LRBs0399/2
JTK:bjk&kjf:ph
2009 - 2010 LEGISLATURE
SENATE SUBSTITUTE AMENDMENT 1,
TO 2009 SENATE BILL 298
April 9, 2010 - Offered by Committee on Ethics Reform and Government
Operations
.
SB298-SSA1,1,4 1An Act to amend 16.855 (2) (intro.), 16.855 (13) (a), 16.855 (14) (a) and 16.855
2(15); and to create 16.855 (14) (ae) and 16.855 (14) (am) to (aq) of the statutes;
3relating to: state building contracting and construction procedures and
4granting rule-making authority.
Analysis by the Legislative Reference Bureau
This substitute amendment makes changes in state building contracting and
construction procedures.
Currently, with certain exceptions, contracts for construction work on state
construction projects that cost more than $40,000 must be let by contract to the
lowest responsible bidder and must be preceded by public notice and a public bidding
process. Wisconsin-based bidders are accorded a preference over bidders whose
home governments grant them a preference in making governmental purchases.
With certain exceptions, if bids are required to be solicited and the estimated cost of
a project exceeds $150,000, the Department of Administration (DOA) must solicit
single and separate bids on each portion of the work that DOA designates. DOA must
attempt to ensure that 5 percent of the total amount expended for construction work
in each fiscal year is awarded to minority-owned businesses. Contractors must be
granted certain progress payments while a project is underway. With certain
exceptions, if the estimated cost of a project exceeds $150,000, the project is subject
to approval of the Building Commission.

The substitute amendment permits DOA either to: 1) solicit both single and
separate bids on any division of the work it designates; or 2) solicit only single bids
on all divisions of the work that DOA designates. The substitute amendment also
permits DOA to utilize another contracting procedure to construct any project called
"construction-manager-at-risk contracting" for any project having an estimated
cost of $40,000,000 or more. Under the construction-manager-at-risk contracting
procedure, DOA hires a construction manager to provide pre-construction services
and to manage the construction process. The construction manager must solicit bids
for all work on a project unless the manager submits a bid for a portion of the work.
The substitute amendment also permits DOA to prescribe, by rule, additional
contracting procedures not specified in current law or in the substitute amendment
that DOA may utilize for any project.
The substitute amendment provides the following when DOA uses a
contracting procedure in which it solicits only single bids on all divisions of the work
(single prime contracting): 1) the prime contractor must submit to DOA the names
of the subcontractors that are proposed to be retained; 2) the prime contractor must
provide proof to DOA of each proposed subcontractor's ability to obtain a bond that
guarantees performance of its division of the work subject to criteria set by DOA; 3)
the prime contractor must submit progress payment requests to DOA and must
promptly pay the subcontractors for their proportionate share of the work when a
payment is received from DOA; and 4) retainages from subcontractors must be
limited to their proportionate share of the work. In addition, the substitute
amendment provides that when DOA uses the single prime contracting procedure
to construct a project, DOA must ensure that each subcontractor has access to the
elements of the project information available to the prime contractor that are
required for the subcontractor to effectively participate in the project.
Under all of the proposed new contracting procedures, as well as any other
procedures prescribed by DOA, DOA must advertise for and solicit bids on all or any
portion of the work it designates and comply with all other laws governing
construction procedures, except that DOA may provide, by rule, that any of these
laws do not apply to a specific project that is constructed using the
construction-manager-at-risk procedure, and except that, as currently provided,
the Building Commission may waive compliance with any of these laws for
construction of a specific project.
Currently, with certain exceptions, a bidder on a contract for a state project
need not submit with its bid a list of the subcontractors to be used on the project, but
DOA may require a list of the subcontractors to be submitted before the contract is
awarded. This substitute amendment permits DOA to require each bidder on a state
project to submit with its bid a list of its subcontractors to be used on the project.
