NR 151.12(5)(c)8.b.
b. Notwithstanding subd.
8. a., the discharge from BMPs shall remain below the enforcement standard at the point of standards application.
NR 151.12(5)(d)1.1. In this paragraph, “
protective area" means an area of land that commences at the top of the channel of lakes, streams and rivers, or at the delineated boundary of wetlands, and that is the greatest of the following widths, as measured horizontally from the top of the channel or delineated wetland boundary to the closest impervious surface. However, in this paragraph, “protective area" does not include any area of land adjacent to any stream enclosed within a pipe or culvert, such that runoff cannot enter the enclosure at this location.
NR 151.12(5)(d)1.a.
a. For outstanding resource waters and exceptional resource waters, and for wetlands in areas of special natural resource interest as specified in s.
NR 103.04, 75 feet.
NR 151.12(5)(d)1.b.
b. For perennial and intermittent streams identified on a United States geological survey 7.5-minute series topographic map, or a county soil survey map, whichever is more current, 50 feet.
NR 151.12(5)(d)1.d.
d. For highly susceptible wetlands, 50 feet. Highly susceptible wetlands include the following types: fens, sedge meadows, bogs, low prairies, conifer swamps, shrub swamps, other forested wetlands, fresh wet meadows, shallow marshes, deep marshes and seasonally flooded basins. Wetland boundary delineation shall be made in accordance with s.
NR 103.08 (1m). This paragraph does not apply to wetlands that have been completely filled in accordance with all applicable state and federal regulations. The protective area for wetlands that have been partially filled in accordance with all applicable state and federal regulations shall be measured from the wetland boundary delineation after fill has been placed.
NR 151.12(5)(d)1.e.
e. For less susceptible wetlands, 10% of the average wetland width, but no less than 10 feet nor more than 30 feet. Less susceptible wetlands include degraded wetlands dominated by invasive species such as reed canary grass.
NR 151.12(5)(d)1.f.
f. In subd.
1. a.,
d. and
e., determinations of the extent of the protective area adjacent to wetlands shall be made on the basis of the sensitivity and runoff susceptibility of the wetland in accordance with the standards and criteria in s.
NR 103.03.
NR 151.12(5)(d)1.g.
g. For concentrated flow channels with drainage areas greater than 130 acres, 10 feet.
NR 151.12(5)(d)2.
2. This paragraph applies to post-construction sites located within a protective area, except those areas exempted pursuant to subd.
4. NR 151.12(5)(d)3.a.
a. Impervious surfaces shall be kept out of the protective area to the maximum extent practicable. The storm water management plan shall contain a written site-specific explanation for any parts of the protective area that are disturbed during construction.
NR 151.12(5)(d)3.b.
b. Where land disturbing construction activity occurs within a protective area, and where no impervious surface is present, adequate sod or self-sustaining vegetative cover of 70% or greater shall be established and maintained. The adequate sod or self-sustaining vegetative cover shall be sufficient to provide for bank stability, maintenance of fish habitat and filtering of pollutants from upslope overland flow areas under sheet flow conditions. Non-vegetative materials, such as rock riprap, may be employed on the bank as necessary to prevent erosion such as on steep slopes or where high velocity flows occur.
NR 151.12 Note
Note: It is recommended that seeding of non-aggressive vegetative cover be used in the protective areas. Vegetation that is flood and drought tolerant and can provide long-term bank stability because of an extensive root system is preferable. Vegetative cover may be measured using the line transect method described in the university of Wisconsin extension publication number A3533, titled “Estimating Residue Using the Line Transect Method".
NR 151.12(5)(d)3.c.
c. Best management practices such as filter strips, swales or wet detention basins, that are designed to control pollutants from non-point sources may be located in the protective area.
NR 151.12 Note
Note: Other regulations, such as ch.
30, Stats., and chs.
NR 103,
115,
116 and
117 and their associated review and approval process may apply in the protective area.
NR 151.12(5)(d)4.c.
c. Structures that cross or access surface waters such as boat landings, bridges and culverts.
