SB1,179,2424 3. Tests for hydrogen ion concentration (pH).
SB1,179,2525 4. Tests for chlorine residual.
SB1,180,1
15. Tests for temperature.
SB1,180,4 2295.643 Mining waste site monitoring. (1) General. The department may
3require the monitoring of groundwater, surface water, leachate, or other physical
4features associated with a mining waste site.
SB1,180,10 5(2) Physical features. The department may require the monitoring of air
6quality, berms, embankments, vegetation growth, and drainage control structures
7associated with the mining waste site. The department may require monitoring of
8other chemical or biological conditions, if the department determines that the
9monitoring is necessary to assess the impact of the mining waste site on critical
10aquatic and terrestrial ecosystems.
SB1,180,15 11(3) Monitoring wells and other devices. (a) The department shall require
12the installation of groundwater monitoring wells at a mining waste site. The
13department may require installation of leachate monitoring wells, lysimeters,
14moisture probes, and similar devices and associated water quality sampling and
15analysis programs to detect the effects of leachate on groundwater.
SB1,180,2116 (b) The department shall determine the required number of groundwater
17monitoring wells based on the size of the mining waste site, the design of the mining
18waste site, the types of mining waste, and the hydrologic and geologic setting of the
19mining waste site. The department shall ensure that the number of wells is adequate
20to yield samples representative of the groundwater quality both up gradient and
21down gradient of the mining waste site.
SB1,180,2422 (c) An operator shall construct all monitoring wells in accordance with ch. NR
23141, Wis. Adm. Code, and in such a manner as to prevent, to the extent practicable,
24the exchange of water between aquifers.
SB1,181,4
1(4) Destruction of monitoring devices. (a) If for any reason a monitoring well
2or other monitoring device associated with a mining waste site is destroyed or
3otherwise fails to function properly, the operator shall notify the department in
4writing within 5 days of discovering the destruction or malfunction.
SB1,181,85 (b) The operator shall either restore the monitoring well or other device or
6properly abandon it and replace it with a functioning device within 60 days of
7notifying the department under par. (a) unless the department notifies the operator
8otherwise in writing within 30 days of receiving notice from the operator.
SB1,181,13 9(5) Sampling other wells. The department may require an operator to sample
10public or private wells as part of a regular monitoring program or to determine the
11extent of groundwater contamination associated with a mining waste site. If the
12owner of a well does not authorize access for sampling, the operator shall promptly
13notify the department.
SB1,181,22 14(6) Required monitoring and analysis. (a) An operator shall monitor
15groundwater at locations identified in the waste site feasibility study and plan of
16operation on a quarterly basis, during March, June, September, and December,
17unless the department agrees to an alternate schedule. The department may base
18an alternate schedule on the hydrogeologic system's characteristics, such as flow
19velocity and stratigraphy, and on fluctuations in quality as determined through
20background water quality or baseline water quality sampling and mining waste
21type. The operator shall analyze for the parameters listed in the approved waste site
22feasibility study and plan of operation.
SB1,181,2523 (b) An operator shall use the methods for groundwater and surface water
24sample collection, preservation, and analysis that are specified in the approved
25mining waste site facility study and plan of operation.
SB1,182,2
1(7) Water elevation measurements. The operator shall make water elevation
2measurements on a quarterly basis.
SB1,182,10 3(8) Operations report. The department may require an operator to submit an
4operations report to assess the effectiveness and environmental acceptability of
5mining waste site operations. The operator may include in the report a discussion
6of confinement of the active fill area and an analysis of leachate and other
7monitoring, surface water control and erosion control, revegetation, settlement,
8volume of the mining waste site utilized, leachate quantity and quality, slope
9stability, equipment performance, volume and type of waste disposed of, and other
10relevant parameters.
SB1,182,13 11(9) Reports of monitoring data. The operator shall forward to the department,
12within 60 days after sampling, 3 copies of the monitoring data required by this
13section to be collected during each quarter.
SB1,182,15 14295.645 Groundwater quality, monitoring, and response. (1)
15Definitions. In this section:
SB1,182,1816 (a) "Alternative concentration limit" means the concentration of a substance
17in groundwater established by the department to replace a groundwater quality
18standard when the department grants an exemption.
