11. DNR must determine whether the final EIS is adequate within 280 days
after publication of the notice under item 8., except that the deadline may be
extended by consent of the applicant or by the governor for good cause.
12. If DNR determines that the EIS is inadequate, it must prepare an adequate
EIS within 60 days of that determination.
The substitute amendment prohibits DNR from making final decisions on any
approvals for the iron mine that were considered in the EIS process, including the
mining permit, before the EIS is determined to be adequate. DNR must generally
make final decisions on those approvals within 90 days after the determination of
adequacy, but the deadline may be extended with the consent of the applicant and
the deadline does not apply if a longer period is required for an approval by federal
law or other state law.
Net proceeds occupation tax
Under current law, the state imposes a net proceeds occupation tax on the
mining of metallic minerals in this state. The tax is based, generally, on a percentage
of net income from the sale of ore or minerals after certain mining processes have
been applied to the ore or minerals. The tax rates are annually adjusted to reflect
the change in gross national product. Gross national product, generally, measures
the output generated by U.S. enterprises, regardless of whether those enterprises
are located in this country.
Under current law, the revenue collected from the net proceeds occupation tax
is deposited into the investment and local impact fund. The fund is managed by the
local impact fund board. The revenue is then distributed to the counties and
municipalities in which metallic minerals are being mined. In addition to paying the
net proceeds occupation tax, a person who intends to apply for a mining permit must
make an additional three payments of $50,000 each to the investment and local
impact fund. Those payment amounts are not annually adjusted to reflect the
change in gross national product.
Under the substitute amendment, instead of paying a net proceeds occupation
tax based on net income, a person who is mining ferrous minerals in this state would
pay a tax equal to $2.38 for each 2,240 pounds of mining product sold, based on a
three-year average. The tax rate would be annually adjusted to reflect the change
in the gross domestic product. Gross domestic product, generally, measures the total
output produced within the United States, regardless of whether the output is
produced by foreign companies. Under the substitute amendment, a person who
intends to apply for a mining permit must also make an additional three payments
of $100,000 each to the investment and local impact fund. Those payment amounts
are annually adjusted to reflect the change in gross domestic product.
The people of the state of Wisconsin, represented in senate and assembly, do
enact as follows:
AB426-ASA2,5,92
70.375
(2) (a)
In Except as provided in sub. (7), with respect to mines not in
3operation on November 28, 1981, there is imposed upon persons engaged in mining
4metalliferous minerals in this state a net proceeds occupation tax effective on the
5date on which extraction begins to compensate the state and municipalities for the
6loss of valuable, irreplaceable metalliferous minerals. The amount of the tax shall
7be determined by applying the rates established under sub. (5) to the net proceeds
8of each mine. The net proceeds of each mine for each year are the difference between
9the gross proceeds and the deductions allowed under sub. (4) for the year.
AB426-ASA2, s. 2
10Section
2. 70.375 (5) (intro.) of the statutes is amended to read:
AB426-ASA2,5,1311
70.375
(5) Rates. (intro.)
The Except as provided in sub. (7), the tax to be
12assessed, levied and collected upon persons engaging in mining metalliferous
13minerals in this state shall be computed at the following rates:
AB426-ASA2,6,18
170.375
(6) Indexing. For Except as provided in sub. (7), for calendar year 1983
2and corresponding fiscal years and thereafter, the dollar amounts in sub. (5) and s.
370.395 (1) and (2) (d) 1m. and 5. a. and (dg) shall be changed to reflect the percentage
4change between the gross national product deflator for June of the current year and
5the gross national product deflator for June of the previous year, as determined by
6the U.S. department of commerce as of December 30 of the year for which the taxes
7are due, except that no annual increase may be more than 10%. For calendar year
81983 and corresponding fiscal years and thereafter until calendar year 1997 and
9corresponding fiscal years, the dollar amounts in s. 70.395 (1m), 1995 stats., shall be
10changed to reflect the percentage change between the gross national product deflator
11for June of the current year and the gross national product deflator for June of the
12previous year, as determined by the U.S. department of commerce as of December
1330 of the year for which the taxes are due, except that no annual increase may be
14more than 10%. The revised amounts shall be rounded to the nearest whole number
15divisible by 100 and shall not be reduced below the amounts under sub. (5) on
16November 28, 1981. Annually, the department shall adopt any changes in dollar
17amounts required under this subsection and incorporate them into the appropriate
18tax forms.
