LRB-3451/1
MDK/JK/RNK:kmg:pg
2003 - 2004 LEGISLATURE
October 29, 2003 - Introduced by Representatives Jensen, Steinbrink, J.
Fitzgerald, Nischke, Pope-Roberts, Gottlieb, J. Lehman, Nass, Zepnick,
Rhoades, Taylor, Weber, Ainsworth, Hundertmark, Hines, Kreibich,
McCormick, Musser, Pettis, Stone, Honadel
and Albers, cosponsored by
Senators Cowles, Leibham, Stepp, Kanavas, Hansen, Panzer, Erpenbach,
Darling
and Plale. Referred to Committee on Energy and Utilities.
AB632,1,12 1An Act to repeal 196.491 (3) (g) 1m.; to renumber 85.02 and 196.491 (3) (h); to
2renumber and amend
30.025 (1), 196.491 (3) (g) 1. and 196.491 (4) (c); to
3amend
15.795 (1), 16.969 (4), 30.02 (1), 30.02 (2), 30.025 (title), 30.025 (2),
430.025 (3) (intro.), 30.025 (4), 66.0119 (1) (a), 79.04 (7) (c) 1m., 91.75 (4), 196.025
5(2) (intro.), 196.491 (3) (a) 1., 196.491 (3) (a) 3. a., 196.491 (3) (b), 196.491 (3) (d)
6(intro.), 196.491 (3) (e), 196.491 (3) (gm) and 196.491 (3) (j); and to create 1.12
7(6), 23.09 (22m), 30.025 (1b), 30.025 (1e), 30.025 (1m), 30.025 (1s) (title), 30.025
8(1s) (b), 30.025 (2g), 30.025 (2s), 30.025 (3m), 30.206 (1m), 79.04 (6) (c) 3., 79.04
9(7) (d), 85.02 (2), 196.02 (5m), 196.025 (1m), 196.025 (2m), 196.20 (7), 196.491
10(3) (ge), 196.491 (3b), 196.491 (4) (c) 2., 196.491 (4) (c) 3. and 196.491 (6) (title)
11of the statutes; relating to: construction of electric generating facilities and
12transmission lines, and granting rule-making authority.
Analysis by the Legislative Reference Bureau
This bill does all of the following: 1) changes requirements for the Public
Service Commission (PSC) to approve the construction of electric generating

facilities and transmission lines; 2) changes requirements for the Department of
Natural Resources (DNR) to issue permits that are required for the construction of
certain utility projects; 3) changes requirements for the PSC and DNR to consider
the environmental impacts of such projects; 3) declares a state policy regarding the
siting of electric transmission facilities; and 4) modifies utility aid payments.
PSC requirements
Under current law, with certain exceptions, a person may not begin the
construction of certain electric generating facilities or high-voltage transmission
lines before the PSC has issued a certificate of public convenience and necessity to
the person. A "high-voltage transmission line" is defined as a line of more than one
mile in length that is designed to operate at 100 or more kilovolts. Current law
specifies the procedure that a person must follow to apply for a certificate to construct
electric generating facilities or high-voltage transmission lines. In addition, current
law specifies the findings that the PSC must make before issuing a certificate.
The bill changes an exemption under current law that applies to the
construction of certain high-voltage transmission lines. Under current law, a
certificate is not required if the line operates at 230 or less kilovolts, and if all
construction activity takes place entirely within an existing electric transmission
right-of-way. The bill changes the exemption to apply to a line that operates at 345
or less kilovolts. The bill also provides that construction of a line that qualifies for
the exemption may proceed even if it is prohibited by a local ordinance.
The bill also creates an expedited procedure for obtaining a certificate for
constructing a high-voltage transmission line. The procedure applies only if the
construction is limited to adding conductors to existing transmission poles or towers
and if all construction activity takes place entirely within an existing electric
transmission right-of-way. The PSC must promulgate rules for applying for a
certificate under the expedited procedure. If the PSC receives an application that
complies with the rules, the PSC must, as soon as practicable, notify the applicant
that the PSC has received a complete application. After a complete application is
received, the applicant is considered to have been issued a certificate, unless the PSC
notifies the applicant within 30 days after the PSC receives a complete application
that the public interest requires the applicant to obtain the PSC's approval for the
construction. If the PSC makes such a notification, the bill requires the applicant
to obtain a certificate that is required under current law for certain public utility
construction projects, rather than the certificate of public convenience and necessity
that is described above.