NR 151.12(5)(d)4.e.
e. Post-construction sites from which runoff does not enter the surface water, except to the extent that vegetative ground cover is necessary to maintain bank stability.
NR 151.12 Note
Note: A vegetated protective area to filter runoff pollutants from post-construction sites described in subd. 4. e. is not necessary since runoff is not entering the surface water at that location. Other practices necessary to meet the requirements of this section, such as a swale or basin, will need to be designed and implemented to reduce runoff pollutants prior to runoff entering a surface water of the state.
NR 151.12(5)(e)
(e)
Fueling and vehicle maintenance areas. Fueling and vehicle maintenance areas shall, to the maximum extent practicable, have BMPs designed, installed and maintained to reduce petroleum within runoff, such that the runoff that enters waters of the state contains no visible petroleum sheen.
NR 151.12 Note
Note: A combination of the following BMPs may be used: oil and grease separators, canopies, petroleum spill cleanup materials, or any other structural or non-structural method of preventing or treating petroleum in runoff.
NR 151.12(5)(f)
(f)
Location. To comply with the standards required under this subsection, BMPs may be located on-site or off-site as part of a regional storm water device, practice or system, but shall be installed in accordance with s.
NR 151.003.
NR 151.12(5)(g)
(g)
Timing. The BMPs that are required under this subsection shall be installed before the construction site has undergone final stabilization.
NR 151.121
NR 151.121 Post-construction performance standards. NR 151.121(1)(1)
General. In ss.
NR 151.121 to
151.128, “post-construction site" means a construction site subject to regulation under this subchapter, after construction is completed and final stabilization has occurred.
NR 151.121(2)
(2)
Applicability. Sections
NR 151.121 to
151.128 apply to a post-construction site that is or was subject to the construction performance standards of s.
NR 151.11, except any of the following:
NR 151.121(2)(a)
(a) A post-construction site with less than 10 percent connected imperviousness, based on the area of land disturbance, provided the cumulative area of all impervious surfaces is less than one acre. However, the exemption of this paragraph does not include exemption from the protective area standard of s.
NR 151.125.
NR 151.121 Note
Note: This exemption includes both point and nonpoint discharges from agricultural facilities and practices. Therefore, post-construction structures such as barns, manure storage facilities, sand settling lanes, and barnyard runoff control systems are subject to subch. II and are not subject, under s.
NR 216.47 (1), to the post-construction performance standards of this subchapter.
NR 151.121(2)(c)
(c) Underground utility construction, but not including the construction of any above ground structures associated with utility construction.
NR 151.121(3)
(3)
Responsible party. The landowner of the post-construction site or other person contracted or obligated by other agreement with the landowner to implement and maintain post-construction storm water BMPs is the responsible party and shall comply with ss.
NR 151.121 to
151.128.
NR 151.121(4)
(4)
Storm water management plan. A written storm water management plan shall be developed and implemented for each post-construction site and shall incorporate the requirements of ss.
NR 151.122 to
151.128.
NR 151.121 Note
Note: Examples of storm water management plans that may be used to comply with ss.
NR 151.122 to
151.128 may include those specified in s.
NR 216.47 or the municipal storm water management program specified in s.
NR 216.07 (5).
NR 151.121(5)
(5)
Maintenance of effort. For redevelopment sites where the redevelopment will be replacing older development that was subject to post-construction performance standards of this chapter in effect on or after October 1, 2004, the responsible party shall meet the total suspended solids reduction, peak flow control, infiltration, and protective areas standards applicable to the older development or meet the redevelopment standards of ss.
NR 151.122 to
151.125, whichever are more stringent.
NR 151.121 History
History: CR 09-112: cr.
Register December 2010 No. 660, eff. 1-1-11.
NR 151.122
NR 151.122 Total suspended solids performance standard. NR 151.122(1)(1)
Requirement. BMPs shall be designed, installed and maintained to control total suspended solids carried in runoff from the post-construction site. BMPs shall be designed in accordance with Table 1., or to the maximum extent practicable as provided in sub.