AB426-ASA2,6,2520
70.375
(7) Per ton rate. (a) Notwithstanding subs. (2), (5), and (6), for mines
21in operation after December 31, 2011, the tax assessed, levied, and collected from a
22person engaged in mining ferrous minerals in this state is an amount equal to $2.38
23for each 2,240 pounds of mining product sold, based on the average annual amount
24sold during the current year and the previous 2 years, not including any year in
25which no ferrous minerals are extracted in this state.
AB426-ASA2,7,6
1(b) Beginning in 2013, and in each year thereafter, the department shall change
2the dollar amounts under par. (a) and s. 70.395 (2) (dc) 1., 2., and 3. to reflect the
3percentage change between the gross domestic product deflator for June of the
4current year and the gross domestic product deflator for June of the previous year,
5as determined by the federal department of commerce on December 30 of the year
6in which the taxes are due.
AB426-ASA2, s. 5
7Section
5. 70.395 (2) (dc) 1. of the statutes is amended to read:
AB426-ASA2,7,128
70.395
(2) (dc) 1. Each person intending to submit an application for a mining
9permit shall pay
$50,000 $100,000, as adjusted under s. 70.375 (7) (b), to the
10department of revenue for deposit in the investment and local impact fund at the
11time that the person notifies the department of natural resources under s. 293.31 (1)
12or 293.495 (2) of that intent.
AB426-ASA2, s. 6
13Section
6. 70.395 (2) (dc) 2. of the statutes is amended to read:
AB426-ASA2,7,1614
70.395
(2) (dc) 2. A person making a payment under subd. 1. shall pay an
15additional
$50,000 $100,000, as adjusted under s. 70.375 (7) (b), upon notification by
16the board that the board has distributed 50% of the payment under subd. 1.
AB426-ASA2, s. 7
17Section
7. 70.395 (2) (dc) 3. of the statutes is amended to read:
AB426-ASA2,7,2118
70.395
(2) (dc) 3. A person making a payment under subd. 2. shall pay an
19additional
$50,000 $100,000, as adjusted under s. 70.375 (7) (b), upon notification by
20the board that the board has distributed all of the payment under subd. 1. and 50%
21of the payment under subd. 2.
AB426-ASA2,7,2523
293.01
(4e) "Ferrous mineral" means an ore or earthen material in natural
24deposits in or on the earth that primarily exists in the form of an iron oxide, including
25taconite and hematite.
AB426-ASA2,8,42
293.01
(4m) "Ferrous mining" means the mining of ferrous minerals at a
3mining site where the department determines that it is not likely that any of the
4disturbed areas will contain significant amounts of sulfide minerals.
AB426-ASA2,8,11
6293.32 Prospecting and mining fees.
(1) When a person gives notice under
7s. 293.31 (1)
or 293.495 (2), the person shall pay a fee established by the department
8by rule designed to cover the costs incurred by the department in connection with the
9proposed prospecting or mining during the year following receipt of the notice, other
10than any costs related to the environmental impact statement for the proposed
11prospecting or mining.
AB426-ASA2,8,19
12(2) The department shall annually compare the fees paid under this section
13and under chs. 30, 280 to 292 and 295 to 299 in connection with proposed prospecting
14or mining for which notice has been given under s. 293.31 (1)
or 293.495 (2) with the
15costs incurred by the department in connection with that proposed prospecting or
16mining, including the costs incurred under chs. 30, 280 to 292 and 295 to 299 but
17excluding costs related to the environmental impact statement. If the costs incurred
18exceed the fees paid, the person who notified the department shall pay a fee equal
19to the amount by which the costs exceed the fees previously paid.
AB426-ASA2,9,6
20(3) When the department issues or denies a prospecting or mining permit or
21when a person who gave notice under s. 293.31 (1)
or 293.495 (2) ceases to seek
22approval of the proposed prospecting or mining project, the department shall
23compare the fees paid under this section and under chs. 30, 280 to 292 and 295 to 299
24in connection with the proposed prospecting or mining with the costs incurred by the
25department in connection with the proposed prospecting or mining, including the
1costs incurred under chs. 30, 280 to 292 and 295 to 299 but excluding costs related
2to the environmental impact statement. If the costs incurred are less than the fees
3paid, the department shall pay the person who gave notice the amount by which the
4fees exceed the costs. If the costs incurred exceed the fees paid, the person who
5notified the department shall pay a final fee equal to the amount by which the costs
6exceed the fees previously paid.
AB426-ASA2,9,138
293.33
(3) Persons giving notice under s. 293.31 (1)
or 293.495 (2) shall
9thereafter appoint a liaison person to any committee established under sub. (1) or (2),
10and shall provide such reasonable information as is requested by the committee.
