AB426-SSA2,97,1111 (z) The mining waste site design includes staged reclamation, if practicable.
AB426-SSA2,97,15 12(8) Limitation on regulation of certain mining waste. The department may
13not regulate the use of mining waste in reclamation or the construction of any facility
14or structure except through the department's review of the mining plan and
15reclamation plan and the approval of the application for the mining permit.
AB426-SSA2,97,19 16(9) Applicability of other laws. Subchapters I to V and VIII of ch. 289 and
17rules promulgated under those subchapters do not apply to a mining waste site, to
18the disposal of mining waste in a mining waste site, or to mining wastes used in the
19reclamation or construction of facilities and structures on the mining site.
AB426-SSA2,97,23 20295.53 Environmental impact statement. (1) Consultants. The
21department may enter into contracts for environmental consultant services under
22s. 23.41 to assist in the preparation of an environmental impact statement or to
23provide assistance to applicants.
AB426-SSA2,98,2 24(2) Notice. After the department receives an application for a mining permit,
25it shall notify the public and affected agencies that an environmental impact

1statement will be prepared for the proposed mine and that the process of identifying
2major issues under s. NR 150.21 (3), Wis. Adm. Code, is beginning.
AB426-SSA2,98,15 3(3) Environmental impact report. (a) An applicant shall prepare an
4environmental impact report for the mining project. In the environmental impact
5report, the applicant shall provide a description of the proposed mining project, the
6present environmental conditions in the area and the anticipated environmental
7impacts of the proposed mining project, the present socioeconomic conditions in the
8area and the anticipated socioeconomic impacts of the proposed mining project,
9details of any wetlands mitigation program under s. 295.60 (8), any measures for
10navigable waters under s. 295.605 (4), any proposed changes to the forest
11designations specified in sub. (4) (c), and the alternatives to the proposed mining
12project. As the applicant provides more information or makes modifications to the
13proposed mining project, the department may revise the requirements it specified
14under s. 295.465 (1) (b) to ensure the potential environmental effects can be
15identified in the department's environmental impact statement.
AB426-SSA2,98,2116 (b) The department shall assist the applicant in meeting the deadlines for
17ultimate submission and review of those analyses consistent with this subchapter.
18If a particular scientific analysis is not completed as of the date the environmental
19impact report is required to be submitted, the applicant shall identify in the
20environmental impact report the scope of the analysis and anticipated date that it
21will be submitted.
AB426-SSA2,98,2322 (c) 1. The applicant shall submit the environmental impact report with the
23application for the mining permit.
AB426-SSA2,99,324 3. Upon receipt of the environmental impact report, the department shall
25review the environmental impact report and, if the department finds that the

1environmental impact report does not contain information reasonably necessary for
2the department to evaluate the proposed mining project and its environmental
3effects, the department may request additional information from the applicant.
AB426-SSA2,99,94 (d) The department shall accept original data from an environmental impact
5report for use in the environmental impact statement and need not verify all original
6data provided by the applicant to accept the data as accurate. The department shall
7use original data from an environmental impact report in the environmental impact
8statement if the data contains the information identified under s. 295.465 (1) (b) and
9any of the following conditions is met:
AB426-SSA2,99,1310 1. The department, its consultant, or a cooperating state or federal agency
11collects sufficient data to perform a limited statistical comparison with data from the
12environmental impact report that demonstrates that the data sets are statistically
13similar within a reasonable confidence limit.
AB426-SSA2,99,1614 2. An expert who is employed by, or is a consultant to, the department or is
15employed by, or is a consultant to, a cooperating state or federal agency determines
16that the data is within the range of expected results.
AB426-SSA2,99,1917 3. The department, its consultant or a cooperating state or federal agency
18determines that the methodology used in the environmental impact report is
19scientifically and technically adequate for the tests being performed.
AB426-SSA2,99,23 20(4) Procedure for environmental impact statement. (a) The department shall
21prepare an environmental impact statement for every application for a mining
22permit. In preparing the environmental impact statement, the department shall
23comply with s. 1.11 (2) and s. NR 150.22 (2), Wis. Adm. Code.
AB426-SSA2,100,3
1(b) The department shall include in the environmental impact statement a
2description of the significant long-term and short-term impacts, including impacts
3after the mining has ended, on all of the following:
AB426-SSA2,100,44 1. Tourism.