DNR requirements
In addition, the bill changes requirements under current law that apply to an
application for a certificate to construct an electric generating facility or a
high-voltage transmission line that is subject to regulatory approval in another
state. Under current law, the PSC must complete action on an application within 180
days after the application is complete. (Current law also provides for an extension
of this deadline under certain circumstances.) However, current law creates an
exemption from the deadline if another state is also taking action on such a facility
or line. This bill eliminates the exemption to the deadline. However, the bill also

allows the PSC to reconsider an application for a certificate if another state considers
certain information or issues in its proceedings that the PSC did not consider and to
revoke or amend the certificate.
The bill also makes the following changes:
1. The bill allows the PSC to use a procedure under current law to obtain an
inspection warrant for the purpose of inspecting property to gather information
related to preparing or reviewing an application for a certificate described above.
The bill specifies that the information that may be gathered includes any
information necessary to evaluate environmental features or effects that are
relevant to such an application.
2. The bill allows a county, town, village, or city that receives certain
distributions that are funded with fees paid by persons that construct high-voltage
transmission lines to use the distributions for any purpose, if the PSC finds that the
purpose is in the public interest. Under current law, such distributions may be used
only for park, conservancy, wetland, or other similar environmental programs.
3. The bill requires a person who applies for a certificate to construct a
high-voltage line to submit a detailed project plan to DNR. Under current law, the
type of plan that a person must submit to DNR for such a line is called an engineering
plan, instead of a project plan.
4. The bill requires a person who applies for a certificate of public convenience
and necessity for certain electric generating facilities or high-voltage transmission
lines to provide a brief description of the anticipated effects of the facility or line on
air and water quality, wetlands, solid waste disposal capacity, and other natural
resources. Current law limits the description to effects on air and water quality.
Generally, under current law, a person proposing to construct a utility facility
in a manner that requires the placement of a structure in navigable waters or that
involves the construction or maintenance of a dam is required to obtain one or more
permits from DNR. Current law requires DNR to hold a public hearing before
granting certain of these permits. Current law also prohibits a person from
discharging dredged or fill material into a nonfederal wetland unless the person is
issued a water quality certification by DNR.
Under current law, electric utilities that propose to construct an electric
generating facility or high-voltage transmission line adjacent to a waterway may
use an optional permit procedure to obtain certain DNR permits. Under that
optional procedure, if the utility must obtain more than one permit from DNR
relating to the placement of structures in navigable waters or the construction or
maintenance of a dam, the utility may, instead of submitting separate applications
for the permits, submit an engineering plan to DNR. If the utility submits an
engineering plan instead of separate applications for permits, DNR is required to
schedule the entire matter for a public hearing, rather than scheduling separate
hearings for each permit application. After the hearing, DNR must grant all of the
necessary permits if certain conditions are met.
This bill provides that a utility facility that is required to obtain a certificate of
public convenience and necessity from the PSC and that is also required to obtain one
or more permits from DNR for the placement of a structure in navigable waters, or

for the construction or maintenance of a dam, or to obtain a water quality
certification for discharging material in a nonfederal wetland, must use a procedure
that requires the utility facility to submit only one application for all of those permits.
Under that procedure, a person proposing to construct a utility facility must first
notify DNR of its intention to file an application. After DNR receives the notice, DNR
must confer with that person and, in cooperation with the PSC, make certain
assessments and analyses concerning the project. The bill provides that once the
application is completed, DNR may schedule the matter for a public hearing. The
hearing may not be conducted as a contested case hearing. In a contested case, all
parties must be given an opportunity for a hearing and must be given the opportunity
to present evidence.