11Operators and persons giving notice under s. 293.31
or 293.495 (2) shall thereafter
12make reasonable efforts to design and operate mining operations in harmony with
13community development objectives.
AB426-ASA2, s. 12
14Section
12. 293.39 (4) and (5) of the statutes are created to read:
AB426-ASA2,9,1715
293.39
(4) (a) A person proposing to engage in ferrous mining shall prepare and
16submit to the department an environmental impact report for the ferrous mining
17project.
AB426-ASA2,9,2218
(b) The department shall determine whether an environmental impact report
19submitted under par. (a) or (c) is complete no later than 30 days after receiving the
20environmental impact report. The department shall notify the person submitting
21the environmental impact report of its determination no later than 5 days after
22making the determination.
AB426-ASA2,9,2423
(c) If the department determines that an environmental impact report
24submitted under par. (a) is incomplete, the person proposing to engage in ferrous
1mining shall prepare and submit to the department a revised environmental impact
2report for the ferrous mining project.
AB426-ASA2,10,123
(d) No more than 30 days after providing notification under par. (b) that an
4environmental impact report is complete, the department shall prepare a draft
5scoping statement consisting of at least the following: a description of known
6governmental approvals or reviews required for the ferrous mining project; a
7description of the issues to be covered in the environmental impact statement;
8alternatives that will be addressed in the environmental impact statement;
9identification of areas potentially affected by the project and by related actions; and
10identification of necessary studies requiring compilation of existing information or
11the development of new data that can be generated within a reasonable amount of
12time and at a reasonable cost.
AB426-ASA2,10,1613
(e) No more than 10 days after completing its responsibilities under par. (d),
14the department shall publish a class 1 notice, under ch. 985, in a newspaper with
15general circulation in the area in which the proposed site is located and in the official
16state newspaper, that includes all of the following:
AB426-ASA2,10,1717
1. The name and location of the proposed ferrous mining project.
AB426-ASA2,10,1818
2. A brief description of the proposed project.
AB426-ASA2,10,2019
3. The location at which copies of the environmental impact report and draft
20scoping statement are available for review.
AB426-ASA2,10,2221
4. The description of the opportunity to comment on the appropriate scope of
22the environmental impact statement for the project.
AB426-ASA2,10,2423
5. A statement that the period for written comment expires 30 days after the
24date of publication of the notice.
AB426-ASA2,10,2525
6. The procedures for commenting.
AB426-ASA2,11,1
17. The date, time, and place of the public informational meeting under par. (g).
AB426-ASA2,11,72
(f) The department shall also provide the notice under par. (e) to the person who
3submitted the environmental impact report, the U.S. army corps of engineers, the
4federal environmental protection agency; the U.S. fish and wildlife service, the state
5historical society, any federally recognized American Indian tribe or band that may
6be affected by the proposed project, and any local governmental unit in which the
7project will take place.
AB426-ASA2,11,108
(g) At least 10 days, but not more than 20 days after publication of the notice
9under par. (e), the department shall hold at least one public informational meeting
10to discuss the scope of the environmental impact statement.
AB426-ASA2,11,2011
(h) The department shall issue its final decision on the scope of the
12environmental impact statement no later than 15 days after the the end of the public
13comment period. The department shall include at least all of the following in the
14scoping decision: a description of known governmental approvals or reviews
15required for the ferrous mining project; a description of the issues to be covered in
16the environmental impact statement; alternatives that will be addressed in the
17environmental impact statement; identification of areas potentially affected by the
18project and by related actions; and identification of necessary studies requiring
19compilation of existing information or the development of new data that can be
20generated within a reasonable amount of time and at a reasonable cost.
AB426-ASA2,12,421
(i) No later than 30 days after it issues the scoping decision, the department
22shall submit to the person who submitted the environmental impact report a draft
23cost agreement. The agreement shall include the estimated cost of preparing the
24environmental impact statement and a brief description of the tasks and the cost of
25each task to be performed by each party in preparing and distributing the
1environmental impact statement. The person may request changes in the cost
2agreement. If, within 30 days after the person receives the draft cost agreement, the
3department and the person have not signed a cost agreement, either party may refer
4the matter to the secretary of administration for resolution.
AB426-ASA2,12,75
(im) No later than 10 days after finalizing the cost agreement under par. (i), the
6person entering into the cost agreement with the department shall pay to the
7department 50 percent of the estimated costs under the cost agreement.
