295.57(8)(8)Deadline for acting on other approvals.
295.57(8)(a)(a) Except as provided in par. (c), if an applicant files an application for an approval other than a mining permit no later than 60 days after the day on which the application for the mining permit is administratively complete under sub. (2) or more than 60 days after that day but in time to allow the application to be considered at the public informational hearing for the mining permit under sub. (5), the department shall approve the application, and issue the approval, or deny the application no later than the deadline under sub. (7) (a), including any extension agreed to by the applicant.
295.57(8)(b)(b)
295.57(8)(b)1.1. If an applicant files an application for an approval other than a mining permit too late to allow the application to be considered at the public informational hearing for the mining permit under sub. (5) but before the department issues the decision to grant or deny the application for the mining permit, the application for the approval is considered to be complete on the 30th day after the department receives the application, unless, before that day, the department provides the applicant with written notification that the application is not complete, stating the reason for the determination and describing the specific information necessary to make the application complete. If the department provides such a notice, the applicant shall supplement the application by providing the specified information. The application is considered to be complete when the applicant provides the information.
295.57(8)(b)2.2. Except as provided in subd. 3., the department shall approve the application for an approval described in subd. 1., and issue the approval, or deny the application after the separate public informational hearing for the approval required under sub. (5) and no later than 75 days after the application for the approval is considered to be complete under subd. 1.
295.57(8)(b)3.3. Except as provided in par. (c), the department shall approve or deny the application for an approval described in subd. 1. that is an individual permit for which federal law requires the opportunity for public comment or the ability to request a public hearing prior to issuance of the approval after the separate public informational hearing required for the approval under sub. (5) and no later than 180 days after the application is considered to be complete under subd. 1.
295.57(8)(c)(c) The deadlines in pars. (a) and (b) do not apply to the application for an air pollution control permit under s. 285.62 for which the department receives an objection from the federal environmental protection agency under s. 285.62 (6).
295.57(8)(d)(d) The department shall incorporate an approval other than a mining permit into a single document with the mining permit, unless the application for the approval was filed more than 60 days after the day on which the application for the mining permit is administratively complete under sub. (2).
295.57(8m)(8m)Submission of technical review to Great Lakes regional body. If an applicant files an application under s. 281.346 for an approval for a withdrawal of surface water or groundwater that is subject to regional review or council approval, the department shall provide its technical review, as defined in s. 281.346 (1) (u), to the regional body, as defined in s. 281.346 (1) (q), no later than 90 days after the applicant files the application for the approval.
295.57(9)(9)Applicable procedure.
295.57(9)(a)(a) The provisions of this section and ss. 295.58 (5) and (6) and 295.77 concerning public notice, comment, and hearing; issuance of department decisions; effective date of department decisions; and review of department decisions; and the duration of approvals apply to any approval for which the application is filed before the department issues the decision to grant or deny the application for the mining permit, notwithstanding any provisions related to those matters in s. 44.40 or 169.25, subch. I or VI of ch. 77, ch. 23, 29, 30, 31, 169, 281, 283, 285, 289, or 291, or rules promulgated under those provisions, except as provided in s. 281.343 (7r) and except that if a withdrawal of surface water or groundwater is subject to regional review or council approval under s. 281.346, the applicable provisions related to regional review or council approval apply.
295.57(9)(b)(b) The provisions of ss. 295.58 (5) and (6) and 295.77 concerning review of department decisions and the duration of department decisions apply to any approval for which the application is filed after the department issues the mining permit, notwithstanding any provisions related to those matters in s. 44.40 or 169.25, subch. I or VI of ch. 77, ch. 23, 29, 30, 31, 169, 281, 283, 285, 289, or 291, or rules promulgated under those provisions, except as provided in s. 281.343 (7r).
295.57 HistoryHistory: 2013 a. 1; 2015 a. 196.
295.58295.58Mining; department grant or denial of permit.
295.58(1)(1)Criteria for approval.
295.58(1)(a)(a) Except as provided in sub. (2) and except with respect to property specified in s. 41.41 (11), the department shall issue a mining permit if it finds all of the following:
295.58(1)(a)1.1. That the mining plan and reclamation plan are reasonably certain to result in reclamation of the mining site consistent with this subchapter.
295.58(1)(a)2.2. That the waste site feasibility study and plan of operation complies with s. 295.51.
295.58(1)(a)3.3. That the applicant has committed to conducting the proposed mining in compliance with the mining permit and any other approvals issued for the mining.
295.58(1)(a)3m.3m. That the proposed mining is likely to meet or exceed the requirements of any municipal floodplain zoning ordinance applicable to the proposed mining under s. 295.607 (3) to the extent that the ordinance has not been made inapplicable to the proposed mining by a local agreement under s. 295.443 (1m).
295.58(1)(a)4.4. That the proposed mining is reasonably certain not to result in substantial adverse impacts to public health, safety, or welfare.
295.58(1)(a)5.5. That the proposed mining will result in a net positive economic impact in the area reasonably expected to be most impacted by the mining.
295.58(1)(a)6.6. That the applicant has applied for all necessary zoning approvals applicable to the proposed mining.
295.58(1)(b)(b) The department shall approve or deny an application for a mining permit in writing and shall include the reasons for its decision with clarity and in detail. The department may modify the applicant’s proposed mining plan, reclamation plan, or mining waste site feasibility study and plan of operation in order to meet the requirements of this subchapter, and, as modified, approve the application. The approval of the application for a mining permit constitutes the approval of the mining plan, reclamation plan, and waste site feasibility study and plan of operation. In its decision on the application for a mining permit, the department shall include a final decision on compliance with s. 1.11 and the requirements of s. 295.53, discussing all of the following:
295.58(1)(b)1.1. Whether the department has considered the environmental impact statement and comments received on it.
295.58(1)(b)2.2. Whether the department has complied with ss. 1.11 and 295.53.
295.58(1)(b)3.3. Whether, consistent with social, economic, and other essential considerations, the department has adopted all practicable means within its authority to avoid or minimize any harm to the environment and, if not, why not.
295.58(2)(2)Criteria for denial. The department shall deny the mining permit if it finds any of the following:
295.58(2)(a)(a) That the site is unsuitable for mining.