ATCP 54.04(1)(j) (j) Remarks indicating operational problems encountered, such as equipment failure, weather conditions not conducive to successful conduct of the operation, personnel problems, and others.
ATCP 54.04(2) (2)Summary records. Each permittee shall prepare a monthly summary listing the following totals from daily logs:
ATCP 54.04(2)(a) (a) Days during each month that the operation was conducted.
ATCP 54.04(2)(b) (b) Time of operation.
ATCP 54.04(2)(c) (c) Amount of each kind of agent used.
ATCP 54.04(2)(d) (d) Average rate of dispersal for each kind of agent used.
ATCP 54.04(2)(e) (e) Time of operation of radar.
ATCP 54.04(2)(f) (f) Days of each type of cloud treated.
ATCP 54.04(3) (3)Weather records. Each permittee shall obtain and retain copies of all daily precipitation and weather records available from national weather service stations in the target area, and such other weather information as may be readily available from other reliable sources in the target area.
ATCP 54.04(4) (4)Record of participants. Each permittee shall keep a roster of the names and addresses of all employees or other persons participating or assisting in the conduct of operations for which a permit was issued.
ATCP 54.04(5) (5)Retention and inspection of records. Records prescribed under this section shall be maintained for a period of 3 years and be readily available for inspection by the department.
ATCP 54.04 History History: Cr. Register, September, 1979, No. 285, eff. 10-1-79.
ATCP 54.05 ATCP 54.05Reports.
ATCP 54.05(1) (1)Monthly report. Within 10 days after the end of each calendar month, the permittee shall submit a report to the department consisting of:
ATCP 54.05(1)(a) (a) A copy of the summary record prepared under s. ATCP 54.04 (2).
ATCP 54.05(1)(b) (b) A copy of the roster prepared under s. ATCP 54.04 (4), listing the names and addresses of all employees and other persons participating or assisting in the conduct of operations.
ATCP 54.05(1)(c) (c) A copy of the federal interim activity report filed for the month with the national oceanic and atmospheric administration under the federal weather modification reporting act. (15 USC 330)
ATCP 54.05(1)(d) (d) A narrative account of the manner in which operations during the month did not conform to the operational plan filed under s. ATCP 54.03.
ATCP 54.05(2) (2)Final report. Within 30 days after completion of any operation, the permittee shall file with the department a final report on the operation consisting of:
ATCP 54.05(2)(a) (a) Copies of logs prepared under s. ATCP 54.04 (1), weather records obtained under s. ATCP 54.04 (3), and totals for the entire operational period based on monthly summary records prepared under s. ATCP 54.04 (2).
ATCP 54.05(2)(b) (b) A copy of the federal final activity report filed with the national oceanic and atmospheric administration under the federal weather modification reporting act. (15 USC 330)
ATCP 54.05(2)(c) (c) A narrative account of the manner in which the operation did not conform to the operational plan filed under s. 93.35 (6) (b) 5., Stats., and s. ATCP 54.03 (2).
ATCP 54.05(3) (3)Evaluation report. Within 120 days after completion of the operation the permittee shall file with the department a narrative evaluation of the operation. The data for this report shall be assembled and evaluated on basis of the evaluation plan prepared under s. ATCP 54.03 (3) (d).
ATCP 54.05(4) (4)Sponsor's report. Permittees shall file with the department a copy of all reports made by the permittee to sponsors of the operation within 10 days after such report was submitted to the sponsor.
ATCP 54.05 History History: Cr. Register, September, 1979, No. 285, eff. 10-1-79.
ATCP 54.06 ATCP 54.06Statutory authority; exemptions.
ATCP 54.06(1)(1) These rules are adopted under authority of s. 93.35, Stats.
ATCP 54.06(2) (2) In addition to activities exempted under s. 93.35 (3), Stats., weather modification operations conducted by agencies of the state and federal governments are exempt from licensing and permit requirements.
ATCP 54.06(3) (3) Persons intending to conduct exempted operations shall file with the department a notice of intent to engage in such operations at least 25 days prior to the date weather modification activities are to begin. Notices shall include a statement indicating the name and address of the person intending to engage in an exempted operation, the nature and objective of the activity, and the area in which the operation is to be conducted.
ATCP 54.06 History History: Cr. Register, September, 1979, No. 285, eff. 10-1-79.