2023 - 2024 LEGISLATURE
May 8, 2023 - Introduced by Senators Tomczyk, Cowles and Testin, cosponsored
by Representatives Steffen, Edming, Bodden, Green, Maxey, Mursau,
Plumer, Rettinger, Schmidt, Spiros, Swearingen, VanderMeer and Wittke.
Referred to Committee on Transportation and Local Government.
SB270,1,5
1An Act to renumber 84.063 (1) (a) and 84.063 (1) (b);
to amend 84.01 (31) and
284.062 (1) (L); and
to create 84.063 (1) (c), 84.063 (1) (e), 84.063 (1) (g) and
384.063 (4m) of the statutes;
relating to: damages claims relating to delayed
4relocation of utilities in a highway right-of-way and modifying administrative
5rules promulgated by the Department of Transportation.
Analysis by the Legislative Reference Bureau
This bill creates a process for a highway improvement contractor to seek
damages for project delays that are the result of an uncompleted relocation or
adjustment of a utility facility located in the right-of-way of the highway. “Utility
facility” means any pipe, pipeline, duct, wire line, conduit, pole, tower, equipment,
or other structure used for transmission, distribution, or delivery of electrical power,
light, heat, water, gas, sewer, telegraph, or telecommunication services.
Under current law, if a utility facility is within the right-of-way of a proposed
highway project, the Department of Transportation must notify the owner, who must
then provide DOT with a description and general location of each utility facility. DOT
must then provide the owner with a set of plans for the proposed project. The owner
must submit a work plan to DOT proposing any relocations or adjustments to utility
facilities required by the proposed project. DOT must review work plans for
compliance with permit requirements and, once approved, notify the owner when
utility facility relocation work may begin.
Under the bill, a contractor that incurs costs as a result of a utility relocation
delay may file a utility delay damages claim with the department. “Utility relocation
delay” means a change in operations of a contractor or the rescheduling of work by
a contractor that is caused by the uncompleted relocation or adjustment of a utility
facility located in the right-of way, regardless of whether the relocation or
adjustment of the utility facility is identified in a plan.
The bill requires DOT to notify the owner of the relevant utility facility upon
receipt of a damages claim. The owner may respond to the claim by providing
additional information related to the claim. DOT must consider all information
provided and, if DOT determines that a utility relocation delay occurred, must
compensate the contractor for costs incurred as a result.
Under the bill, if a utility relocation delay was caused by a utility facility
owner's failure to complete a relocation in accordance with an approved plan, the
utility facility owner is liable to DOT for any compensation paid to a contractor as
a result of a utility relocation delay. The owner must make payment to DOT within
60 days, subject to the right to appeal DOT's determination. If the owner fails to
make the required payment, DOT may seek remedy by filing a civil suit against the
owner.
The bill requires DOT to submit a report to the Joint Committee on Finance
within four years providing specified information about utility relocation damages
claims received by DOT. Within six months of receipt of the report, JFC must make
a recommendation as to whether the process created by the bill should be amended
or repealed.
For further information see the state fiscal estimate, which will be printed as
an appendix to this bill.
The people of the state of Wisconsin, represented in senate and assembly, do
enact as follows:
SB270,1
1Section
1. 84.01 (31) of the statutes is amended to read:
SB270,3,22
84.01
(31) Accommodation of utility facilities within highway rights-of-way. 3Notwithstanding ss. 84.06 (4), 84.063, 84.065, and 84.093, the department may, upon
4finding that it is feasible and advantageous to the state, negotiate and enter into an
5agreement to accept any plant or equipment used for the conveyance, by wire, optics,
6radio signal, or other means, of voice, data, or other information at any frequency
7over any part of the electromagnetic spectrum, or to accept any services associated
8with the collection, storage, forwarding, switching, and delivery incidental to such
9communication, as payment for the accommodation of a utility facility, as defined in
10s. 84.063 (1)
(b) (f), within a highway right-of-way. Any agreement under this
1subsection is exempt from ss. 16.70 to 16.75, 16.755 to 16.82, and 16.85 to 16.89, but
2ss. 16.528, 16.752, and 16.754 apply to such agreement.
SB270,2
3Section
2. 84.062 (1) (L) of the statutes is amended to read:
SB270,3,54
84.062
(1) (L) “Project” means a project involving a highway improvement, as
5defined in s. 84.063 (1)
(a) (d).
SB270,3
6Section 3
. 84.063 (1) (a) of the statutes is renumbered 84.063 (1) (d).
SB270,4
7Section 4
. 84.063 (1) (b) of the statutes is renumbered 84.063 (1) (f).
SB270,5
8Section
5. 84.063 (1) (c) of the statutes is created to read:
SB270,3,109
84.063
(1) (c) “Contractor” means a person who is seeking or has entered into
10a highway improvement contract with the department under s. 84.06.
