SB1,20
12Section
20. 30.025 (4m) of the statutes is created to read:
SB1,32,2013
30.025
(4m) Procedure for a single permit application. A person proposing
14to construct a utility facility that is related to mining, as defined in s. 295.41 (26), and
15for which not more than one permit is required, may submit an application for that
16single permit with the department in the same manner as a combined application
17for permits may be submitted under sub. (1s). If the applicant elects to submit the
18application in the same manner as a combined application for permits, the
19procedures under this section that apply to a combined application for permits shall
20apply to that application for a single permit.
SB1,21
21Section
21. 30.12 (3m) (c) (intro.) of the statutes is amended to read:
SB1,32,2422
30.12
(3m) (c) (intro.) The department shall issue an individual permit to a
23riparian owner for a structure or a deposit pursuant to an application under par. (a)
24if the department finds that all of the following
apply requirements are met:
SB1,22
1Section
22. 30.123 (8) (c) of the statutes is renumbered 30.123 (8) (c) (intro.)
2and amended to read:
SB1,33,53
30.123
(8) (c) (intro.) The department shall issue an individual permit
4pursuant to an application under par. (a) if the department finds that
the all of the
5following requirements are met:
SB1,33,6
61. The bridge or culvert will not materially obstruct navigation
,.
SB1,33,8
72. The bridge or culvert will not materially reduce the effective flood flow
8capacity of a stream
, and.
SB1,33,9
93. The bridge or culvert will not be detrimental to the public interest.
SB1,23
10Section
23. 30.133 (2) of the statutes is amended to read:
SB1,33,1611
30.133
(2) This section does not apply to riparian land located within the
12boundary of any hydroelectric project licensed or exempted by the federal
13government, if the conveyance is authorized under any license, rule or order issued
14by the federal agency having jurisdiction over the project.
This section does not apply
15to riparian land that is associated with an approval required for bulk sampling or
16mining that is required under subch. III of ch. 295.
SB1,24
17Section
24. 30.19 (4) (c) (intro.) of the statutes is amended to read:
SB1,33,2018
30.19
(4) (c) (intro.) The department shall issue an individual permit pursuant
19to an application under par. (a) if the department finds that all of the following
apply 20requirements are met:
SB1,25
21Section
25. 30.195 (2) (c) (intro.) of the statutes is amended to read:
SB1,33,2422
30.195
(2) (c) (intro.) The department shall issue an individual permit applied
23for under this section to a riparian owner if the department determines that all of the
24following
apply requirements are met:
SB1,26
25Section
26. 31.23 (3) (e) of the statutes is created to read:
SB1,34,3
131.23
(3) (e) This subsection does not apply to a bridge that is constructed,
2maintained, or operated in association with mining or bulk sampling that is subject
3to subch. III of ch. 295.
SB1,27
4Section
27. 32.02 (12) of the statutes is amended to read:
SB1,34,85
32.02
(12) Any person operating a plant which creates waste material which,
6if released without treatment would cause stream pollution, for the location of
7treatment facilities. This subsection does not apply to a person
licensed with a
8permit under ch. 293
or subch. III of ch. 295.
SB1,28
9Section
28. 70.375 (1) (as) of the statutes is amended to read:
SB1,34,1210
70.375
(1) (as) "Mine" means an excavation in or at the earth's surface made
11to extract metalliferous minerals for which a permit has been issued under s. 293.49
12or 295.58.
SB1,29
13Section
29. 70.375 (1) (bm) of the statutes is amended to read:
SB1,34,2114
70.375
(1) (bm) "Mining-related purposes" means activities which are directly
15in response to the application for a mining permit under s. 293.37
or 295.47; directly
16in response to construction, operation, curtailment of operation or cessation of
17operation of a metalliferous mine site; or directly in response to conditions at a
18metalliferous mine site which is not in operation. "Mining-related purposes" also
19includes activities which anticipate the economic and social consequences of the
20cessation of mining. "Mining-related purposes" also includes the purposes under s.
2170.395 (2) (g).
SB1,30
22Section
30. 70.375 (4) (h) of the statutes is amended to read:
SB1,34,2423
70.375
(4) (h) The cost of premiums for bonds required under s. 293.51
, 295.45
24(5), or 295.59.
SB1,31
25Section
31. 70.38 (2) of the statutes is amended to read:
SB1,35,4
170.38
(2) Combined reporting. If the same person extracts metalliferous
2minerals from different sites in this state, the net proceeds for each site for which a
3permit has been issued under s. 293.49
or 295.58 shall be reported separately for the
4purposes of computing the amount of the tax under s. 70.375 (5).