SB1,182,2119 (b) "Statistically significantly different" means an amount of change
20determined by the use of statistical tests for measuring significance at the 95 percent
21confidence level.
SB1,183,4 22(2) Design management zone. (a) Notwithstanding the rule-making authority
23in s. 160.21 (2) and except as provided under par. (b), for the purposes of ch. 160, the
24horizontal distance to the boundary of the design management zone for a mining
25operation is 1,200 feet from the limits of the engineered structures of the mining

1waste site, including any wastewater and sludge storage or treatment lagoons, the
2edge of the mine, and the adjacent mine mill and ferrous mineral processing facilities
3or at the boundary of the property owned or leased by the applicant or on which the
4applicant holds an easement, whichever distance is less.
SB1,183,115 (b) When issuing or modifying a mining permit or issuing or reissuing any other
6approval, the department may expand the design management zone by a horizontal
7distance of up to an additional 1,200 feet in any direction as provided in this
8paragraph, but not beyond the boundary of the property owned or leased by the
9applicant or on which the applicant holds an easement. The department may not
10expand the design management zone unless the applicant demonstrates all of the
11following:
SB1,183,1412 1. That preventive action limits and enforcement standards or alternative
13concentration limits cannot be met at the boundary of the design management zone
14if it is not expanded.
SB1,183,1715 2. That preventive action limits and enforcement standards or alternative
16concentration limits will be met at the boundary of the expanded design
17management zone.
SB1,183,2218 (c) Notwithstanding the rule-making authority in s. 160.21 (2), for the
19purposes of ch. 160, the vertical distance to the boundary of the design management
20zone for a mining site, including any mining waste site, extends no deeper than 1,000
21feet into the Precambrian bedrock or than the final depth of the mining excavation,
22whichever is greater.
SB1,184,6 23(3) Point of standards application. (a) Any point at which groundwater is
24monitored is a point of standards application to determine whether a preventive
25action limit or an alternative concentration limit to a preventive action limit has been

1attained or exceeded for an activity regulated under a mining permit or another
2approval related to the mining operation. Any of the following is a point of standards
3application to determine whether an enforcement standard or an alternative
4concentration limit to an enforcement standard has been attained or exceeded for an
5activity regulated under a mining permit or another approval related to the mining
6operation:
SB1,184,77 1. Any point of present groundwater use.
SB1,184,98 2. Any point beyond the boundary of the property on which the activity is
9conducted, subject to par. (b).
SB1,184,1110 3. Any point that is within the boundary of the property on which the activity
11is conducted but is beyond the design management zone, subject to par. (b).
SB1,184,1412 (b) No point at a depth of greater than 1,000 feet into the Precambrian bedrock
13or than the final depth of the mining excavation, whichever is greater, is a point of
14standards application under this subsection.
SB1,184,1615 (c) Section 160.21 (2) does not apply to an activity regulated under this
16subchapter.
SB1,184,22 17(4) Change in groundwater quality. If the analysis of samples collected
18through monitoring indicates that the quality of groundwater is statistically
19significantly different from either baseline water quality or background water
20quality and the evaluation of the data shows a reasonable probability that without
21intervention groundwater quality standards or alternative concentration limits will
22be attained or exceeded, the operator shall do all of the following:
SB1,184,2423 (a) Notify the department within 10 days after the operator receives the results
24of the analysis of the samples.
SB1,185,2
1(b) Determine, if possible, the cause of the difference in water quality, such as
2a spill, a design failure, or an improper operational procedure.
SB1,185,43 (c) Determine the extent of groundwater contamination or the potential for
4groundwater contamination.
SB1,185,55 (d) Implement the applicable portions of the approved contingency plan.
SB1,185,25 6(5) Response concerning preventive action limits. In accordance with s. NR
7140.24 (1) to (5), Wis. Adm. Code, the department shall evaluate the range of
8responses proposed by the operator when a preventive action limit or an alternative
9concentration limit to a preventive action limit is attained or exceeded and the
10analysis of samples indicates that the quality of groundwater is statistically
11significantly different from either baseline water quality or background water
12quality at a point of standards application. In designating the appropriate response,
13the department shall evaluate the operator's proposed range of responses, including
14any alternate responses to those identified in s. NR 140.24, Wis. Adm. Code. For any
15alternate responses, the department shall consider the technical and economic
16feasibility of alternate responses, the practicality of stopping the further release of
17the substance, and the risks and benefits of continued mining operations. The
18department shall designate the appropriate response, except that, notwithstanding
19s. 160.21 (3) and the rule-making authority under s. 160.21 (1), the department may
20not prohibit a practice or activity or require closure and abandonment of a mining
21waste site, including any wastewater and sludge storage or treatment lagoon, unless
22it has followed the procedures in s. 295.78 and satisfies the requirements of s. 160.23
23(4) and (6). The department may determine that no response is necessary and that
24an exemption is not required when the requirements of s. NR 140.24 (5) (a) or (b), Wis.
25Adm. Code are met.
SB1,186,15
1(6) Response concerning enforcement standards. (a) In accordance with s.
2NR 140.26 (1) and (2), Wis. Adm. Code, the department shall evaluate the range of
3responses proposed by the operator based on the responses listed in Table 6 of s. NR
4140.26, Wis. Adm. Code, when an enforcement standard or an alternative
5concentration limit to an enforcement standard is attained or exceeded and the
6analysis of samples indicates that the quality of groundwater is statistically
7significantly different from either baseline water quality or background water
8quality at a point of standards application. In designating the appropriate response,
9the department shall evaluate the operator's proposed range of responses against
10those identified in Table 6 of s. NR 140.26, Wis. Adm. Code. The department shall
11designate the appropriate response, except that, notwithstanding ss. 160.21 (3) and
12160.25 (1) (a) and the rule-making authority under s. 160.21 (1), the department may
13not prohibit a practice or activity or require closure and abandonment of a mining
14waste site, including any wastewater and sludge storage or treatment lagoon, unless
15it has followed the procedures in s. 295.78 and all of the following apply:
SB1,186,1616 1. The department bases its decision upon reliable test data.
SB1,186,1917 2. The department determines, to a reasonable certainty, by the greater weight
18of the credible evidence, that no other remedial action would prevent the violation
19of the enforcement standard at the point of standards application.
SB1,186,2120 3. The department establishes the basis for the boundary and duration of the
21prohibition.
SB1,186,2422 4. The department ensures that any prohibition imposed is reasonably related
23in time and scope to maintaining compliance with the enforcement standard at the
24point of standards application.
SB1,187,8
15. If the substance involved is naturally occurring, unless the substance
2involved is carcinogenic, teratogenic, or mutagenic in humans, the department
3considers the existence of the background concentration of the substance in
4evaluating response options to the noncompliance with the enforcement standard or
5alternative concentration limit for that substance and determines that the proposed
6prohibition will result in the protection of or substantial improvement in
7groundwater quality notwithstanding the background concentrations of the
8substance.
SB1,187,149 (b) The department may only require a remedial action to be taken if the
10remedial action is reasonably related in time and scope to the substance, activity, or
11practice that caused the enforcement standard or alternative concentration limit to
12an enforcement standard to be attained or exceeded and the quality of groundwater
13to be statistically significantly different from either baseline water quality or
14background water quality at the point of standards application.
SB1,188,215 (c) If nitrates or any substance of welfare concern attains or exceeds an
16enforcement standard and if the analysis of samples indicates that the quality of
17groundwater is statistically significantly different from either baseline or
18background water quality, then the department shall evaluate whether the
19enforcement standard was attained or exceeded in whole or in part due to high
20background water quality concentrations of the substance and whether the
21additional concentrations represent a public welfare concern before it designates the
22appropriate response and, notwithstanding ss. 160.21 (3) and 160.25 (1) (a) and the
23rule-making authority under s. 160.21 (1), the department may not prohibit a
24practice or activity or require closure and abandonment of a mining waste site,

1including any wastewater and sludge storage or treatment lagoon, unless it has
2followed the procedures in s. 295.78 and par. (a) 1. to 4. apply.
SB1,188,43 (d) If compliance with an enforcement standard is achieved at a point of
4standards application, then sub. (5) applies.
SB1,188,12 5(6m) Mandatory intervention boundary for mining waste site and mine. (a)
6Except as provided under par. (am), the horizontal distance to the mandatory
7intervention boundary for a mining waste site is 300 feet from the outer waste
8boundary or the outer edge of the excavation, unless the boundary of the design
9management zone is within 600 feet of the outer waste boundary or the outer edge
10of the excavation, in which case the mandatory intervention boundary is one-half
11the distance from the outer waste boundary or the outer edge of the excavation to the
12boundary of the design management zone.
SB1,188,1613 (am) The department may reduce the mandatory intervention boundary under
14par. (a) by a horizontal distance of up to 150 feet if the department determines that
15the reduction is necessary to adequately identify and respond to potential
16groundwater quality issues.
SB1,188,2217 (b) An operator shall monitor groundwater quality at locations approved by the
18department along the mandatory intervention boundary, except for any portion of
19the mandatory intervention boundary that is within another mandatory
20intervention boundary, and within the mandatory intervention boundary. When
21approving locations for monitoring, the department shall ensure that duplicative
22monitoring is not required within overlapping mandatory intervention boundaries.
SB1,189,223 (c) 1. Notwithstanding sub. (5), if a preventive action limit or an enforcement
24standard has been exceeded beyond the mandatory intervention boundary, the

1department shall require a response in accordance with s. NR 140.24, Wis. Adm.
2Code, except that s. NR 140.24 (5), Wis. Adm. Code, does not apply.
SB1,189,93 2. If sampling results indicate that an enforcement standard or a preventive
4action limit has been exceeded within, but not beyond, the mandatory intervention
5boundary and a comparison of sampling results to the results of modeling indicates
6that the sampling results are consistent with the design and expected performance
7of the mining waste site, the operator may recommend a no response action, and the
8department may approve a no response action if that is authorized under s. NR
9140.24 (5), Wis. Adm. Code.
SB1,189,11 10(7) Environmental analysis not required. An action under sub. (5) or (6) with
11respect to a specific site does not constitute a major state action under s. 1.11 (2).
SB1,189,15 12(8) Exemptions to groundwater quality standards. When issuing or
13modifying a mining permit or issuing or reissuing any other approval, the
14department may grant an exemption from a groundwater quality standard and
15establish an alternative concentration limit to a groundwater quality standard.
SB1,189,18 16(9) Applicability of other law. Chapter NR 140, Wis Adm. Code, applies to
17mining operations and mining sites, including mining waste sites, only to the extent
18that it does not conflict with this section.
SB1,189,24 19295.65 Successors. (1) When one operator succeeds to the interest of another
20in an uncompleted mining operation by sale, assignment, lease, or otherwise, the
21department shall release the first operator from the duties imposed upon the first
22operator by this subchapter as to the mining operation and transfer the mining
23permit and any approvals under ss. 295.60, 295.605, and 295.61 to the successor
24operator if all of the following apply:
SB1,190,2
1(a) The successor operator agrees to comply with the requirements of this
2subchapter.
SB1,190,63 (b) The successor operator discloses whether it has forfeited any performance
4security because of noncompliance with any mining laws within the previous 10
5years, posts any bond or other security required under s. 295.59, and assumes all
6responsibilities of all applicable approvals granted to the predecessor operator.
SB1,190,8 7(2) The department is not required to prepare an environmental impact
8statement or an environmental assessment for the purposes of this section.
SB1,190,23 9295.66 Cessation of mining or reclamation. If there is a cessation of
10mining or reclamation for 30 days or more that is not set forth in either the mining
11plan or the reclamation plan, the operator shall notify the department of the
12cessation within 48 hours of the cessation of mining and shall begin stabilization of
13the mining site. The department may require the operator to provide technical,
14engineering, and any other information that the operator believes shows that its
15actions to stabilize the mining site are adequate. If the department determines, after
16reviewing the information provided by the operator, that the proposed stabilization
17of the mining site will result in a substantial adverse impact to the environment, the
18department shall order the operator to begin additional measures to protect the
19environment, including, if the cessation is reasonably anticipated to extend for a
20protracted period of time, reclamation according to the reclamation plan or part of
21the reclamation plan. Usual and regular shutdown of operations on weekends, for
22maintenance or repair of equipment or facilities, or for other customary reasons do
23not constitute a cessation of mining.
SB1,191,2 24295.67 Determination of abandonment of mining. (1) Except as provided
25in sub. (2), abandonment of mining occurs if there is a cessation of mining, not set

1forth in an operator's mining plan or reclamation plan or by any other sufficient
2written or constructive notice, extending for more than 6 consecutive months.
SB1,191,3 3(2) Abandonment of mining does not occur if all of the following apply:
SB1,191,54 (a) The cessation of mining is due either to labor strikes or to unforeseen
5developments such as adverse market conditions.
SB1,191,76 (b) The cessation of mining does not continue beyond the time, not to exceed
75 years, specified by the department.
SB1,191,98 (c) The mining site is maintained in an environmentally stable manner during
9the cessation of mining.
SB1,191,1110 (d) The reclamation of the mining site continues according to the reclamation
11plan during the cessation of mining to the extent practicable.
SB1,191,21 12295.68 Certificates of completion and release of security. (1) Upon the
13petition of the operator, but not less than 4 years after notification to the department
14by the operator of the completion of the reclamation plan or not less than one year
15after notification to the department by the operator of the completion of the
16reclamation plan as to a portion of the mining site, if the department finds that the
17operator has completed reclamation of any portion of the mining site in accordance
18with the reclamation plan and this subchapter, the department shall issue a
19certificate of completion setting forth a description of the area reclaimed and a
20statement that the operator has fulfilled its duties under the reclamation plan as to
21that area.
SB1,192,2 22(2) Upon the issuance of any certificate of completion under sub. (1) for any
23portion of the mining site, but not for the entire mining site, the department shall
24allow the operator to reduce the amount of the bond or other security provided under
25s. 295.59 (1) to an amount equal to the estimated cost of reclamation of the portion

1of the mining site that is disturbed or for which reclamation has been completed but
2no certificate of completion has been issued.
SB1,192,8 3(3) Upon issuance of a certificate or certificates of completion of reclamation
4for the entire mining site, the department shall require the operator to maintain a
5bond or other security under s. 295.59 (1) equal to at least 10 percent of the cost to
6the state of reclamation of the entire mining site, except that if the mining site in the
7mining plan is less than 10 acres, the department may release the bond or other
8security after issuance of the certificate of completion for the entire mining site.
SB1,192,12 9(4) After 10 years after the issuance of a certificate or certificates of completion
10for the entire mining site, the department shall release the remaining bond or other
11security provided under s. 295.59 (1) if the department finds that the reclamation
12plan has been complied with.
SB1,193,2 13295.69 Termination of proof of financial responsibility for long-term
14care of mining waste site.
(1) One year after closure, and annually thereafter
15until the department terminates the obligation to maintain proof of financial
16responsibility for long-term care of a mining waste site under sub. (2) (c), an operator
17who has carried out all necessary long-term care during the preceding year, may
18apply to the department for a reduction in the amount of the proof of financial
19responsibility provided under s. 295.59 (2m) equal to the costs of long-term care for
20that year. The operator shall provide an itemized list of costs incurred. If the
21department determines that the costs incurred are in accordance with the long-term
22care requirements in the approved waste site feasibility study and plan of operation
23and that adequate funds exist to complete required long-term care for the remainder
24of the 40-year period on which the amount of the proof of financial responsibility was
25originally determined, the department shall authorize in writing a reduction in the

1amount of proof of financial responsibility provided. The department shall make its
2determinations within 90 days of an application.
SB1,193,12 3(2) (a) An operator may apply to the department for termination of its
4obligation to maintain proof of financial responsibility for long-term care of the
5mining waste site under s. 295.59 (2m) at any time after the mining waste site has
6been closed for 20 years by submitting an application that demonstrates that
7continuation of the obligation to maintain proof of financial responsibility for
8long-term care is not necessary for adequate protection of public health or the
9environment. The burden is on the operator to prove by a preponderance of the
10evidence that continuation of the obligation to maintain proof of financial
11responsibility for long-term care is not necessary for adequate protection of public
12health or the environment.
SB1,193,2413 (b) Within 30 days of receiving an application under par. (a), the department
14shall provide notice to the public of the application for termination of the obligation
15to maintain proof of financial responsibility for long-term care. In the notice, the
16department shall invite the submission of written comments by any person on the
17application within 30 days of the date of the publication of the notice. The
18department shall provide the notice by publishing a class 1 notice under ch. 985 in
19the official newspaper designated under s. 985.04 or 985.05 or, if none exists, in a
20newspaper likely to give notice in the area of the mining waste site, and shall publish
21notice on the department's Internet site. The date on which the department first
22publishes the notice on its Internet site shall be considered the date of the publication
23of the notice required to be published under this paragraph. The department shall
24also send the notice to the operator.