SB270,6
11Section
6. 84.063 (1) (e) of the statutes is created to read:
SB270,3,1212
84.063
(1) (e) “Owner” means an owner of a utility facility.
SB270,7
13Section 7
. 84.063 (1) (g) of the statutes is created to read:
SB270,3,1814
84.063
(1) (g) “Utility relocation delay” means a change in operations of a
15contractor or the rescheduling of work by a contractor that is caused by the
16uncompleted relocation or adjustment of a utility facility located in the right-of way,
17regardless of whether the relocation or adjustment of the utility facility is identified
18in a plan under sub. (3).
SB270,8
19Section
8. 84.063 (4m) of the statutes is created to read:
SB270,3,2220
84.063
(4m) Utility relocation delay damages claims. (a) A contractor that
21incurs costs as a result of a utility relocation delay may file a utility relocation delay
22damages claim with the department.
SB270,3,2523
(b) The department shall notify the owner of the relevant utility facility upon
24receipt of a claim under par. (a). The owner may respond to the claim by providing
25additional information related to the claim.
SB270,4,7
1(c) The department shall consider all information provided by the contractor
2under par. (a) and, if applicable, the owner under par. (b). If the department
3determines that a utility relocation delay occurred, the department shall compensate
4the contractor for costs incurred as a result of the utility relocation delay and may
5not impose liquidated damages. The amount of compensation under this paragraph
6shall be calculated and paid in accordance with the department's standard
7specifications for compensable delays.
SB270,4,168
(d) 1. If a utility relocation delay identified under par. (c) was caused by an
9owner's failure to complete a relocation in accordance with a work plan approved by
10the department under sub. (3), the owner shall be liable to the department for
11compensation paid to a contractor under par. (c). An owner shall not be liable under
12this subdivision when the failure to complete a relocation is caused by circumstances
13outside of the owner's reasonable control. The department may not assess against
14the owner any fees, costs, or expenses in excess of the compensation paid under par.
15(c). Subject to subd. 2., an owner shall make payment to the department no later than
1660 days after receiving notice of the amount owed.
SB270,4,2017
2. An owner may appeal the decision of the department under subd. 1. as
18provided in s. 227.42 if the owner previously responded to the claim as provided in
19par. (b). Any amount that the owner owes to the department under subd. 1. shall be
20stayed pending the appeal.
SB270,4,2321
3. If an owner fails to make payment of amounts owed to the department under
22this paragraph, the department may seek remedy by filing a civil suit against the
23owner.
SB270,5,3
1(e) The department may not consider amounts paid or owed under par. (d) when
2making a determination on an owner's permit application, amounts paid to the
3owner under par. (4) (a) or s. 84.09, or any other matter involving the owner.
SB270,9
4Section
9. Trans 220.06 (7) (c) of the administrative code is amended to read:
SB270,5,215
Trans 220.06
(7) (c)
If the owner fails to provide a work plan as provided in s.
6Trans 220.05, or fails to complete the alteration or relocation of its facilities in
7accordance with the work plan approved by the department as provided in s. Trans
8220.05, the owner shall be liable to the contractor for all delay costs and liquidated
9damages incurred by the contractor which are The department shall compensate the
10contractor for any costs caused by or
which grow out of failure of the owner to carry
11out and complete its work in accordance with the approved work plan
attributed to
12a utility relocation delay as defined in s. 84.063 (1) (g), Stats., and may not impose
13liquidated damages. The owner shall be liable, subject to the right to appeal the
14decision of the department under s. 227.42, Stats., for compensation paid by the
15department to a contractor under this paragraph for a utility relocation delay, as
16defined in s. 84.063 (1) (g), Stats., that was caused by the owner's failure to complete
17a relocation in accordance with the work plan approved by the department as
18provided in s. Trans 220.05. The owner shall not be liable to the department for any
19delay if the owner's failure to complete the relocation in accordance with the work
20plan approved by the department was due to circumstances outside of the owner's
21reasonable control.
SB270,10
22Section
10.
Nonstatutory provisions.
SB270,6,223
(1) No later than the last day of the first month following the effective date of
24this subsection, the department of transportation shall update its standard
1specifications for compensable delays to conform with the requirements under s.
284.063 (4m).
SB270,6,103
(2) No later than 4 years after the effective date of this subsection, the
4department of transportation shall submit a report to the joint committee on finance
5detailing utility relocation damages claims received by the department, including
6total claims received, claims denied, payments made to contractors, damages
7recovered from owners, the length and impact of delays, and net expenditures by the
8department. No later than 6 months after receipt of the report under this subsection,
9the joint committee on finance shall make a recommendation to the legislature as to
10whether s. 84.063 (4m) should be amended or repealed.