AB426-ASA2,12,118
(j) No later than 45 days after receiving the payment under par. (im), the
9department shall publish a class 1 notice, under ch. 985, in at least one newspaper
10of general circulation in each county where the project will occur and in the official
11state newspaper, containing a summary of the scoping decision.
AB426-ASA2,13,512
(k) After the department publishes the notice under par. (j), the department
13shall prepare a preliminary environmental impact statement for the proposed
14ferrous mining project in accordance with the scoping decision. When the
15preliminary environmental impact statement is complete, the department shall
16make it available for public review and comment and shall publish a class 1 notice,
17under ch. 985, of completion of the preliminary environmental impact statement, of
18the ability to comment on the preliminary environmental impact statement, and of
19the date, time, and place of the public meeting under par. (L) in at least one
20newspaper of general circulation in each county where the project will occur and in
21the official state newspaper. The department shall also distribute a summary of the
22preliminary environmental impact statement and notice of the date, time, and place
23of the meeting under par. (L) to the person who submitted the environmental impact
24report, the U.S. army corps of engineers, the federal environmental protection
25agency, the U.S. fish and wildlife service, the state historical society, any federally
1recognized American Indian tribe or band that may be affected by the proposed
2project, any local governmental unit in which the project will take place, any person
3that submitted substantive comments within the comment period on the
4environmental impact report and the draft scoping statement, and any person
5requesting the summary.
AB426-ASA2,13,116
(L) Not less than 15 days after publication of the notice under par. (k), the
7department shall conduct a public informational meeting on the adequacy of the
8preliminary environmental impact statement in a county in which at least part of the
9proposed mining site is located. The department shall receive public comments on
10the adequacy of the preliminary environmental impact statement for at least 10 days
11after the day on which it conducts the public informational meeting.
AB426-ASA2,14,212
(m) The department shall prepare a final environmental impact statement,
13taking into consideration the comments received under par. (L). When the final
14environmental impact statement is complete, the department shall make it available
15for public review and comment and shall publish a class 1 notice, under ch. 985, of
16completion of the final environmental impact statement, of the ability to submit
17written comments on the final environmental impact statement, and of the date by
18which comments must be submitted, in at least one newspaper of general circulation
19in each county where the project will occur and in the official state newspaper. The
20department shall also distribute a summary of the final environmental impact
21statement to the person who submitted the environmental impact report, the U.S.
22army corps of engineers, the federal environmental protection agency, the U.S. fish
23and wildlife service, the state historical society, any federally recognized American
24Indian tribe or band that may be affected by the proposed project, any local
25governmental unit in which the project will take place, any person that submitted
1substantive comments within the comment period on the preliminary environmental
2impact statement, and any person requesting the summary.
AB426-ASA2,14,113
(n) The department shall accept written comments on the adequacy of the final
4environmental impact statement for at least 10 days after the day on which the notice
5under par. (m) is published. The department shall make the determination of
6adequacy of the final environmental impact statement at least 10 days after
7publication of the notice of availability of the final environmental impact statement.
8The department shall make the determination of adequacy of the final
9environmental impact statement within 280 days after publication of the notice
10under par. (j) unless the time is extended by consent of the person submitting the
11environmental impact report or by the governor for good cause.
AB426-ASA2,15,212
(o) If the department determines that the environmental impact statement is
13inadequate, the department shall prepare an adequate environmental impact
14statement within 60 days of that determination. When the adequate environmental
15impact statement is complete, the department shall publish a class 1 notice, under
16ch. 985, of completion of the environmental impact statement in at least one
17newspaper of general circulation in each county where the project will occur and in
18the official state newspaper. The department shall also distribute a summary of the
19adequate environmental impact statement to the person who submitted the
20environmental impact report, the U.S. army corps of engineers, the federal
21environmental protection agency, the U.S. fish and wildlife service, the state
22historical society, any federally recognized American Indian tribe or band that may
23be affected by the proposed project, any local governmental unit in which the project
24will take place, any person that submitted substantive comments within the
1comment period on the previous version of the environmental impact statement, and
2any person requesting the summary.
AB426-ASA2,15,5
3(5) (a) The department may not issue a mining permit or any other approval
4required in connection with a ferrous mining project before it determines that the
5environmental impact statement for the project is adequate.
AB426-ASA2,15,106
(b) Within 90 days after the determination of adequacy of a final environmental
7impact statement, the department shall make final decisions on those approvals that
8were identified as required in the scoping process and for which information was
9developed concurrently with the preparation of the environmental impact
10statement, except as follows:
AB426-ASA2,15,1211
1. The department may extend the 90-day period with the consent of the
12applicant.