Under the bill, DNR must grant the permits for the utility facility if DNR makes
certain findings, including that the proposal complies with certain environmental
statutes and that it does not unduly affect public rights and interests in navigable
waterways. The bill requires DNR to grant or deny the application within 30 days
of the date on which the PSC issues its decision on the utility's application for a
certificate of public convenience and necessity.
The bill also specifies that as a part of this permit procedure DNR must review
the proposed utility facility to assess whether the location, site, or route is capable
of satisfying conditions for obtaining the required permits from DNR and must
provide this information to the PSC. DNR must also participate in PSC
investigations or proceedings relating to the application for a certificate of public
convenience and necessity for the utility facility. The bill provides that if the PSC
issues the certificate for that utility facility, after considering DNR's participation in
the PSC's proceedings and after considering certain other factors, DNR may not
require the applicant to make any further analysis of utility facility alternatives,
except that DNR may identify adjustments that may be required to address
permitting issues within the location, site, or route for which the certificate is issued.
Under current law, for certain activities affecting navigable waters that are
undertaken by riparian owners, or for activities relating to the construction,
dredging, or enlarging of certain waterways, DNR may issue general permits
authorizing a class of activities. This bill requires DNR to issue a general permit for
the construction of those high-voltage transmission line projects to which the
expedited procedure created in this bill for obtaining a certificate from the PSC
applies.
Environmental impacts
Current law requires state agencies, including the PSC and DNR, to consider
the environmental impacts of proposed actions, including proposals to issue the
certificates, permits, and approvals described above. These requirements were
created by the Wisconsin Environmental Policy Act (WEPA). The PSC and DNR
have promulgated rules for complying with WEPA. Under these rules, the PSC or
DNR must prepare an environmental impact statement (EIS) for major actions that
significantly affect the quality of the human environment and an environmental
assessment (EA) for actions that have the potential to significantly affect the quality

of the human environment. Based on the results of an EA, the PSC or DNR may also
prepare an EIS.
The bill requires the PSC and DNR to coordinate their compliance with WEPA
when the PSC and DNR receive applications for certificates, permits, and approvals
that are required for the construction of electric generating facilities and
high-voltage transmission lines. The bill also requires such coordination when
public utilities that are not telecommunications utilities apply to the PSC for
certificates authorizing other types of construction projects. Such coordination is
also required when a natural gas utility applies to the PSC for a certificate
authorizing a project involving switching sources of natural gas supplies.
Under the bill, if the rules of either the PSC or DNR require the preparation of
an EIS for an application for a certificate, permit, or approval described above, the
PSC and DNR must cooperatively prepare an EIS. If neither agency's rules require
an EIS, but either agency's rules require an EA, the PSC and DNR must
cooperatively prepare an EA. The joint EIS or EA that is required under the bill must
include all of the information necessary for both the PSC and DNR to comply with
WEPA. In addition, the bill does not waive the duty of the PSC or DNR to comply
with WEPA, except that the PSC and DNR are only required to consider the project
that is the subject of the application and one alternative to the project, and that
alternative must be an alternative location, site, or route for the project that is
specified by the person applying for the certificate, permit, or approval. Under
current law, the PSC and DNR must consider more than one alternative under
WEPA. In addition, the bill does not waive any duty of the PSC or DNR to take any
other action required by law regarding the project.
The bill also specifies that the PSC is not required to prepare an EIS for
construction of a high-voltage line that does not require a certificate from the PSC.
As discussed above, this exemption is changed by the bill to apply to certain
construction activities related to high-voltage transmission lines that operate at 345
or less kilovolts. Although an EIS is not required, the bill requires the PSC to prepare
an EA for construction that is subject to the exemption, but only if the PSC's rules
require an EA for the construction.
State policy on siting of electric transmission facilities
Current law makes certain declarations of state energy policy, including goals
for conserving energy and meeting energy demands. This bill declares a new policy
regarding the siting of new electric transmission facilities, including high-voltage
transmission lines. The bill provides that, in the siting of such facilities, it is state
policy to utilize the following corridors in the following order of priority: 1) existing
utility corridors; 2) highway and railroad corridors; 3) recreational trails; and 4) new
corridors. The corridors must be utilized in such a manner to the greatest extent
feasible that is consistent with economic and engineering considerations and
protection of the environment. Also, recreational trails must be utilized to the extent
that facilities may be constructed below ground and do not significantly impact
environmentally sensitive areas.

The bill also directs the PSC, DNR, and Department of Transportation to
implement the policy described above in making all decisions, rules, and orders
regarding the siting of new electric transmission facilities.
Utility aid payment
Under current law, generally, each municipality and county in which a power
production plant is located annually receives utility aid payments based on the net
value of the production plant. Beginning with utility aid payments in 2005, each
municipality and county in which a production plant is located will receive a
payment based on the megawatt capacity of the production plant, if the plant began
operating after December 31, 2003. If a plant is located in more than one
municipality, the payment is divided among the municipalities in which the plant is
located based on the net value of that portion of the plant located in each
municipality. Under this bill, if a plant is located in more than one county, the
payment is divided among the counties in which the plant is located based on the net
value of that portion of the plant located in each county.
Under current law, for production plants that begin operating after December
31, 2003, each municipality and county in which such a production plant is located
may receive an additional utility aid payment based on the production plant's
megawatt capacity if the plant is built on the site of an existing or decommissioned
production plant or on brownfields or if the plant is a baseload electric generating
facility, derives energy from an alternative energy resource, or is a cogeneration
production plant. Under this bill, if such a production plant is located in more than
one municipality or county, the payment is divided among the municipalities or
counties in which the plant is located based on the net value of that portion of the
plant located in each municipality or county.
Under current law, a county or municipality that receives a utility aid payment
based on a cogeneration production plant located in the county or municipality may
not receive a payment based on a production plant that derives energy from an
alternative energy resource and that is located in the county or municipality. Under
this bill, a county or municipality that receives a utility aid payment based on a
cogeneration production plant located in the county or municipality may also receive
a payment based on a production plant that derives energy from an alternative
energy resource, if the production plant that derives energy from an alternative
energy resource is not the cogeneration production plant.
Under this bill, generally, an electric public utility may not recover in rates the
cost of any payments paid to a local unit of government to mitigate the impact of an
electric generating facility on the local unit of government, unless the agreement
providing for the payments is received by the PSC before June 10, 2003, and the PSC
finds the agreement to be reasonable.
For further information see the state and local fiscal estimate, which will be
printed as an appendix to this bill.
The people of the state of Wisconsin, represented in senate and assembly, do
enact as follows:
AB632, s. 1
1Section 1. 1.12 (6) of the statutes is created to read:
AB632,7,72 1.12 (6) Siting of electric transmission facilities. In the siting of new electric
3transmission facilities, including high-voltage transmission lines, as defined in s.
4196.491 (1) (f), it is the policy of this state that, to the greatest extent feasible that
5is consistent with economic and engineering considerations and protection of the
6environment, the following corridors should be utilized in the following order of
7priority:
AB632,7,88 (a) Existing utility corridors.
AB632,7,99 (b) Highway and railroad corridors.
AB632,7,1210 (c) Recreational trails, to the extent that the facilities may be constructed below
11ground and that the facilities do not significantly impact environmentally sensitive
12areas.
AB632,7,1313 (d) New corridors.
AB632, s. 2 14Section 2. 15.795 (1) of the statutes is amended to read:
AB632,7,2215 15.795 (1) Office of the commissioner of railroads. There is created an office
16of the commissioner of railroads which is attached to the public service commission
17under s. 15.03, provided that s. 85.02 (1) does not apply to the office of the
18commissioner of railroads. The commissioner of railroads shall have expertise in
19railroad issues and may not have a financial interest in a railroad, as defined in s.
20195.02 (1). The commissioner may not serve on or under any committee of a political
21party. The commissioner shall hold office until a successor is appointed and
22qualified.
AB632, s. 3 23Section 3. 16.969 (4) of the statutes is amended to read:
Loading...
Loading...