SB1,32
5Section
32. 70.395 (1e) of the statutes is amended to read:
SB1,35,136
70.395
(1e) Distribution. Fifteen days after the collection of the tax under ss.
770.38 to 70.39, the department of administration, upon certification of the
8department of revenue, shall transfer the amount collected in respect to mines not
9in operation on November 28, 1981, to the investment and local impact fund
, except
10that the department of administration shall transfer 60 percent of the amount
11collected from each person extracting ferrous metallic minerals to the investment
12and local impact fund and 40 percent of the amount collected from any such person
13to the economic development fund.
SB1,33
14Section
33. 70.395 (2) (dc) 1. of the statutes is amended to read:
SB1,35,1915
70.395
(2) (dc) 1. Each person intending to submit an application for a mining
16permit
under s. 293.37 or 295.47 shall pay
$50,000 $75,000 to the department of
17revenue for deposit in the investment and local impact fund at the time that the
18person notifies the department of natural resources under s. 293.31 (1)
or 295.465 19of that intent.
SB1,34
20Section
34. 70.395 (2) (dc) 2. of the statutes is amended to read:
SB1,35,2321
70.395
(2) (dc) 2. A person making a payment under subd. 1. shall pay an
22additional
$50,000 $75,000 upon notification by the board that the board has
23distributed 50% of the payment under subd. 1.
SB1,35
24Section
35. 70.395 (2) (dc) 3. of the statutes is amended to read:
SB1,36,4
170.395
(2) (dc) 3. A person making a payment under subd. 2. shall pay an
2additional
$50,000 $75,000 upon notification by the board that the board has
3distributed all of the payment under subd. 1. and 50% of the payment under subd.
42.
SB1,36
5Section
36. 70.395 (2) (dc) 4. of the statutes is amended to read:
SB1,36,106
70.395
(2) (dc) 4. Six months after the signing of a local agreement under s.
7293.41
or 295.443 for the proposed mine for which the payment is made, the board
8shall refund any funds paid under this paragraph but not distributed under par. (fm)
9from the investment and local impact fund to the person making the payment under
10this paragraph.
SB1,37
11Section
37. 70.395 (2) (fm) of the statutes is amended to read:
SB1,36,1912
70.395
(2) (fm) The board may distribute a payment received under par. (dc)
13to a county, town, village, city, tribal government or local impact committee
14authorized under s. 293.41 (3)
or 295.443 only for legal counsel, qualified technical
15experts in the areas of transportation, utilities, economic and social impacts,
16environmental impacts and municipal services and other reasonable and necessary
17expenses incurred by the recipient that directly relate to the good faith negotiation
18of a local agreement under s. 293.41
or 295.443 for the proposed mine for which the
19payment is made.
SB1,38
20Section
38. 70.395 (2) (h) 1. of the statutes is amended to read:
SB1,36,2421
70.395
(2) (h) 1. Distribution shall first be made to those municipalities in
22which metalliferous minerals are extracted or were extracted within 3 years
23previous to December 31 of the current year, or in which a permit has been issued
24under s. 293.49
or 295.58 to commence mining;
SB1,39
25Section
39. 70.395 (2) (hg) of the statutes is amended to read:
SB1,37,3
170.395
(2) (hg) The board shall, by rule, establish fiscal guidelines and
2accounting procedures for the use of payments under pars. (d), (f), (fm) and (g), sub.
3(3) and
s. ss. 293.65 (5)
and 295.61 (9).
SB1,40
4Section
40. 70.395 (2) (hr) of the statutes is amended to read:
SB1,37,85
70.395
(2) (hr) The board shall, by rule, establish procedures to recoup
6payments made, and to withhold payments to be made, under pars. (d), (f), (fm) and
7(g), sub. (3) and
s. ss. 293.65 (5)
and 295.61 (9) for noncompliance with this section
8or rules adopted under this section.
SB1,41
9Section
41. 70.395 (2) (hw) of the statutes is amended to read:
SB1,37,1810
70.395
(2) (hw) A recipient of a discretionary payment under par. (f) or (g), sub.
11(3) or
s. ss. 293.65 (5)
and 295.61 (9) or any payment under par. (d) that is restricted
12to mining-related purposes who uses the payment for attorney fees may do so only
13for the purposes under par. (g) 6. and for processing mining-related permits or other
14approvals required by the municipality. The board shall recoup or withhold
15payments that are used or proposed to be used by the recipient for attorney fees
16except as authorized under this paragraph. The board may not limit the hourly rate
17of attorney fees for which the recipient uses the payment to a level below the hourly
18rate that is commonly charged for similar services.
SB1,42
19Section
42. 87.30 (2) of the statutes is renumbered 87.30 (2) (a) and amended
20to read:
SB1,38,421
87.30
(2) (a)
Every Except as provided in par. (b), every structure, building, fill,
22or development placed or maintained within any floodplain in violation of a zoning
23ordinance adopted under this section, or s. 59.69, 61.35 or 62.23 is a public nuisance
24and the creation thereof may be enjoined and maintenance thereof may be abated by
25action at suit of any municipality, the state or any citizen thereof. Any person who
1places or maintains any structure, building, fill or development within any
2floodplain in violation of a zoning ordinance adopted under this section, or s. 59.69,
361.35 or 62.23 may be fined not more than $50 for each offense. Each day during
4which such violation exists is a separate offense.
SB1,43
5Section
43. 87.30 (2) (b) of the statutes is created to read:
SB1,38,106
87.30
(2) (b) Paragraph (a) does not apply to a structure, building, fill, or
7development placed or maintained as part of a mining operation covered by a mining
8permit under s. 295.58 except to the extent that regulation of the placement or
9maintenance of the structure, building, fill, or development is required for
10compliance with a floodplain zoning ordinance as provided under s. 295.607 (3).
SB1,44
11Section
44. 107.001 (1) of the statutes is amended to read:
SB1,38,1812
107.001
(1) "Exploration mining lease" means any lease, option to lease, option
13to purchase or similar conveyance entered into for the purpose of determining the
14presence, location, quality or quantity of
metalliferous nonferrous metallic minerals
15or for the purpose of mining, developing or extracting
metalliferous nonferrous
16metallic minerals, or both
under ch. 293. Any lease, option to lease, option to
17purchase or similar conveyance entered into by a mining company is rebuttably
18presumed to be an exploration mining lease.
SB1,45
19Section
45. 107.001 (2) of the statutes is repealed.
SB1,46
20Section
46. 107.01 (intro.) of the statutes is amended to read:
SB1,38,24
21107.01 Rules governing mining rights. (intro.) Where there is no contract
22between the parties or terms established by the landlord to the contrary the following
23rules and regulations shall be applied to mining contracts and leases for the digging
24of
ores and nonferrous metallic minerals:
SB1,47
25Section
47. 107.01 (2) of the statutes is amended to read:
SB1,39,9
1107.01
(2) The discovery of a crevice or range containing
ores or minerals 2nonferrous metallic minerals shall entitle the discoverer to the
ores or minerals 3nonferrous metallic minerals pertaining thereto, subject to the rent due the
4discoverer's landlord, before as well as after the
ores or minerals nonferrous metallic
5minerals are separated from the freehold; but such miner shall not be entitled to
6recover any
ores or minerals nonferrous metallic minerals or the value thereof from
7the person digging on the miner's range in good faith and known to be mining thereon
8until the miner shall have given notice of the miner's claim; and the miner shall be
9entitled to the
ores or minerals nonferrous metallic minerals dug after such notice.
SB1,48
10Section
48. 107.02 of the statutes is amended to read:
SB1,40,5
11107.02 Mining statement; penalty. When there is no agreement between the
12parties to any mining lease, license or permit, to mine or remove
ore nonferrous
13metallic minerals from any lands in this state, regulating the method of reporting
14the amount of
ore nonferrous metallic minerals taken, the person mining and
15removing the
ore or ores nonferrous metallic minerals shall keep proper and correct
16books, and therefrom to make and deliver by or before the fifteenth day of each month
17to the lessor, owner or person entitled thereto, a detailed statement covering the
18operations of the preceding month. The statement shall show the total amount of
19tons or pounds of each kind of
ore nonferrous metallic minerals produced; if sold, then
20to whom sold, giving the date of sale, date of delivery to any railroad company,
21naming the company, and the station where delivered or billed for shipment; the
22name and address of the purchaser; the price per ton at which sold and the total value
23of each kind of
ore nonferrous metallic minerals so sold. The books shall be always
24open to any owner, lessor, licensor or stockholder, if the owner, lessor or licensor is
25a corporation, and to any person or stockholder interested in any such mining
1operations, for the purpose of inspection and taking copies thereof or abstracts
2therefrom. Any person and every officer, agent or employee of any thereof, who
3violates this section, or who makes any false or incomplete entries on any such books
4or statements, shall be fined not less than $100 or imprisoned in the county jail for
5not more than 3 months or both.