SB1,194,8
1(c) Within 120 days of the date of the publication of the notice under par. (b),
2the department shall determine either that proof of financial responsibility for
3long-term care of the mining waste site is no longer required, in which case the
4applicant is relieved of the responsibility of providing proof of financial responsibility
5for long-term care, or that proof of financial responsibility for long-term care of the
6mining waste site is still required, in which case the applicant may not submit
7another application under par. (a) until at least 5 years have elapsed since the
8previous application.
SB1,194,18 9295.695 Inspections by the department. (1) Any duly authorized officer,
10employee, or representative of the department who has received the safety training
11under 30 CFR 48.31 may enter and inspect any property, premises, or place on or at
12which any mining operation or facility is located or is being constructed or installed
13at any reasonable time for the purpose of ascertaining the state of compliance with
14this subchapter and the provisions of chs. 281, 283, 285, 289, 291, 292, and 299 and
15rules promulgated under those chapters that are applicable to the mining operation.
16No person may refuse entry or access to any authorized representative of the
17department who requests entry for purposes of inspection, and who presents
18appropriate credentials.
SB1,194,20 19(2) No person may obstruct, hamper, or interfere with any inspection
20authorized in sub. (1).
SB1,194,23 21(3) The department shall furnish to the operator a written report on any
22inspection setting forth all observations, relevant information, and data that relate
23to compliance status.
SB1,195,2 24295.73 Fees. (1) (a) Except as provided in par. (b), an applicant for a mining
25permit is not required to pay any application or filing fee for any approval other than

1a mining permit, notwithstanding any fee required under ch. 23, 29, 30, 31, 169, 281,
2283, 285, 289, or 291, or rules promulgated under those chapters.
SB1,195,43 (b) An applicant for a mining permit shall pay any fee required under s. 281.343
4(3) (c) 1.
SB1,195,9 5(3) (a) The department shall assess an applicant a fee equal to its costs, other
6than costs of a contract under par. (d), for evaluating the mining project, including
7the costs for consultants retained by the department to evaluate the application for
8the mining permit and the application for any other approval, or $2,000,000,
9whichever is less.
SB1,195,1010 (b) The applicant shall pay the fees under par. (a) as follows:
SB1,195,1311 1. One hundred thousand dollars shall be paid at the time that the bulk
12sampling plan is filed under s. 295.45 or at the time that the notice of the intention
13to file a mining permit application is filed, whichever is first.
SB1,195,1614 2. Two hundred fifty thousand dollars when the department provides cost
15information demonstrating that the payment under subd. 1. has been fully allocated
16against actual costs.
SB1,195,1917 3. Two hundred fifty thousand dollars when the department provides cost
18information demonstrating that the payment under subd. 2. has been fully allocated
19against actual costs.
SB1,195,2220 4. Two hundred fifty thousand dollars when the department provides cost
21information demonstrating that the payment under subd. 3. has been fully allocated
22against actual costs.
SB1,195,2523 5. Two hundred fifty thousand dollars when the department provides cost
24information demonstrating that the payment under subd. 4. has been fully allocated
25against actual costs.
SB1,196,3
16. Two hundred fifty thousand dollars when the department provides cost
2information demonstrating that the payment under subd. 5. has been fully allocated
3against actual costs.
SB1,196,64 7. Two hundred fifty thousand dollars when the department provides cost
5information demonstrating that the payment under subd. 6. has been fully allocated
6against actual costs.
SB1,196,97 8. Two hundred fifty thousand dollars when the department provides cost
8information demonstrating that the payment under subd. 7. has been fully allocated
9against actual costs.
SB1,196,1210 9. One hundred fifty thousand dollars when the department provides cost
11information demonstrating that the payment under subd. 8. has been fully allocated
12against actual costs.
SB1,196,1713 (c) After the department approves or denies the application for a mining permit
14or, if the applicant withdraws the application for a mining permit, after the applicant
15withdraws the application, the department shall refund to the applicant any amount
16paid by the applicant under par. (a) but not fully allocated against the department's
17actual costs.
Loading...