AB426-ASA2,15,1413
2. The 90-day period does not apply if a longer period is required for an
14approval by federal law or state statute.
AB426-ASA2, s. 13
15Section
13. 293.49 (1) (a) 3. of the statutes is amended to read:
AB426-ASA2,15,2316
293.49
(1) (a) 3. In the case of a surface mine, the site is not unsuitable for
17mining. The preliminary determination that a site was not unsuitable for mining
18under s. 293.45 may not be conclusive in the determination of the site's suitability
19for mining under this section. However,
for mining other than ferrous mining, at the
20hearing held under this section and s. 293.43, testimony and evidence submitted at
21the prospecting permit proceeding relevant to the issue of suitability of the proposed
22mining site for surface mining may be adopted, subject to the opportunity for
23cross-examination and rebuttal, if not unduly repetitious.
AB426-ASA2,16,2
1293.495 Process for ferrous mining. (1) Applicability of other provisions. 2The following provisions do not apply to proposed ferrous mining projects:
AB426-ASA2,16,33
(a) Section 293.31.
AB426-ASA2,16,44
(b) Section 293.37 (2) (d).
AB426-ASA2,16,55
(c) Section 293.43.
AB426-ASA2,16,66
(d) The time limit in s. 293.49 (1) (a) (intro.) and (2) (intro.).
AB426-ASA2,16,77
(e) Section 293.49 (1) (a) 2.
AB426-ASA2,16,88
(f) Section 293.55 (1) (c) to (e).
AB426-ASA2,16,109
(g) The authority in s. 293.65 (2) (h) to conduct a hearing on a permit under s.
10293.65 as part of the hearing on the application for a mining permit.
AB426-ASA2,16,1111
(h) Section 293.65 (2) (i).
AB426-ASA2,16,16
12(2) Notice of intent. At least 12 months before submitting an application for
13a mining permit under s. 293.37 or an environmental impact report under s. 293.39
14(4) (a), whichever is earlier, a person proposing to engage in ferrous mining shall
15notify the department in writing of the intent to submit an application for a mining
16permit.
AB426-ASA2,16,25
17(3) Determination of completeness. After the department receives an
18application for a mining permit under s. 293.37 for ferrous mining, the department
19shall determine whether the application is complete. The department shall make the
20determination within 30 days after receiving the application, except that the
21department may extend the 30-day period with the consent of the applicant. If the
22department determines that the application is not complete, the department shall
23inform the applicant of the additional information that must be provided to complete
24the application. When the department determines that the application is complete,
25it shall notify the applicant.
AB426-ASA2,17,7
1(4) Notice of application. After receiving notice under sub. (3) that the
2application for a mining permit is complete, an applicant proposing to engage in
3ferrous mining shall publish a legal notice, under ch. 985, of the ownership, location,
4and boundaries of the proposed mining area and reclamation and restoration
5operations, at least once a week for 4 successive weeks. Within 7 days of publication
6of the last date of publication, the person shall submit a copy of the notice to the
7department.
AB426-ASA2,17,10
8(5) Hearing. (a) No later than 30 days after the day of publication of the last
9notice required under sub. (4), any of the following may file written objections to an
10application for a permit under s. 293.37 for a ferrous mining project:
AB426-ASA2,17,1211
1. A person owning property that will be affected by the proposed ferrous
12mining operation.
AB426-ASA2,17,1413
2. Any federal, state, or local governmental agency with responsibilities
14affected by the proposed ferrous mining operation.
AB426-ASA2,17,1915
(b) If the department receives written objections under par. (a), the department
16shall hold a public hearing on the mining permit application in the county in which
17the majority of the mining site is located no more than 30 days after receiving the
18objections, after providing appropriate notice of the date, time, and place of the
19hearing.
AB426-ASA2,17,2320
(c) The department may hold a hearing on an application for a mining permit
21under s. 293.37 for ferrous mining without receipt of objections no later than 30 days
22after the day of publication of the last notice required under sub. (4) if the department
23determines that a hearing is necessary to protect public health, safety, and welfare.
AB426-ASA2,18,2
24(6) Action on application. If s. 293.39 (5) (a) does not apply, no later than 120
25days after receiving the notice of publication under sub. (4) or, if the department
1holds a hearing under sub. (5), after holding the hearing, the department shall issue
2or deny the mining permit.
AB426-ASA2,18,84
293.51
(3) Upon approval of the operator's bond, mining application
, other
5departmental approvals that are required in connection with the mining project, and
6certificate of insurance, the department shall issue written authorization to
7commence mining at the permitted mining site in accordance with the approved
8mining and reclamation plans.