283.16(3)(cm)(cm) If the department of administration decides under par. (c) that the determination remains accurate, the department of natural resources shall decide whether it is appropriate to apply more stringent effluent limitations than those in sub. (6) (a) to all point sources or to any category of point sources, based on the availability and cost effectiveness of technology for compliance and, if so, specify those more stringent effluent limitations based on the report under par. (a).
283.16(3)(d)(d) The department of administration shall provide public notice of its preliminary decisions under par. (c) no later than the 60th day after preparing the report under par. (a) and shall provide the opportunity for public comment on the decisions for at least 30 days following the public notice.
283.16(3)(e)(e) The department of administration shall consider any public comments in making its final decisions under par. (c) and shall make the final decisions no later than the 30th day after the end of the public comment period.
283.16(3)(f)(f) The department of administration shall send a notice that describes its final decisions under par. (c) to the legislative reference bureau for publication in the administrative register.
283.16(3)(g)(g) If the department of administration decides under par. (c) that the determination described in that paragraph remains accurate, the department of natural resources shall seek aproval from the federal environmental protection agency under 40 CFR 131.21 for renewal of the variance under this section.
283.16(3m)(3m)Highest attainable condition review.
283.16(3m)(a)(a) Every 5 years after the variance under this section is approved by the federal environmental protection agency, the department shall, as part of the review required by 40 CFR 131.14 (b) (1) (v), review the interim effluent limitations under sub. (6) (a), or any other effluent limitations that are in effect as a result of a previous review under this subsection or sub. (3), and determine whether they are consistent with the highest attainable condition for the point sources and categories of point sources that are eligible for the variance under this section. In conducting this review, the department shall use all existing and readily available information. The department shall hold a public hearing in order to receive additional information and public comment. The department shall publish notice of the hearing on the department’s Internet site at least 45 days before the hearing date.
283.16(3m)(b)(b) The department shall submit the results of a review under this subsection to the federal environmental protection agency within 30 days after determining that the review under par. (a) has been completed.
283.16(3m)(c)(c) If the department does not conduct a review within the time specified under par. (a), the variance under this section will cease to be available until the department completes the review and submits the results of the review to the federal environmental protection agency.
283.16(3m)(d)(d) If the department does not submit the results of a review to the federal environmental protection agency within the time specified under par. (b), the variance under this section will cease to be available until the department submits the results of the review to the federal environmental protection agency.
283.16(3m)(e)(e) In addition to the review under par. (a), at the time the variance under this section is initially approved for a point source, and at the time the source’s permit is reissued, modified, or revoked and reissued, the department may review the interim effluent limitations under sub. (6) (a), or any other effluent limitations that are in effect as a result of a previous review under this subsection or sub. (3), and determine whether they are consistent with the highest attainable condition for the point source.
283.16(4)(4)Availability of variance.
283.16(4)(a)(a) When a determination under sub. (2) (a) that attaining the water quality standard for phosphorus through compliance with water quality based effluent limitations by point sources that cannot achieve compliance without major facility upgrades is not feasible and approval of the variance under this section by the federal environmental protection agency are in effect, a permittee is eligible for a variance to the water quality standard for phosphorus for an existing source if all of the following apply:
283.16(4)(a)1.1. The determination applies to the existing source.
283.16(4)(a)2.2. Subject to par. (am) 1., the permittee certifies that the existing source cannot achieve compliance with the water quality based effluent limitation for phosphorus without a major facility upgrade.
283.16(4)(a)3.3. The permittee agrees to comply with the requirements under sub. (6).
283.16(4)(am)(am)
283.16(4)(am)1.1. The department shall approve an application for a variance if the requirements in pars. (a) and (b) are complied with, unless the department determines that the certification under par. (a) 2. is substantially inaccurate.
283.16(4)(am)2.2. The department shall act on an application for a variance under this section no later than the 30th day after the day on which the department receives the application for the variance.
283.16(4)(am)3.3. If the department does not act on the application for a variance by the deadline under subd. 2., the application is approved.
283.16(4)(b)(b) A permittee may apply for the variance under this section in any of the following ways:
283.16(4)(b)1.1. By requesting the variance in the application for reissuance of the permit.
283.16(4)(b)2.2. By requesting the variance within 60 days after the department reissues or modifies the permit to include a water quality based effluent limitation for phosphorus.
283.16(4)(b)3.3. If the department issued a permit to the permittee before April 25, 2014, that includes a water quality based effluent limitation for phosphorus, by requesting a modification of the permit.
283.16(4)(b)4.4. If the department issued a permit to the permittee before April 25, 2014, that includes a water quality based effluent limitation for phosphorus and that requires the permittee to submit to the department options for complying with the water quality based effluent limitation, by submitting a request for the variance as a compliance option.
283.16(4)(c)(c) After an application for a variance is submitted to the department under par. (b) 2., 3., or 4., and until the last day for seeking review of the department’s final decision on the application or a later date fixed by order of the reviewing court, the water quality based effluent limitation for phosphorus and any corresponding compliance schedule are not effective. All other provisions of the permit continue in effect except those for which a petition for review has been submitted under s. 283.63.
283.16(4)(d)(d) Notwithstanding sub. (3m) (c) and (d), the variance under this section remains in effect for an approved point source until the point source’s permit is reissued, modified, or revoked and reissued.
283.16(4)(e)(e) Notwithstanding s. 227.42, there is no right to a hearing under this subsection.
283.16(4)(f)(f) If the department approves a variance under this section and the department issues a modified water quality based effluent limitation under s. 283.63 for phosphorus, the permittee shall comply with the least stringent of the 2 effluent limitations.