196.485(2)(b)(b) By June 30, 2000, the commission shall, except as provided in par. (bm), order each transmission utility in this state that is a public utility to identify and separately account for the cost of retail transmission service and to take all retail transmission service from an independent system operator or independent transmission owner.
196.485(2)(bm)(bm) The commission may issue an order under par. (b) after June 30, 2000, if the commission determines that a later date is necessary due to circumstances beyond the control of a transmission utility, including regulatory delays at the commission or applicable federal agency.
196.485(2)(bx)(bx) If the Midwest system operator fails to commence operations or ceases operations, the requirements of this section that apply to the Midwest independent system operator shall apply to any other independent system operator or regional transmission organization that is authorized under federal law to operate in this state. The commission shall require that any transfer of transmission facilities to such independent system operator or regional transmission organization satisfies the requirements of this section.
196.485(2)(c)(c) The commission has jurisdiction to do all things necessary and convenient to enforce the requirements of this section.
196.485(2)(d)(d) The commission shall determine each of the following:
196.485(2)(d)1.1. The date on which the transmission company begins operations.
196.485(2)(d)2.2. Whether the Midwest independent system operator has begun operations and the date on which such operations have begun.
196.485(3)(3)Independent system operator and independent transmission owner duties.
196.485(3)(a)(a) If an independent system operator that has control over transmission facilities in this state determines that there is a need for additional transmission facilities in this state, the independent system operator shall order any transmission utility that has transferred control over transmission facilities to the independent system operator to, subject to the requirements of ss. 196.49 and 196.491 (3), expand the portion of the electric transmission system that is in this state and under the control of the independent system operator or construct additional transmission facilities in that portion of the transmission system. An independent system operator may issue an order under this paragraph only if a transmission utility that is subject to the order is reasonably compensated for the costs incurred in complying with the order.
196.485(3)(b)(b) If an independent transmission owner determines that there is a need for additional transmission facilities in a portion of the electric transmission system of this state that consists of transmission facilities the interest in which has been divested to the independent transmission owner by a transmission utility, the independent transmission owner shall, subject to the requirements of ss. 196.49 and 196.491 (3), expand that portion of the electric transmission system or construct additional transmission facilities in that portion.
196.485(3)(c)(c) An independent transmission owner or an independent system operator shall operate transmission facilities over which it has control in a manner that does each of the following:
196.485(3)(c)1.1. To the maximum extent practicable, eliminates advantages in electric generation, wholesale and retail markets that are otherwise related to ownership, control or operation of transmission facilities over which it has control.
196.485(3)(c)2.2. Satisfies the reasonable needs of transmission users in this state for reliable, low-cost and competitively priced electric service.
196.485(3m)(3m)Transmission company.
196.485(3m)(a)(a) Duties.
196.485(3m)(a)1.1. The transmission company shall do each of the following:
196.485(3m)(a)1.a.a. Apply for any approval under state or federal law that is necessary for the transmission company to begin operations no later than January 1, 2001.
196.485(3m)(a)1.b.b. Subject to any approval required under state or federal law, contract with each transmission utility that has transferred transmission facilities to the transmission company for the transmission utility to provide reasonable and cost-effective operation and maintenance services to the transmission company during the 3-year period after the transmission company first begins operations. The transmission company and a transmission utility may, subject to any approval required under federal or state law, agree to an extension of such 3-year period.
196.485(3m)(a)1.c.c. Assume the obligations of a transmission utility that has transferred ownership of its transmission facilities to the transmission company under any agreement by the transmission utility to provide transmission service over its transmission facilities or credits for the use of transmission facilities, except that the transmission company may modify such an agreement to the extent allowed under the agreement and to the extent allowed under state or federal law.
196.485(3m)(a)1.d.d. Apply for membership in the Midwest independent system operator as a single zone for pricing purposes that includes the transmission area and, upon a determination by the commission under sub. (2) (d) that the Midwest independent system operator has begun operations, transfer operational control of the transmission company’s transmission facilities to the Midwest independent system operator.
196.485(3m)(a)1.e.e. Except as provided under par. (b) 3., remain a member of the Midwest independent system operator, or any independent system operator or regional transmission organization that has been approved under federal law to succeed the Midwest independent system operator, for at least the 6-year transition period that is specified in the agreement conditionally approved by the federal energy regulatory commission that establishes the Midwest independent system operator.
196.485(3m)(a)1.f.f. Subject to subd. 4., elect to be included in a single zone for the purpose of any tariff administered by the Midwest independent system operator.
196.485(3m)(a)2.2. The transmission company may not do any of the following:
196.485(3m)(a)2.a.a. Sell or transfer its assets to, or merge its assets with, another person, unless the assets are sold, transferred or merged on an integrated basis and in a manner that ensures that the transmission facilities in the transmission area are planned, constructed, operated, maintained and controlled as a single transmission system.
196.485(3m)(a)2.b.b. Bypass the distribution facilities of an electric utility or provide service directly to a retail customer or member.
196.485(3m)(a)2.c.c. Own electric generation facilities or sell, market or broker electric capacity or energy in a relevant wholesale or retail market as determined by the commission, except that, if authorized or required by the federal energy regulatory commission, the transmission company may procure or resell ancillary services obtained from 3rd parties, engage in redispatch activities that are necessary to relieve transmission constraints or operate a control area.
196.485(3m)(a)3.3. Notwithstanding subd. 1. a., the transmission company may not begin operations until it provides an opinion to the commission from a nationally recognized investment banking firm that the transmission company is able to finance, at a reasonable cost, its start-up costs, working capital and operating expenses and the cost of any new facilities that are planned.
196.485(3m)(a)4.4. If the transmission charges or rates of any transmission utility in the transmission area are 10 percent or more below the average transmission charges or rates of the transmission utilities in the transmission area on the date, as determined by the commission, that the last public utility affiliate files a commitment with the commission under sub. (5) (a) 2., the transmission company shall, after consulting with each public utility affiliate that has filed a commitment under sub. (5) (a) 2., prepare a plan for phasing in a combined single zone rate for the purpose of pricing network use by users of the transmission system operated by the Midwest independent system operator and shall seek plan approval by the federal energy regulatory commission and the Midwest independent system operator. A plan under this subdivision shall phase in an average-cost price for the combined single zone in equal increments over a 5-year period, except that, under the plan, transmission service shall be provided to all users of the transmission system on a single-zone basis during the phase-in period.
196.485(3m)(b)(b) Powers. The transmission company may do any of the following: