281.36(3m)(d)(d) Additional information requested. If the department determines that the application is incomplete, the department shall notify the applicant in writing and may make only one request for additional information during the 30-day period specified in par. (c). Within 10 days after receiving all of the requested information from the applicant, the department shall notify the applicant in writing as to whether the application is complete. The date on which the 2nd notice under this paragraph is sent shall be set as the date of closure for purposes of par. (g) 1. The department may request additional information from the applicant to supplement the application, but the department may not request items of information that are outside the scope of the original request unless the applicant and the department both agree. A request for any such additional information may not affect the date of closure. 281.36(3m)(e)(e) Specificity of notice; limits on information. Any notice stating that an application has been determined to be incomplete or any other request for information that is sent under par. (d) shall state the reason for the determination or request and the specific items of information that are still needed. 281.36(3m)(f)(f) Failure to meet time limits. If the department fails to meet the 30-day time limit under par. (c) or 10-day time limit under par. (d), the application shall be considered to have a date of closure that is the last day of that 30-day or 10-day time period for purposes of par. (g) 1. 281.36(3m)(g)1.1. Within 15 days after the date of closure, as determined under par. (c) or (d), the department shall provide notice of pending application to interested members of the public. If the applicant has requested a public informational hearing as part of the submitted application, a notice of the public hearing shall be part of the notice of pending application. 281.36(3m)(g)2.2. If the notice of pending application does not contain a notice of public informational hearing, any person may request a public informational hearing in writing or the department may decide to hold a public informational hearing with or without a request being submitted if the department determines that there is a significant public interest in holding a hearing. 281.36(3m)(h)(h) Request for hearing. A request for a public informational hearing under par. (g) 2. must be submitted to the department or the department’s decision to hold a public informational hearing must occur within 20 days after the department provides the notice of pending application. The department shall provide notice of public informational hearing within 15 days after the request for the public hearing is submitted or the department makes its decision to hold a public informational hearing. 281.36(3m)(i)(i) Decision. Within 20 days after the period for public comment under par. (j) has ended or if no public informational hearing is held, within 30 days after the 30-day comment period under par. (j) has ended, the department shall render a decision issuing or denying the wetland individual permit that is the subject of the application submitted under par. (a). If the decision issued by the department under this paragraph is a denial, the department shall include in the decision the specific grounds and reasons as to how the applicable provisions of this section were not met. If the denial is based on an incomplete application, the department shall inform the applicant of the areas of the application that were incomplete. 281.36(3m)(j)1.1. The department shall provide a period for public comment after the department has provided a notice of pending application under par. (g) during which time any person may submit written comments with respect to the application for a wetland individual permit. The department shall retain all of the written comments submitted during this period and shall consider all of the comments in rendering a decision on the application. The period for public comment shall end on the 30th day following the date on which the department provides the notice of pending application except as provided in subd. 2. 281.36(3m)(j)2.2. If a public informational hearing is held, the period for public comment shall end on the 10th day following the date on which the hearing is completed. 281.36(3n)(a)(a) Review limits. For the purpose of issuing a wetland individual permit, during the period between the date on which the application under sub. (3m) (a) is submitted and the date on which a decision under sub. (3m) (i) is rendered, the department shall conduct its review under this subsection. The department shall review the analysis of practicable alternatives presented in the application under sub. (3m) (b). The department shall limit its review of practicable alternatives as follows: 281.36(3n)(a)1.1. The department shall limit its review to those practicable alternatives that are located at the site of the discharge and that are located adjacent to that site if the applicant has demonstrated any of the following: 281.36(3n)(a)1.a.a. That the proposed project causing the discharge will result in a demonstrable economic public benefit. 281.36(3n)(a)1.b.b. That the proposed project is necessary for the expansion of an existing industrial, commercial, agricultural, or aquacultural facility that is in existence at the time the application is submitted. 281.36(3n)(a)1.c.c. That the proposed project will occur in an industrial park that is in existence at the time the application is submitted. 281.36(3n)(a)2.2. Except as provided in par. (am), the department shall limit its review to those practicable alternatives that are located on the property owned by the applicant for a project involving fewer than 2 acres of wetland if the project is limited to one of the following: 281.36(3n)(a)2.a.a. The construction or expansion of a single-family home and attendant features. 281.36(3n)(a)3.3. The department shall limit its review to those practicable alternatives that are consistent with the overall purpose and scope of the project. The department shall impose a level of scrutiny and require an applicant to provide an amount of information that is commensurate with the severity of the environmental impact of the project, as determined by the department. 281.36(3n)(am)(am) Exception to review limit. A lot created as part of a subdivision, land division, or other development that is initiated after July 1, 2012, is not eligible for the limited review under par. (a) 2. 281.36(3n)(b)(b) Factors used in review. In its review under par. (a), the department shall consider all of the following factors when it assesses the impacts to wetland functional values: 281.36(3n)(b)1.1. The direct impacts of the proposed project to wetland functional values. 281.36(3n)(b)2.2. The cumulative impacts attributable to the proposed project that may occur to wetland functional values based on past impacts or reasonably anticipated impacts caused by similar projects in the area affected by the project. 281.36(3n)(b)3.3. Potential secondary impacts of the proposed project to wetland functional values. 281.36(3n)(b)4.4. The impact on functional values resulting from the mitigation that is required under sub. (3r). 281.36(3n)(b)5.5. The net positive or negative environmental impact of the proposed project.