The people of the state of Wisconsin, represented in senate and assembly, do
enact as follows:
SB298-SSA1, s. 1 1Section 1. 16.855 (2) (intro.) of the statutes is amended to read:
SB298-SSA1,3,4
116.855 (2) (intro.) Except as provided in subs. (10) and (14) (ae), (am), and (ao)
2and except
for projects authorized under s. 16.858, whenever the estimated
3construction cost of a project exceeds $40,000, or if less and in the best interest of the
4state, the department shall:
SB298-SSA1, s. 2 5Section 2. 16.855 (13) (a) of the statutes is amended to read:
SB298-SSA1,3,126 16.855 (13) (a) A The department may require each person who submits a bid
7to provide a
list of the major subcontractors shall not be required to be submitted,
8as designated by the department in its solicitation documents, for work to be
9performed
with the person's bid. The Except as provided in sub. (14) (ae) 2., the
10department may also require the each prime contractor to submit in writing the
11names of prospective subcontractors for the department's approval before the award
12of a contract to the prime contractor.
SB298-SSA1, s. 3 13Section 3. 16.855 (14) (a) of the statutes is amended to read:
SB298-SSA1,3,2514 16.855 (14) (a) If a project requires prior approval of the building commission
15under s. 13.48 (10) (a) and or bids are required to be solicited under sub. (2), the
16department shall take may solicit both single bids and separate bids on any division
17of the work that it designates. If a project does not require prior approval of the
18building commission under s. 13.48 (10) (a) and bids are required to be solicited under
19sub. (2), the department may take single bids or separate bids on any division of the
20work that it designates
or may solicit only single bids on all divisions of the work.
21If the department awards contracts by the division of work, the department shall
22award the contracts according to the division of work selected for bidding. Except
23as provided in pars. (am) and (ao) and sub. (10m) (a), the department shall award all
24contracts to the lowest qualified responsible bidder or bidders that result in the
25lowest total construction cost for the project.
SB298-SSA1, s. 4
1Section 4. 16.855 (14) (ae) of the statutes is created to read:
SB298-SSA1,4,22 16.855 (14) (ae) 1. In this paragraph:
SB298-SSA1,4,53 a. "Base bid" means the bid of a prime contractor for all work to be performed
4on a project submitted in accordance with the solicitation, excluding any alternatives
5or options.
SB298-SSA1,4,76 b. "Single prime contracting" means a contracting procedure in which the
7department solicits only single bids on all divisions of the work on a project.
SB298-SSA1,4,108 2. If the department elects to use single prime contracting for the construction
9of a project, the department shall set forth the divisions of the work in the
10solicitation. The department shall also enforce the following requirements:
SB298-SSA1,4,1711 a. Each bidder shall submit in writing the names of the subcontractors who are
12proposed to be retained to perform services required under the base bid for each
13division of the work specified by the department together with the amount to be paid
14by the prime contractor to each subcontractor. No modification may be made in the
15submission unless the department permits a modification. The department may
16permit a modification after the opening of bids but prior to execution of the contract
17with the prime contractor.
SB298-SSA1,4,2118 b. For each subcontractor that is enumerated by the prime contractor, the
19prime contractor shall provide to the department proof of the subcontractor's ability
20to obtain a bond that guarantees performance of its division of the work subject to
21criteria set by the department.
SB298-SSA1,4,2422 c. The prime contractor shall submit progress payment requests to the
23department for each period designated by the department and upon receiving each
24progress payment shall pay each subcontractor for its division of the work promptly.
SB298-SSA1,5,3
1d. In making payments to each subcontractor, the prime contractor shall limit
2the amount of any retainage to the proportionate share of the retainage under sub.
3(19) that is attributable to the subcontractor's division of the work.
SB298-SSA1,5,64 e. The prime contractor shall promptly pay each subcontractor for any
5retainage when the work contracted to that subcontractor is completed to the
6satisfaction of the department.
SB298-SSA1,5,107 3. If the department elects to use single prime contracting for the construction
8of a project, the department shall ensure that each subcontractor has access to the
9elements of the project information available to the prime contractor that are
10required for the subcontractor to effectively participate in execution of the project.