AB426-SSA2,100,55 2. Employment.
AB426-SSA2,100,66 3. Schools and medical care facilities.
AB426-SSA2,100,77 4. Private and public social services.
AB426-SSA2,100,88 5. The tax base.
AB426-SSA2,100,99 6. The local economy.
AB426-SSA2,100,1410 (c) The department and other state agencies shall address the application for
11a mining permit, for any approval, and for any action relating to the mining project
12involving other state agencies in one comprehensive analysis in the environmental
13impact statement prepared by the department, including any environmental
14analysis required by the department with regard to any of the following:
AB426-SSA2,100,1715 1. The withdrawal of land entered as county forest land under s. 28.11 and any
16modification of, or amendment to, a county forest land use plan necessitated by the
17withdrawal of the land.
AB426-SSA2,100,1818 2. The withdrawal of land entered as forest cropland under s. 77.10.
AB426-SSA2,100,2119 3. The withdrawal of land designated as managed forest land under subch. VI
20of ch. 77 and any modification of, or amendment to, a managed forest land
21management plan necessitated by the withdrawal of the land.
AB426-SSA2,101,222 4. The transfer of land for which amounts were awarded by the department,
23including under s. 23.09 (17m), 26.38, 28.11 (5r), or 77.895, to fund the acquisition
24of, or to fund activities conducted on, forest land and any modification of, or

1amendment to, a forest stewardship management plan or other plan necessitated by
2the transfer of the land.
AB426-SSA2,101,103 (d) The public notice, informational hearing, and comment provisions in s.
4295.57, the provision concerning the effective date of approvals in s. 295.58 (6), and
5the provisions for review in s. 295.77 apply to an environmental impact statement
6prepared under this subsection. If the department revises and redistributes an
7environmental impact statement or portion of an environmental impact statement
8prepared under this section, the department shall distribute the environmental
9impact statement or portion of the environmental impact statement as provided in
10s. 295.57, but the period for public comment is 30 days, rather than 45 days.
AB426-SSA2,102,211 (e) The department shall conduct its environmental review process jointly with
12any federal or local agency that consents to a joint environmental review process.
13The department may adopt any environmental analysis prepared by another state
14agency or by a federal or local agency. The department may enter into a written
15agreement with any of those agencies that have a major responsibility related to or
16that are significantly affected by the proposed mining. In the written agreement, the
17parties shall define the responsibility of each agency in the development of a single
18environmental impact statement on the proposed mining and outline the procedures
19to be used in the regulatory process. The department shall be the lead agency for any
20environmental review process involving other state agencies. To the extent that any
21federal or local agency's environmental review process conflicts with the provisions
22of this section or s. 295.57, then the department shall follow the provisions of this
23section and s. 295.57 and may only coordinate its environmental review to the extent
24consistent with the provisions of this section and s. 295.57. The department shall
25comment on any federal agency's environmental assessment or environmental

1impact statement associated with a mining project in accordance with s. NR 150.30,
2Wis. Adm. Code.
AB426-SSA2,102,11 3(5) Relationship to other laws. This section and s. 295.57 govern the
4department's obligations under ss. 1.11 and 1.12 with respect to a mining project.
5Sections 23.11 (5) and 23.40 and ss. NR 2.085, 2.09, and 2.157, Wis. Adm. Code, do
6not apply with respect to a mining project. The rest of ch. NR 2, Wis. Adm. Code, only
7applies with respect to a mining project to the extent that it does not conflict with this
8section and s. 295.57. Sections NR 150.24 and 150.25, Wis. Adm. Code, do not apply
9with respect to a mining project. The rest of ch. 150, Wis. Adm. Code, only applies
10with respect to a mining project to the extent that it does not conflict with this section
11and s. 295.57.
AB426-SSA2,102,14 12295.56 Exemptions. (1) The department may grant an exemption, as
13provided in this section, from any of the requirements of this subchapter applicable
14to any of the following:
AB426-SSA2,102,1615 (a) A mining permit application, including the mining plan, reclamation plan,
16and mining waste site feasibility study and plan of operation.
AB426-SSA2,102,1717 (b) A mining permit.
AB426-SSA2,102,1818 (c) Any other approval.
AB426-SSA2,102,22 19(2) (a) An applicant shall submit a request for an exemption in writing and
20shall describe the grounds for the exemption and provide documentation identifying
21the conditions requiring the exemption, the reasons for the exemption, and the
22reasonableness of the exemption.
AB426-SSA2,103,323 (b) An applicant may obtain an exemption only if the applicant submits the
24request no later than the 180th day after the application for the mining permit is
25administratively complete under s. 295.57 (2), unless the condition that is the basis

1for the requested exemption is not known to the applicant before that day, in which
2case the deadline is extended to the 20th day before the deadline under s. 295.57 (7)
3(a).
AB426-SSA2,103,94 (c) The department shall issue a decision on a request for an exemption no later
5than the 15th day after the day on which it received the request under par. (a).
6Subject to par. (b) and except as provided in par. (d), the department shall grant the
7exemption if it is consistent with the purposes of this subchapter and will not violate
8any applicable environmental law outside of this subchapter and if one of the
9following applies:
AB426-SSA2,103,1010 1. The exemption will not result in significant adverse environmental impacts.
AB426-SSA2,103,1411 2. The exemption will result in significant adverse environmental impacts, but
12the applicant will offset those impacts through mitigation, as provided in s. 295.60,
13through the measures provided in s. 295.605, or through the conservation measures
14provided in s. 295.61.
AB426-SSA2,103,1615 (d) 1. The department shall deny a request for an exemption if granting the
16exemption would violate federal law.
AB426-SSA2,103,2217 2. If federal law imposes a standard for an exemption that differs from the
18standard in par. (c) and that cannot be modified by state law, and if that standard has
19been approved by the federal government for use by the state through a delegation
20agreement, federally approved state implementation plan, or other program
21approval, then the department shall determine whether to grant the request for the
22exemption using the federal standard.
AB426-SSA2,103,24 23295.57 Application procedure. (1) Submission. (a) An applicant shall
24submit the application for a mining permit as provided in s. 295.47.
AB426-SSA2,104,6
1(b) The department and the state geologist shall protect as confidential any
2information, other than effluent data, contained in an application for a mining
3permit, upon a showing that the information is entitled to protection as a trade
4secret, as defined in s. 134.90 (1) (c), and any information relating to production or
5sales figures or to processes or production unique to the applicant or that would tend
6to adversely affect the competitive position of the applicant if made public.
AB426-SSA2,104,13 7(2) Determination of administrative completeness. (a) The department shall
8review an application for a mining permit and, within 30 days after the application
9is submitted, shall determine either that the application is complete or that
10additional information is needed. If the department determines that the application
11is complete, the department shall notify the applicant in writing of that fact within
12the 30-day period and the date on which the department sends the notice is the day
13on which the application is administratively complete.
AB426-SSA2,104,2114 (b) If the department determines under par. (a) that an application is
15incomplete, the department shall notify the applicant in writing and may make one
16request for additional information during the 30-day period specified in par. (a).
17Within 10 days after receiving additional requested information from the applicant,
18the department shall notify the applicant in writing as to whether it has received all
19of the requested information. The day on which the department sends the 2nd notice
20under this paragraph is the day on which the application is administratively
21complete.
AB426-SSA2,104,2422 (c) If the department fails to meet the 30-day time limit under par. (a) or the
2310-day time limit under par. (b), the application is administratively complete on the
24last day of the 30-day time limit or 10-day time limit.
AB426-SSA2,105,4
1(d) The department may request additional information needed to process a
2mining application from the applicant after the application is administratively
3complete, but the department may not delay the determination of administrative
4completeness based on a request for additional information.
AB426-SSA2,105,8 5(3) Notice of additional approvals. Within 30 days after the mining permit
6is administratively complete under sub. (2), the department shall notify the
7applicant in writing of any approval required for the construction or operation of the
8mining site that was not previously identified by the department.
AB426-SSA2,105,13 9(3m) Receipt of certain approvals. If a storm water discharge permit under
10s. 283.33 (1) (a) or a water quality certification under rules promulgated under subch.
11II of ch. 281 to implement 33 USC 1341 (a) is needed for a mining operation, the
12person applying for the mining permit may apply for and be issued the permit or
13certification.
AB426-SSA2,105,16 14(4) Public information and notice. (a) The department shall make available
15for review in the city, village, or town in which the proposed mining site is located,
16information concerning the proposed mining, including all of the following:
AB426-SSA2,105,1817 1. The application for the mining permit, including the mining plan,
18reclamation plan, and mining waste site feasibility study and plan of operation.