(3). The design shall be based on an average annual rainfall, as compared to no runoff management controls.
-
See PDF for table NR 151.122(2)
(2)
Redevelopment. Except as provided in s.
NR 151.121 (5), the redevelopment total suspended solids reduction standard of Table 1., applies to redevelopment.
NR 151.122(3)
(3)
Maximum extent practicable. If the design cannot meet a total suspended solids reduction performance standard of sub.
(1), Table 1., the storm water management plan shall include a written, site-specific explanation of why the total suspended solids reduction performance standard cannot be met and why the total suspended solids load will be reduced only to the maximum extent practicable. The department may not require any person to exceed the applicable total suspended solids reduction performance standard to meet the requirements of maximum extent practicable.
NR 151.122 Note
Note: Pollutant loading models such as DETPOND, SLAMM, P8, or equivalent methodology may be used to evaluate the efficiency of the design in reducing total suspended solids. Information on how to access these models is available from the department's storm water management program at dnr.wi.gov. Use the most recent version of the model and the rainfall files and other parameter files identified for Wisconsin users unless directed otherwise by the regulatory authority.
NR 151.122(4)
(4)
Off-site drainage. When designing BMPs, runoff draining to the BMP from off-site shall be taken into account in determining the treatment efficiency of the practice. Any impact on the efficiency shall be compensated for by increasing the size of the BMP accordingly.
NR 151.122 History
History: CR 09-112: cr.
Register December 2010 No. 660, eff. 1-1-11.
NR 151.123
NR 151.123 Peak discharge performance standard. NR 151.123(1)(1)
Requirement. By design, BMPs shall be employed to maintain or reduce the 1-year, 24-hour and the 2-year, 24-hour post-construction peak runoff discharge rates to the 1-year, 24-hour and the 2-year, 24-hour pre-development peak runoff discharge rates respectively, or to the maximum extent practicable. The runoff curve numbers in Table 2. shall be used to represent the actual pre-development condition.
-
See PDF for table NR 151.123 Note
Note: Where the pre-development condition is a combination of woodland, grassland, or cropland, the runoff curve number should be pro-rated by area.
NR 151.123(2)
(2)
Exemptions. This section does not apply to the following:
NR 151.123(2)(a)
(a) A post-construction site where the discharge is directly into a lake over 5,000
acres or a stream or river segment draining more than 500 square miles.
NR 151.123 Note
Note: The intent of s.
NR 151.123 is to minimize streambank and shoreline erosion under bank-full conditions.
NR 151.123 History
History: CR 09-112: cr.
Register December 2010 No. 660, eff. 1-1-11.
NR 151.124
NR 151.124 Infiltration performance standard. NR 151.124(1)(1)
Requirement. BMPs shall be designed, installed, and maintained to infiltrate runoff in accordance with the following or to the maximum extent practicable:
NR 151.124(1)(a)
(a) Low imperviousness. For development up to 40 percent connected imperviousness, such as parks, cemeteries, and low density residential development, infiltrate sufficient runoff volume so that the post-development infiltration volume shall be at least 90 percent of the pre-development infiltration volume, based on an average annual rainfall. However, when designing appropriate infiltration systems to meet this requirement, no more than one percent of the post-construction site is required as an effective infiltration area.
NR 151.124(1)(b)
(b) Moderate imperviousness. For development with more than 40 percent and up to 80 percent connected imperviousness, such as medium and high density residential, multi-family development, industrial and institutional development, and office parks, infiltrate sufficient runoff volume so that the post-development infiltration volume shall be at least 75 percent of the pre-development infiltration volume, based on an average annual rainfall. However, when designing appropriate infiltration systems to meet this requirement, no more than 2 percent of the post-construction site is required as an effective infiltration area.
NR 151.124(1)(c)
(c) High imperviousness. For development with more than 80 percent connected imperviousness, such as commercial strip malls, shopping centers, and commercial downtowns, infiltrate sufficient runoff volume so that the post-development infiltration volume shall be at least 60 percent of the pre-development infiltration volume, based on an average annual rainfall. However, when designing appropriate infiltration systems to meet this requirement, no more than 2 percent of the post-construction site is required as an effective infiltration area.