SB298-SSA1, s. 5 11Section 5. 16.855 (14) (am) to (aq) of the statutes are created to read:
SB298-SSA1,5,2112 16.855 (14) (am) 1. In this paragraph, "construction-manager-at-risk
13contracting" means a contracting procedure in which a person is selected by the
14department to act as a construction manager for a project; to provide
15pre-construction services during the design phase of the project; and to manage the
16construction process, which includes, but is not limited to, supervision of public
17notice and bidding for construction work on the project, contracting for construction
18work required to be performed on the project, compliance with all terms and
19conditions of applicable collective bargaining agreements, if any, and assumption of
20responsibility for the project's cost, completion schedule, and workmanship of
21construction.
SB298-SSA1,6,322 2. As an alternative to the procedures under par. (a), the department may
23utilize construction-manager-at-risk contracting to construct a project having an
24estimated cost of $40,000,000 or more. The department shall prescribe, by rule, the
25specific procedures to be used by the department for projects constructed using

1construction-manager-at-risk contracting. A rule promulgated under this
2subdivision may provide that any provision of this section does not apply to a project
3constructed in accordance with the procedures prescribed in the rule.
SB298-SSA1,6,94 3. When the department elects to utilize construction-manager-at-risk
5contracting to construct a project, the construction manager shall solicit bids on all
6work on the project in the manner prescribed under this subsection unless the
7construction manager elects to submit a bid to perform a portion of the work. In that
8case, the department shall solicit bids for that portion of the work in accordance with
9procedures prescribed by rule.
SB298-SSA1,6,1210 (an) The department may prescribe, by rule, additional contracting procedures
11not enumerated in this subsection that the department may utilize to construct any
12project that requires approval of the building commission under s. 13.48 (10) (a).
SB298-SSA1,6,1613 (ao) On any project constructed under a procedure identified in or prescribed
14under par. (ae), (am), or (an), the department shall comply with all provisions of this
15section unless the building commission waives compliance under s. 13.48 (19), or a
16rule promulgated under par. (am) provides for an alternative procedure.
SB298-SSA1,6,1717 (ap) The department shall define, by rule:
SB298-SSA1,6,2118 1. Any specific contracting procedures not specified in par. (ae) that prime
19contractors must use when the department elects under par. (a) to solicit only single
20bids on all divisions of the work on a project to provide protections to major
21subcontractors.
SB298-SSA1,6,2422 2. The specific contracting procedures identified in or authorized to be
23prescribed under pars. (am) and (an) and how they will be applied to construction
24projects.
SB298-SSA1,7,2
13. The criteria that will be applied to the selection of the contracting procedure
2that will be utilized by the department on a particular project.
SB298-SSA1,7,53 4. The selection process that the department will use to select a contractor for
4any contracting procedure to be utilized on a project other than the procedures
5identified in par. (a).
SB298-SSA1,7,86 5. The procedures that the department will use to solicit bids for any portion
7of the work on a project in which the construction manager at risk for the project
8elects to submit a bid to perform the portion of the work.
SB298-SSA1,7,129 (aq) The department may define, by rule, the criteria that will be applied to the
10selection of a contracting procedure for a project when the building commission
11waives any provision of this section to permit the use of innovative types of design
12and construction processes under s. 13.48 (19).
SB298-SSA1, s. 6 13Section 6. 16.855 (15) of the statutes is amended to read:
SB298-SSA1,7,1514 16.855 (15) The department shall promulgate rules to implement the
15advertising and award of contracts under sub. (1).
SB298-SSA1, s. 7 16Section 7. Initial applicability.
SB298-SSA1,7,1917 (1) The treatment of section 16.855 (2) (intro.), (13) (a), (14) (a), (ae), and (am)
18to (aq), and (15) of the statutes first applies with respect to contracts for services or
19construction work entered into on the effective date of this subsection.
Loading...
Loading...