmission lines, independent system operator or transmission owner of electric transmission system, certain out-of-state retail electric sales, ownership and operation of wholesale merchant plants, service standards for electric generation, transmission or distribution facilities, regional transmission planning and granting rule-making authority. (FE)
Date / House | Action | Journal |
---|---|---|
3/19/1998 Asm. | Introduced by Representatives Hoven, Gard, Johnsrud, Ott, Riley and Plale; cosponsored by Senators Welch, Rude and Farrow, by request of Governor Tommy G. Thompson. | |
3/19/1998 Asm. | Read first time and referred to committee on Utilities Oversight | |
3/20/1998 Asm. | Public hearing held. | |
3/24/1998 Asm. | Public hearing held. | |
3/24/1998 Asm. | Executive action taken. | |
3/24/1998 Asm. | Assembly amendment 1 offered by committee on Utilities Oversight | |
3/24/1998 Asm. | Report Assembly amendment 1 adoption recommended by committee on Utilities Oversight, Ayes 9, Noes 0 | |
3/24/1998 Asm. | Report passage as amended recommended by committee on Utilities Oversight, Ayes 9, Noes 0 | |
3/24/1998 Asm. | Referred to committee on Rules | |
3/24/1998 Asm. | Placed on calendar 3-25-98 by committee on Rules. | |
3/25/1998 Asm. | Read a second time | |
3/25/1998 Asm. | Assembly amendment 1 to Assembly amendment 1 offered by Representatives Duff, Riley, Johnsrud, Plale, R. Potter and Hoven | |
3/25/1998 Asm. | Assembly amendment 1 to Assembly amendment 1 adopted | |
3/25/1998 Asm. | Assembly amendment 1 adopted | |
3/25/1998 Asm. | Ordered to a third reading | |
3/25/1998 Asm. | Rules suspended | |
3/25/1998 Asm. | Read a third time and passed, Ayes 95, Noes 0 | |
3/25/1998 Asm. | Ordered immediately messaged | |
3/26/1998 Sen. | Received from Assembly | |
3/26/1998 Sen. | Read first time and referred to committee on Utility Regulation | |
3/26/1998 Sen. | Executive action taken. | |
3/26/1998 Sen. | Report concurrence recommended by committee on Utility Regulation, Ayes 6, Noes 0 | |
3/26/1998 Sen. | Available for scheduling. | |
3/26/1998 Sen. | Rules suspended and taken up | |
3/26/1998 Sen. | Read a second time | |
3/26/1998 Sen. | Ordered to a third reading | |
3/26/1998 Sen. | Rules suspended | |
3/26/1998 Sen. | Read a third time and concurred in, Ayes 31, Noes 1 | |
3/26/1998 Sen. | Ordered immediately messaged | |
3/26/1998 Asm. | Received from Senate concurred in | |
4/2/1998 Asm. | Report correctly enrolled | |
4/28/1998 Asm. | Report approved by the Governor on 4-28-98. 1997 Wisconsin Act 204 | |
4/30/1998 Asm. | Published 5-11-98 |