NR 151.124 Note
Note: A histogram showing the relationship between connected imperviousness and land use is available from the department at dnr.wi.gov.
NR 151.124 Note
Note: A model that calculates runoff volume, such as SLAMM, P8, or an equivalent methodology may be used. For performance standards based on an average annual rainfall, specific rainfall files for five geographic locations around the state may be used. Information on how to access SLAMM and P8 and the rainfall files is available from the department's storm water management program at dnr.wi.gov. Use the most recent version of the model and the parameter files for Wisconsin users unless directed otherwise by the regulatory authority.
NR 151.124(3)(a)(a)
Prohibitions. Runoff from the following areas may not be infiltrated and may not qualify as contributing to meeting the requirements of this section unless demonstrated to meet the conditions of sub.
(6):
NR 151.124(3)(a)1.
1. Areas associated with a tier 1 industrial facility identified in s.
NR 216.21 (2) (a), including storage, loading, and parking. Rooftops may be infiltrated with the concurrence of the regulatory authority.
NR 151.124 Note
Note: Runoff from the employee and guest parking and rooftop areas of a tier 2 facility may be infiltrated but runoff from the parking area may require pretreatment.
NR 151.124(3)(a)3.
3. Fueling and vehicle maintenance areas. Rooftops of fueling and vehicle maintenance areas may be infiltrated with the concurrence of the regulatory authority.
NR 151.124(3)(b)
(b) Exemptions. Runoff from the following areas may be credited toward meeting the requirement when infiltrated, but the decision to infiltrate runoff from these source areas is optional:
NR 151.124(3)(b)1.
1. Parking areas and access roads less than 5,000 square feet for commercial development.
NR 151.124(3)(b)2.
2. Parking areas and access roads less than 5,000 square feet for industrial development not subject to the prohibitions under par.
(a).
NR 151.124(3)(b)5.
5. Roads in commercial, industrial, and institutional land uses, and arterial residential roads.
NR 151.124(4)(a)(a)
Prohibitions. Infiltration practices may not be located in the following areas:
NR 151.124(4)(a)1.
1. Areas within 1,000 feet upgradient or within 100 feet downgradient of direct conduits to groundwater.
NR 151.124(4)(a)2.
2. Areas within 400 feet of a community water system well as specified in s.
NR 811.16 (4) or within the separation distances listed in s.
NR 812.08 for any private well or non-community well for runoff infiltrated from commercial, including multi-family residential, industrial, and institutional land uses or regional devices for one- and two-family residential development.
NR 151.124(4)(b)1.1. Infiltration practices shall be located so that the characteristics of the soil and the separation distance between the bottom of the infiltration system and the elevation of seasonal high groundwater or the top of bedrock are in accordance with Table 3:
-
See PDF for table NR 151.124(4)(b)2.
2. Notwithstanding par.
(b), applicable requirements for injection wells classified under ch.
NR 815 shall be followed.
NR 151.124(4)(c)
(c) Infiltration rate exemptions. Infiltration practices located in the following areas may be credited toward meeting the requirement under the following conditions, but the decision to infiltrate under these conditions is optional:
NR 151.124(4)(c)1.
1. Where the infiltration rate of the soil measured at the proposed bottom of the infiltration system is less than 0.6 inches per hour using a scientifically credible field test method.
NR 151.124(4)(c)2.
2. Where the least permeable soil horizon to 5 feet below the proposed bottom of the infiltration system using the U.S. department of agriculture method of soils analysis is one of the following: sandy clay loam, clay loam, silty clay loam, sandy clay, silty clay, or clay.
NR 151.124(5)
(5)
Alternate use. Where alternate uses of runoff are employed, such as for toilet flushing, laundry or irrigation or storage on green roofs where an equivalent portion of the runoff is captured permanently by rooftop vegetation, such alternate use shall be given equal credit toward the infiltration volume required by this section.