AB426-SSA2,105,1919 2. Any of the following relating to an approval other than the mining permit:
AB426-SSA2,105,2020 a. The application.
AB426-SSA2,105,2121 b. A draft approval.
AB426-SSA2,105,2222 c. Information or summaries relating to the approval.
AB426-SSA2,105,2523 3. The environmental impact statement, environmental impact report, and any
24additional supporting information used in the department's evaluation of the
25proposed mining.
AB426-SSA2,106,2
14. The department's analyses and preliminary determinations relating to any
2approval.
AB426-SSA2,106,103 (b) The department shall distribute a notice that describes the availability of
4the information under par. (a); the opportunity for written public comment, including
5an invitation for the submission of written comments by any person within 45 days
6after the notice is published; and the date, time, and location of the public
7informational hearing and that includes any additional information that a law
8concerning any approval requires to be provided. The department shall publish the
9notice as a Class I notice under ch. 985. The department shall also send the notice
10to all of the following:
AB426-SSA2,106,1211 1. The clerk of any city, village, town, or county with zoning jurisdiction over
12the proposed mining site.
AB426-SSA2,106,1413 2. The clerk of any city, village, town, or county within whose boundaries any
14portion of the proposed mining site is located.
AB426-SSA2,106,1615 3. The clerk of any city, village, or town, contiguous to any city, village, or town
16within whose boundaries any portion of the proposed mining site is located.
AB426-SSA2,106,1917 4. The main public library of each city, village, town, or county with zoning
18jurisdiction over the proposed mining site or within whose boundaries any portion
19of the proposed mining site is located.
AB426-SSA2,106,2120 5. Any regional planning commission for the area within which the proposed
21mining site lies.
AB426-SSA2,106,2422 6. Any state agency that the department knows is required to grant a permit
23or other authorization necessary for the construction or operation of the proposed
24mining project.
AB426-SSA2,107,4
17. The federal environmental protection agency, U.S. Army Corps of Engineers,
2and states potentially affected by the proposed discharge if a water discharge permit
3under ch. 283 or a water quality certification for a federal wetland under s. 295.60
4(4) is to be considered at the public informational hearing.
AB426-SSA2,107,75 8. The federal environmental protection agency and appropriate agencies in
6other states that may be affected if an air pollution control permit under ch. 285 is
7to be considered at the public informational hearing.
AB426-SSA2,107,108 9. If a water withdrawal permit under s. 295.61 for a withdrawal of surface
9water is to be considered at the public informational hearing, the persons specified
10in s. 30.18 (4) (a).
AB426-SSA2,107,1611 10. If an individual permit under s. 30.12 for a structure through which water
12transferred from the Great Lakes basin would be returned to the source watershed
13through a stream tributary to one of the Great Lakes is to be considered at the public
14informational hearing, the governing body of each city, village, and town through
15which the stream flows or that is adjacent to the stream downstream from the point
16at which the water would enter the stream.
AB426-SSA2,107,1717 11. Any person upon request.
AB426-SSA2,107,1818 12. The applicant.
AB426-SSA2,107,2119 13. Any other person to whom the department is required to give notice of any
20proposed determination, application, or hearing concerning an approval under the
21laws relating to the issuance of any approval or under s. 1.11.
AB426-SSA2,108,222 (c) The department shall coordinate the public comment period for the mining
23permit with the public comment period for any other approval for the mining
24operation, except that if an application for an approval is filed too late to allow public
25comment within the public comment period for the mining permit, the department

1shall issue separate notice, as described in par. (b), for the approval after the
2application is filed.
AB426-SSA2,108,16 3(5) Informational hearing. The department shall hold a public informational
4hearing before issuing or denying a mining permit and not less than 30 days after
5publishing the notice under sub. (4) (b). The department shall hold the public
6informational hearing in the county where the majority of the proposed mining site
7is located. The department shall hold a single public informational hearing covering
8the mining permit, all other approvals, and the environmental impact statement,
9except that if an application for an approval is filed too late to allow the application
10to be considered at the public informational hearing for the mining permit, the
11department shall hold a separate public informational hearing on the approval in the
12county where the proposed site is located not less than 30 days after publishing the
13notice under sub. (4) (b) for the approval. The public informational hearing under
14this subsection is not a contested case hearing under ch. 227. At the hearing, the
15department shall take testimony on all of the following with regard to any proposed
16withdrawal of groundwater or surface water:
AB426-SSA2,108,1817 (a) The public rights in any body of water and the related environment that may
18be injured by the proposed withdrawal of groundwater or surface water.
AB426-SSA2,108,2019 (b) The public benefits provided by increased employment, economic activity,
20and tax revenues from the proposed mining operation.
AB426-SSA2,108,2221 (c) The direct and indirect social and economic costs and benefits of the
22proposed mining operation.
AB426-SSA2,108,2423 (d) Whether the proposed withdrawal of groundwater or surface water will
24consume nonsurplus water.
AB426-SSA2,108,2525 (e) The rights of competing users of the groundwater or surface water.
AB426-SSA2,109,2
1(f) Any other water withdrawal issues identified by the department as relevant
2to the decision of whether to issue or deny a permit.
AB426-SSA2,109,6 3(6) Summary. After considering the comments received under subs. (4) and (5)
4and before acting on the application for the mining permit, the department shall
5prepare a summary of the comments and the department's response to the
6comments.
AB426-SSA2,109,14 7(7) Deadline for acting on mining permit application. (a) No more than 420
8days after the day on which the application for a mining permit is administratively
9complete under sub. (2), the department shall approve the application, and issue a
10mining permit, or deny the application, in accordance with s. 295.58, unless the
11department and the applicant agree to extend the deadline. The department and the
12applicant may agree to not more than one extension and that extension may not
13exceed 60 days. The department and the applicant may enter into an extension only
14if one of the following applies:
AB426-SSA2,109,1615 1. An extension is necessary to enable the department and the U.S. Army Corps
16of Engineers to jointly prepare their environmental impact statements.
AB426-SSA2,109,1817 2. New information or a change to the mining proposal necessitates additional
18time to review the application.
AB426-SSA2,109,2119 (b) If the department does not comply with the deadline under par. (a),
20including any extension agreed to by the applicant, the department shall refund the
21fees under s. 295.73 (3) (a) and (d) that were paid by the applicant.
AB426-SSA2,110,222 (c) If the department does not comply with the deadline under par. (a),
23including any extension agreed to by the applicant, the applicant may bring an action
24for mandamus to compel the department to approve or deny the application.
25Notwithstanding s. 814.04 (1), in an action under this paragraph the court shall

1award the applicant its costs, including reasonable attorney fees, if it determines
2that the department did not comply with the deadline under par. (a).
AB426-SSA2,110,8 3(8) Deadline for acting on other approvals. (a) Except as provided in par.
4(c), if an applicant files an application for an approval other than a mining permit
5no later than 60 days after the day on which the application for the mining permit
6is administratively complete under sub. (2), the department shall approve the
7application, and issue the approval or deny the application no later than the deadline
8under sub. (7) (a), including any extension agreed to by the applicant.
AB426-SSA2,110,159 (b) Except as provided in par. (c) if an applicant files an application for an
10approval other than a mining permit more than 60 days after the day on which the
11application for the mining permit is administratively complete under sub. (2), the
12deadline for acting on the application is extended beyond the deadline under sub. (7)
13(a), including any extension agreed to by the applicant, by the number of days beyond
14the 60th day after the day on which the application for the mining permit is
15administratively complete that the applicant files the application for the approval.
AB426-SSA2,110,1716 (c) Paragraphs (a) and (b) do not apply to the application for an air pollution
17control permit under s. 285.62.
AB426-SSA2,110,2118 (d) The department shall incorporate an approval other than a mining permit
19into a single document with the mining permit, unless the application for the
20approval was filed more than 60 days after the day on which the application for the
21mining permit is administratively complete under sub. (2).
AB426-SSA2,111,2 22(8m) Submission of technical review to Great Lakes regional body. If an
23applicant files an application under s. 281.346 for an approval for a withdrawal of
24surface water or groundwater that is subject to regional review or council approval,
25the department shall provide its technical review, as defined in s. 281.346 (1) (u), to

1the regional body, as defined in s. 281.346 (1) (q), no later than 90 days after the
2applicant files the application for the approval.
Loading...
Loading...