AB75-SSA1,401,107
30.443
(1) (a) Promulgate rules establishing standards for erosion prevention
8or control at sites in the riverway that are not subject to the standards established
9under s.
101.1205 (1) or 101.653 (2)
or 281.33 (3m) (a) and that have a natural slope
10of 20% or less.
AB75-SSA1,401,1512
30.443
(1) (b) Promulgate rules establishing standards for erosion prevention
13or control that are in addition to standards established under ss.
101.1205 (1) and 14101.653 (2)
and 281.33 (3m) (a) for sites in the riverway that are subject to those
15standards and that have a natural slope of 12% or more but 20% or less.
AB75-SSA1,401,2017
30.443
(2) The board may impose any of the applicable standards established
18under sub. (1) (a) or (b) or ss.
101.1205 (1) and 101.653 (2)
or 281.33 (3m) (a) as a
19condition for receiving a permit under s. 30.44 (1), and the board may promulgate
20rules to enforce these standards in the riverway.
AB75-SSA1,401,2322
30.52
(3) (b)
Fee for boats under 16 feet. The fee for the issuance or renewal of
23a certificate of number for a boat less than 16 feet in length is
$19 $22.
AB75-SSA1,402,3
130.52
(3) (c)
Fee for boats 16 feet or more but less than 26 feet. The fee for the
2issuance or renewal of a certificate of number for a boat 16 feet or more but less than
326 feet in length is
$28 $32.
AB75-SSA1,402,75
30.52
(3) (d)
Fee for boats 26 feet or more but less than 40 feet. The fee for the
6issuance or renewal of a certificate of number for a boat 26 feet or more but less than
740 feet in length is
$52 $60.
AB75-SSA1,402,109
30.52
(3) (e)
Fee for boats 40 feet or longer. The fee for the issuance or renewal
10of a certificate of number for a boat 40 feet or more in length is
$86 $100.
AB75-SSA1, s. 706c
11Section 706c. 30.52 (3m) (title) and (a) of the statutes are amended to read:
AB75-SSA1,402,1712
30.52
(3m) (title)
Voluntary contributions; lake research invasive species
13grants. (a) Any applicant for the issuance or renewal of a certificate of number or
14registration under sub. (3) (b) to (im) may, in addition to paying the fee charged for
15the certificate, elect to make a voluntary
$3 contribution
of at least $2 to be used for
16lake research grants under s. 23.22 (2) (c) to control invasive species that are aquatic
17species.
AB75-SSA1,402,2319
30.52
(3m) (am) If a person appointed under sub. (1m) (a) 3. collects a voluntary
20contribution under par. (a) from an applicant for the issuance or renewal of a
21certificate of number or registration, the person collecting the voluntary contribution
22may retain 50 cents of the voluntary contribution to compensate for the person's
23services in collecting the voluntary contribution.
AB75-SSA1,403,3
130.52
(3m) (b) All moneys collected under par. (a)
, less the amount retained as
2authorized under par. (am), shall be deposited into the account under s. 20.370 (3)
3(is).
AB75-SSA1,403,8
530.527 Nonresident boat sticker. (1) Except as provided in sub. (2),
6beginning on January 1, 2010, no person may operate, and no owner may give
7permission for operation of, a boat in the waters of this state unless a nonresident
8boat sticker issued under this subsection is displayed on the boat.
AB75-SSA1,403,10
9(2) The requirement under sub. (1) does not apply to a person who operates,
10or gives permission for the operation of, a boat if any of the following applies:
AB75-SSA1,403,1211
(a) The boat is covered by a registration issued by the department under s.
1230.51 (1) (b).
AB75-SSA1,403,1413
(b) The boat is exempt from registration under s. 30.51 (2) (a) 1., 2., 3m., 4., or
146. to 9. or (c) 1., 2., or 4.
AB75-SSA1,403,1615
(c) The boat does not land or dock at, or launch from, a pier, wharf, or other area
16on, or extending from, the shore of the waters of this state.
AB75-SSA1,403,20
17(3) A person who applies for issuance of a nonresident boat sticker under this
18section shall pay the department a fee of $11.25. A nonresident boat sticker issued
19under this section may be issued only by the department and persons appointed by
20the department and expires on December 31 of each year.
AB75-SSA1,403,23
21(4) (a) The department may appoint any person who is not an employee of the
22department as the department's agent to issue nonresident boat stickers and to
23collect the fees for these stickers.
AB75-SSA1,404,224
(b) Any person, including the department, who issues a nonresident boat
25sticker shall collect in addition to the fee under sub. (3) an issuing fee of 75 cents.
1An agent appointed under sub. (3) may retain 50 cents of the issuing fee to
2compensate the agent for the agent's services in issuing the sticker.
AB75-SSA1,404,53
(c) The department shall establish, by rule, procedures for issuing nonresident
4boat stickers and the department may promulgate rules regulating the activities of
5persons who are appointed to be agents under this subsection.
AB75-SSA1, s. 707
8Section
707. 31.19 (1) of the statutes is renumbered 31.19 (1m) and amended
9to read:
AB75-SSA1,404,1110
31.19
(1m) Determination of dam size. For the purposes of this section, a dam
11is considered to be a large dam if
either of the following applies:
AB75-SSA1,404,1312
(a) It has a structural height of 25 feet or more and impounds more than 15
13acre-feet of water
; or.
AB75-SSA1,404,1514
(b) It has a structural height of more than 6 feet and impounds
more than 50
15acre-feet
or more of water.
AB75-SSA1,404,1717
31.19
(1g) Definitions. In this section:
AB75-SSA1,404,1918
(a) "High hazard dam" means a large dam the failure of which would probably
19cause loss of human life.
AB75-SSA1,404,2120
(b) "Low hazard dam" means a large dam the failure of which would probably
21not cause significant property damage or loss of human life.
AB75-SSA1,404,2422
(c) "Significant hazard dam" means a large dam the failure of which would
23probably cause significant property damage but would probably not cause loss of
24human life.
AB75-SSA1, s. 709
25Section
709. 31.19 (2) (title) of the statutes is amended to read:
AB75-SSA1,404,26
131.19
(2) (title)
Decennial Large dam inspection.
AB75-SSA1,405,63
31.19
(2) (a)
Requirement
Inspection by the department. Except as provided
4under par. (b), at At least once every 10 years the department shall conduct a detailed
5inspection of each
high hazard dam
which is maintained or operated in or across
6navigable waters and each significant hazard dam.
AB75-SSA1,405,108
31.19
(2) (ag)
Owner responsibility. 1. Owners of each high hazard dam, each
9significant hazard dam, and each low hazard dam shall engage a professional
10engineer registered under s. 443.04 to inspect the dam as specified in this paragraph.
AB75-SSA1,405,1511
2. An owner of a high hazard dam shall cause the dam to be inspected at least
124 times between each inspection conducted by the department under par. (a). An
13owner of a significant hazard dam shall cause the dam to be inspected at least 2 times
14between each inspection conducted by the department under par. (a). An owner of
15a low hazard dam shall cause the dam to be inspected at least once every 10 years.
AB75-SSA1,405,2016
3. The owner of a dam required to be inspected under this paragraph shall
17submit to the department, no later than 90 days after the date of the inspection, a
18report of the results of the inspection. The report shall include information on any
19deficiencies in the dam, recommendations for addressing those deficiencies, and
20recommendations on improving the safety and structural integrity of the dam.
AB75-SSA1,405,2422
31.19
(2) (ar)
Dam classification. The department shall classify each dam in
23this state as a high hazard, significant hazard, or low hazard dam for the purpose of
24this section.
AB75-SSA1,406,5
131.19
(2) (b)
Exemption for federally inspected dams. An Notwithstanding the
2inspection requirements under pars. (a) and (ag), an inspection under par. (a)
or (ag) 3is not required if the dam is inspected periodically by or under the supervision of a
4federal agency in a manner which is acceptable to the department and if the results
5of each inspection are made available to the department.
AB75-SSA1, s. 713
6Section
713. 31.385 (1b) (intro.) and (a) of the statutes are consolidated,
7renumbered 31.385 (1b) and amended to read:
AB75-SSA1,406,108
31.385
(1b) In this section
: (a) "Dam "dam safety project" means the
9maintenance, repair, modification, abandonment or removal of a dam to increase its
10safety or any other activity that will increase the safety of a dam.
AB75-SSA1,406,1313
31.385
(1m) (b) To private owners for the removal of
small dams.
AB75-SSA1, s. 715g
14Section 715g. 31.385 (2) (a) 1. of the statutes is renumbered 31.385 (2) (a) 1.
15(intro.) and amended to read:
AB75-SSA1,406,1716
31.385
(2) (a) 1. (intro.) Except as provided in subd. 2., financial assistance for
17a dam safety project is limited to
no the sum of the following:
AB75-SSA1,406,18
18a. No more than 50% of the
cost
first $400,000 of costs of the project.
AB75-SSA1, s. 715m
19Section 715m. 31.385 (2) (a) 1. b. of the statutes is created to read:
AB75-SSA1,406,2120
31.385
(2) (a) 1. b. No more than 25 percent of the costs of the project that exceed
21$400,000.
AB75-SSA1, s. 716
22Section
716. 31.385 (2) (a) 2. of the statutes is amended to read:
AB75-SSA1,406,2423
31.385
(2) (a) 2. A project to remove
an abandoned a dam shall not be subject
24to the
50% cost
limit limits under subd. 1.
AB75-SSA1, s. 717
25Section
717. 31.385 (2) (a) 3. of the statutes is amended to read:
AB75-SSA1,407,2
131.385
(2) (a) 3. Financial assistance is limited to no more than
$200,000 2$400,000 for each dam safety project.
AB75-SSA1,407,64
31.385
(2) (ag) Of the amounts appropriated under s. 20.866 (2) (tL)
and (tx),
5at least $250,000 shall be used for projects to remove
small dams. A project to remove
6a
small dam may include restoring the stream or river that was dammed.
AB75-SSA1,407,118
31.385
(2) (ar) Of the amounts appropriated under s. 20.866 (2) (tL)
and (tx),
9at least $100,000 shall be used for the removal of abandoned dams.