SB1,49
6Section
49. 107.03 of the statutes is amended to read:
SB1,40,16
7107.03 Conflicting claims. In case of conflicting claims to a crevice or range
8bearing
ores or nonferrous metallic minerals the court may continue any action to
9enforce a claim or grant any necessary time for the purpose of allowing parties to
10prove up their mines or diggings if it satisfactorily appears necessary to the ends of
11justice. In such case the court or judge may appoint a receiver and provide that the
12mines or diggings be worked under the receiver's direction, subject to the order of the
13court, in such manner as best ascertains the respective rights of the parties. The
ores
14or nonferrous metallic minerals raised by either party pending the dispute shall be
15delivered to the receiver, who may, by order of the court or judge, pay any rent or other
16necessary expenses therefrom.
SB1,50
17Section
50. 107.04 of the statutes is amended to read:
SB1,41,4
18107.04 Lessee's fraud; failure to work mine. Any miner who conceals or
19disposes of any
ores or nonferrous metallic minerals or mines or diggings for the
20purpose of defrauding the lessor of rent or who neglects to pay any rent on
ores or 21nonferrous metallic minerals raised by the miner for 3 days after the notice thereof
22and claim of the rent, shall forfeit all right to his or her mines, diggings or range; and
23the landlord after the concealment or after 3 days have expired from the time of
24demanding rent, may proceed against the miner to recover possession of the mines
25or diggings in circuit court as in the case of a tenant holding over after the
1termination of the lease. If a miner neglects to work his or her mines or diggings
2according to the usages of miners, without reasonable excuse, he or she shall likewise
3forfeit the mines or diggings and the landlord may proceed against the miner in like
4manner to recover possession of the mines or diggings.
SB1,51
5Section
51. 107.11 of the statutes is amended to read:
SB1,41,17
6107.11 Account of ore nonferrous metallic minerals received. Every
7person operating a metal recovery system and every purchaser of
ores and 8nonferrous metallic minerals shall keep a substantially bound book, ruled into
9suitable columns, in which shall be entered from day to day, as
ores or nonferrous
10metallic minerals are received, the following items: the day, month and year when
11received; the name of the person from whom purchased; the name of the person by
12whom hauled and delivered; name of the owner of the land from which the
ores or 13nonferrous metallic minerals were obtained, or if not known, the name of the
14diggings or some distinct description of the land. The bound book shall be kept at the
15furnace or at the usual place of business of such person or purchaser or his or her
16agent in this state, and shall be open to authorized representatives of the department
17of revenue at reasonable times for inspection and taking extracts.
SB1,52
18Section
52. 107.12 of the statutes is amended to read:
SB1,41,25
19107.12 Penalty. If any person operating a metal recovery system or purchaser
20of
ores and nonferrous metallic minerals or the agent of any such person or purchaser
21doing business fails to keep such a book or to make such entries as required under
22s. 107.11 or unreasonably refuses to show the book for inspection or taking extracts
23or makes false entries in the book he or she shall forfeit $10 for each offense, one-half
24to the use of the prosecutor; and each day such failure or refusal continues shall be
25deemed a distinct and separate offense.
SB1,53
1Section
53. 107.20 (1) of the statutes is amended to read:
SB1,42,132
107.20
(1) Any provision of an exploration mining lease entered into after April
325, 1978, granting an option or right to determine the presence, location, quality or
4quantity of
metalliferous nonferrous metallic minerals shall be limited to a term not
5exceeding 10 years from the date on which the exploration mining lease is recorded
6in the office of the register of deeds of the county where the property is located, except
7that any provision of an exploration mining lease entered into after April 25, 1978,
8granting an option or right to determine the quality and quantity of
metalliferous 9nonferrous metallic minerals under a prospecting permit shall be limited to a term
10not exceeding 10 years from the date that the lessee applies for a prospecting permit
11under s. 293.35, if the lessee applies for the prospecting permit within 10 years from
12the date on which the exploration mining lease is recorded in the office of the register
13of deeds of the county where the property is located.
SB1,54
14Section
54. 107.20 (2) of the statutes is amended to read:
SB1,42,1915
107.20
(2) Any provision of an exploration mining lease entered into after April
1625, 1978
, granting an option or right to develop or extract
metalliferous nonferrous
17metallic minerals shall be limited to a term not exceeding 50 years from the date on
18which the exploration mining lease is recorded in the office of the register of deeds
19of the county where the property is located.
SB1,55
20Section
55. 107.30 (8) of the statutes is amended to read:
SB1,42,2521
107.30
(8) "Mining" or "mining operation"
has the meaning set forth in s. 293.01
22(9) means all or part of the process involved in the mining of metallic minerals, other
23than for exploration or prospecting, including commercial extraction,
24agglomeration, beneficiation, construction of roads, removal of overburden, and the
25production of refuse.
SB1,56
1Section
56. 107.30 (15) of the statutes is amended to read:
SB1,43,142
107.30
(15) "Prospecting"
has the meaning set forth in s. 293.01 (18) means
3engaging in the examination of an area for the purpose of determining the quality
4and quantity of minerals, other than for exploration but including the obtaining of
5an ore sample, by such physical means as excavating, trenching, construction of
6shafts, ramps, and tunnels and other means, other than for exploration, which the
7department of natural resources, by rule, identifies, and the production of
8prospecting refuse and other associated activities. "Prospecting" does not include
9such activities when the activities are, by themselves, intended for and capable of
10commercial exploitation of the underlying ore body. The fact that prospecting
11activities and construction may have use ultimately in mining, if approved, does not
12mean that prospecting activities and construction constitute mining within the
13meaning of sub. (8), provided such activities and construction are reasonably related
14to prospecting requirements.
SB1,57
15Section
57. 107.30 (16) of the statutes is amended to read:
SB1,43,1816
107.30
(16) "Prospecting site"
has the meaning set forth in s. 293.01 (21) means
17the lands on which prospecting is actually conducted as well as those lands on which
18physical disturbance will occur as a result of such activity.
SB1,58
19Section
58. 160.19 (12) of the statutes is amended to read:
SB1,44,220
160.19
(12) The requirements in this section shall not apply to rules governing
21an activity regulated under ch. 293
or subch. III of ch. 295, or to a solid waste facility
22regulated under subch. III of ch. 289 which is part of an activity regulated under ch.
23293
or subch. III of ch. 295, except that the department may promulgate new rules
24or amend rules governing this type of activity, practice or facility if the department
1determines that the amendment or promulgation of rules is necessary to protect
2public health, safety or welfare.
SB1,59
3Section
59. 196.491 (3) (a) 3. b. of the statutes is amended to read:
SB1,44,184
196.491
(3) (a) 3. b.
Within
Except as provided under subd. 3. c., within 20
5days after the department provides a listing specified in subd. 3. a. to a person, the
6person shall apply for the permits and approvals identified in the listing. The
7department shall determine whether an application under this subd. 3. b. is complete
8and, no later than 30 days after the application is filed, notify the applicant about
9the determination. If the department determines that the application is incomplete,
10the notice shall state the reason for the determination. An applicant may
11supplement and refile an application that the department has determined to be
12incomplete. There is no limit on the number of times that an applicant may refile
13an application under this subd. 3. b. If the department fails to determine whether
14an application is complete within 30 days after the application is filed, the
15application shall be considered to be complete. The department shall complete action
16on an application under this subd. 3. b. for any permit or approval that is required
17prior to construction of a facility within 120 days after the date on which the
18application is determined or considered to be complete.
SB1,60
19Section
60. 196.491 (3) (a) 3. c. of the statutes is created to read:
SB1,44,2320
196.491
(3) (a) 3. c. The 20-day deadline specified in subd. 3. b. for applying
21for the applicable permits and approvals specified in the listing provided by the
22department does not apply to a person proposing to construct a utility facility for
23ferrous mineral mining and processing activities governed by subch. III of ch. 295.
SB1,61
24Section
61. 196.491 (4) (b) 2. of the statutes is amended to read:
SB1,45,8
1196.491
(4) (b) 2. The person shows to the satisfaction of the commission that
2the person reasonably anticipates, at the time that construction of the equipment or
3facilities commences, that on each day that the equipment and facilities are in
4operation the person will consume no less than 70% of the aggregate kilowatt hours
5output from the equipment and facilities in manufacturing processes at the site
6where the equipment and facilities are located
or in ferrous mineral mining and
7processing activities governed by subch. III of ch. 295 at the site where the equipment
8and facilities are located.
SB1,62
9Section
62. 227.483 (3) (c) of the statutes is created to read:
SB1,45,1310
227.483
(3) (c) If the proceeding relates to mining for ferrous minerals, as
11defined in s. 295.41 (18), that the petition, claim, or defense was commenced, used,
12or continued primarily for the purpose of causing delay to an activity authorized
13under a license that is the subject of the hearing.
SB1,63
14Section
63. 238.14 of the statutes is created to read: