AB1156-AA3,1,1110
65.90
(3) (b) 3. Revenue and expenditure totals for each impact fee that is
11imposed by a municipality.".
AB1156-AA3,2,2312
66.0617
(9) (a) Subject to par. (b), an ordinance enacted under this section shall
13specify that impact fees that are imposed and collected by a
political subdivision 14municipality but are not used within 7 years after they are collected to pay the capital
15costs for which they were imposed shall be refunded to the current owner of the
16property with respect to which the impact fees were imposed
, along with any interest
17that has accumulated, in described in sub. (8). The ordinance shall specify, by type
18of public facility, reasonable time periods within which impact fees must be spent or
19refunded under this subsection, subject to the 7-year limit in this paragraph and the
20extended time period specified in par. (b). In determining the length of the time
21periods under the ordinance, a
political subdivision
municipality shall consider what
22are appropriate planning and financing periods for the particular types of public
23facilities for which the impact fees are imposed.".
AB1156-AA3,3,85
236.45
(6) Requirements for approval conditions. (a) Notwithstanding subs.
6(1) and (2) (a) (intro.), a municipality, town, or county may not, as a condition of
7approval under this chapter, impose any fees or other charges to fund the acquisition
8or improvement of land, infrastructure, or other real or personal property.
AB1156-AA3,3,129
(b) Any land dedication, easement, or other public improvement required by a
10municipality, town, or county as a condition of approval under this chapter must bear
11a rational relationship to a need for the land dedication, easement, or other public
12improvement resulting from the subdivision or other division of land.
AB1156-AA3,3,17
14(1) Requirements for approval conditions. The treatment of section 236.45
15(6) of the statutes first applies to a certified survey map, a preliminary plat, or, if no
16preliminary plat was submitted, a final plat that is submitted for approval on the
17effective date of this subsection.".