The amounts
10required to be used under this paragraph are in addition to the amounts required to
11be used for the removal of dams under par. (ag).
AB75-SSA1,407,1513
31.385
(6) (a) Notwithstanding the limitations under sub. (2) (a) and the
14funding allocation requirements under sub. (2) (ag) and (ar), the department shall
15provide financial assistance to all of the following:
AB75-SSA1,407,1716
1. Adams County for a dam safety project for Easton Dam in the amount
17necessary for the project, but not to exceed $150,000.
AB75-SSA1,407,1918
2. The city of Stanley for a dam safety project for Stanley Dam in the amount
19necessary for the project, but not to exceed $150,000.
AB75-SSA1,407,2120
3. The city of Montello for a dam safety project for Montello Dam, in the amount
21necessary for the project, but not to exceed $150,000.
AB75-SSA1,407,2422
4. Eau Claire County for dam safety projects for Lake Altoona Dam, for Lake
23Eau Claire Dam, and for a dam located in Coon Fork Lake County Park, in the
24amount necessary for the projects, but not to exceed $27,000.
AB75-SSA1,408,5
1(b) The counties and cities need not contribute to the costs of the dam safety
2projects under par. (a) 1. to 4., and sub. (2) (c) does not apply to these projects. The
3dam safety projects under par. (a) 1. to 4. need not be included as dam safety projects
4under the inventory maintained by the department under sub. (4) in order to receive
5financial assistance under this subsection.
AB75-SSA1,408,117
32.02
(11) Any housing authority created under ss. 66.1201 to 66.1211;
8redevelopment authority created under s. 66.1333
; community development
9authority created under s. 66.1335; local cultural arts district created under subch.
10V of ch. 229, subject to s. 229.844 (4) (c);
or local exposition district created under
11subch. II of ch. 229
; or transit authority created under s. 66.1039.
AB75-SSA1,408,1713
32.035
(1) (b) "Farm operation" means any activity conducted solely or
14primarily for the production of one or more agricultural commodities resulting from
15an agricultural use, as defined in s. 91.01
(1) (2), for sale and home use, and
16customarily producing the commodities in sufficient quantity to be capable of
17contributing materially to the operator's support.
AB75-SSA1,409,1419
32.05
(1) (a) Except as provided under par. (b), a county board of supervisors
20or a county highway committee when so authorized by the county board of
21supervisors, a city council, a village board, a town board, a sewerage commission
22governing a metropolitan sewerage district created by ss. 200.05 or 200.21 to 200.65,
23the secretary of transportation, a commission created by contract under s. 66.0301,
24a joint local water authority created by contract under s. 66.0823,
a transit authority
25created under s. 66.1039, a housing authority under ss. 66.1201 to 66.1211, a local
1exposition district created under subch. II of ch. 229, a local cultural arts district
2created under subch. V of ch. 229, a redevelopment authority under s. 66.1333 or a
3community development authority under s. 66.1335 shall make an order providing
4for the laying out, relocation and improvement of the public highway, street, alley,
5storm and sanitary sewers, watercourses, water transmission and distribution
6facilities, mass transit facilities, airport, or other transportation facilities, gas or
7leachate extraction systems to remedy environmental pollution from a solid waste
8disposal facility, housing project, redevelopment project, cultural arts facilities,
9exposition center or exposition center facilities which shall be known as the
10relocation order. This order shall include a map or plat showing the old and new
11locations and the lands and interests required. A copy of the order shall, within 20
12days after its issue, be filed with the county clerk of the county wherein the lands are
13located or, in lieu of filing a copy of the order, a plat may be filed or recorded in
14accordance with s. 84.095.
AB75-SSA1,410,216
32.07
(2) The petitioner shall determine necessity if application is by the state
17or any commission, department, board or other branch of state government or by a
18city, village, town, county, school district, board, commission, public officer,
19commission created by contract under s. 66.0301, joint local water authority under
20s. 66.0823,
transit authority created under s. 66.1039, redevelopment authority
21created under s. 66.1333, local exposition district created under subch. II of ch. 229,
22local cultural arts district created under subch. V of ch. 229, housing authority
23created under ss. 66.1201 to 66.1211 or for the right-of-way of a railroad up to 100
24feet in width, for a telegraph, telephone or other electric line, for the right-of-way
1for a gas pipeline, main or service or for easements for the construction of any
2elevated structure or subway for railroad purposes.
AB75-SSA1,410,155
34.05
(1) Except as provided in sub. (4), the The governing board of each public
6depositor shall, by resolution, designate one or more public depositories, organized
7and doing business under the laws of this state or federal law and located in this
8state, in which the treasurer of the governing board shall deposit all public moneys
9received by him or her and specify whether the moneys shall be maintained in time
10deposits subject to the limitations of s. 66.0603 (1m), demand deposits, or savings
11deposits and whether a surety bond or other security shall be required to be
12furnished under s. 34.07 by the public depository to secure the repayment of such
13deposits. A designation of a public depository by the governing board shall be a
14designation of the public depository for all treasurers of the governing board and for
15all public depositors for which each treasurer shall act.