Chapter NR 425
COMPLIANCE SCHEDULES, DELAYS, EXCEPTIONS AND INTERNAL OFFSETS FOR ORGANIC COMPOUND EMISSION SOURCES IN CHS. NR 419 TO 424
NR 425.01   Applicability; purpose.
NR 425.02   Definitions.
NR 425.03   Compliance schedules.
NR 425.04   Exceptions and non-ozone season allowances.
NR 425.05   Internal offsets.
Ch. NR 425 NoteNote: Corrections made under s. 13.93 (2m) (b) 7., Stats., Register, December, 1996, No. 492.
NR 425.01NR 425.01Applicability; purpose.
NR 425.01(1)(1)Applicability. This chapter applies to all air contaminant sources governed by chs. NR 419 to 424 and to their owners and operators.
NR 425.01(2)(2)Purpose. This chapter is adopted under ss. 285.11, 285.13 and 285.17, Stats., to establish time schedules for air contaminant sources governed by chs. NR 419 to 424 to meet the emission limits set for each specific organic compound emission source, to specify exceptions to the requirements of chs. NR 419 to 424, to establish an internal offset system and to establish criteria for granting compliance schedule delays.
NR 425.01 HistoryHistory: Cr. Register, September, 1986, No. 369, eff. 10-1-86; am. (1) and (2), Register, February 1990, No. 410, eff. 3-1-90; am. (2), Register, February, 1995, No. 470, eff. 3-1-95.
NR 425.02NR 425.02Definitions. The definitions contained in chs. NR 400, 419, 420 and 421 apply to the terms used in this chapter. In addition, the following definitions apply to the terms used in this chapter:
NR 425.02(1)(1)“Energy intensive control device” means an air pollution control device or system which consumes energy at a rate in excess of what would be required to heat the exhaust gas stream from 70°F to 800°F, taking into account energy recovered in the form of heat or organic compounds.
NR 425.02(2)(2)“Hydrophobic substrate” means any substrate that is resistant to or avoids wetting. This may include but is not limited to polyethylene, polypropylene, cellophane, metalized polyester, nylon and polyester film.
NR 425.02 HistoryHistory: Renum. from NR 154.01, Register, September, 1986, No. 369, eff. 10-1-86; am. (intro.), Register, February, 1990, No. 410, eff. 3-1-90; am. (intro.) and (2), Register, October, 1999, No. 526, eff. 11-1-99.
NR 425.03NR 425.03Compliance schedules.
NR 425.03(1)(1)Effective dates. Subsections (2) to (8) do not apply to a source which is in compliance with the emission limitations of chs. NR 419 to 424, provided the source has determined and certified compliance to the satisfaction of the department within 90 days after the date specified in the effective date table, nor do subs. (2) to (7) apply to a source on which construction or modification commenced on or after the specified date. Sources on which construction or modification commenced on or after the date specified in the effective date table shall meet the emission requirements of chs. NR 419 to 424 in accordance with the provisions of sub. (8).
NR 425.03(2)(2)Process and emission control equipment installations. Except as provided under sub. (5) and s. NR 425.04, the owner or operator of a VOC emission source proposing to install and operate VOC emission control equipment or replacement process equipment to comply with the emission limiting requirements of chs. NR 419 to 424 shall achieve final compliance within 26 months of the date specified in the effective date table for that source.
Effective Date Table
The effective date listed under the Date column applies to the requirements outlined in all sections listed in the Section column to the right of the effective date in this table.
NR 425.03(3)(3)Low solvent content coating or ink.
NR 425.03(3)(a)(a) Except as provided under pars. (b) to (e) and subs. (5) and (7m), the owner or operator of a VOC source proposing to employ low solvent content coating or ink application technology to comply with the requirements of chs. NR 419 to 424 shall achieve final compliance within 28 months of the date specified in the effective date table for that source.
NR 425.03(3)(b)(b) The owner or operator of a can coating or flexible packaging facility proposing to employ low solvent content coating technology to comply with the requirements of s. NR 422.05 (2) (d) or 422.07 (2) may exceed the deadline in par. (a) by 12 months in developing acceptable can end sealing compounds or coatings for hydrophobic flexible packaging substrates.
NR 425.03(3)(c)(c) The owner or operator of a graphic arts facility proposing to employ low solvent content ink application technology to comply with the requirements of s. NR 422.14 may, for hydrophobic substrates, extend the date for achieving final compliance to December 31, 1985, provided:
NR 425.03(3)(c)1.1. Final plans for achieving compliance are submitted by September 1, 1981.
NR 425.03(3)(c)3.3. Sufficient documentation is submitted to justify the extension.
NR 425.03(3)(c)4.4. The plans provide for final compliance by December 31, 1985 through the use of an emission reduction system described in s. NR 422.14 (2) (c) and (3) in case the product quality and commercial acceptability evaluation shows low solvent content ink application technology to be unsatisfactory.
NR 425.03(3)(d)(d) The owner or operator of a miscellaneous metal parts and products coating facility proposing to employ low solvent content coating technology to comply with the requirements of s. NR 422.15 may, for extreme performance coatings requiring prolonged product quality evaluation periods, extend final compliance to accommodate the prolonged evaluation period but in no case beyond December 31, 1985.
NR 425.03(3)(e)(e) Where the department determines that the low solvent content coating or ink application technology has been sufficiently researched and developed for a particular application, the owner or operator of a VOC source proposing to comply with the requirements of chs. NR 419 to 424 through application of low solvent content coatings or inks shall achieve final compliance within 21 months of the date specified in the effective date table for that source.
NR 425.03(4)(4)Equipment modification. Except as provided under subs. (5) and (7m), the owner or operator of a VOC source proposing to comply with the requirements of chs. NR 419 to 424 by modification of existing processing or emission control equipment shall achieve final compliance within 20 months of the date specified in the effective date table for that source.
NR 425.03(5)(5)Alternate compliance schedules. Notwithstanding the deadlines specified in subs. (2) to (4), for any particular source the department may issue or approve a separate compliance schedule with later deadlines if it finds that those specified in subs. (2) to (4) would not be feasible. All alternate compliance schedules proposed or promulgated under this subsection shall provide for compliance of the source with the requirements of chs. NR 419 to 424 not later than December 31, 1982 or, where the owner or operator proposes to comply through development of a new surface coating which is subject to approval by a federal agency, not later than December 31, 1985.
NR 425.03(6)(6)Phased emission reduction schedules.
NR 425.03(6)(a)(a) This subsection applies only to sources covered under ss. NR 422.09 and 422.15 (3).
NR 425.03(6)(b)(b) Except as provided under sub. (7m), the owner or operator of a source required to undertake a phased compliance program shall achieve final compliance on or before the date specified in the applicable rule or approved compliance plan, but not later than December 31, 1987.
NR 425.03(7)(7)Final compliance plans.
NR 425.03(7)(a)(a) If the department finds any compliance plan submitted under this chapter to be unsatisfactory, it may require that the plan be resubmitted with appropriate revisions.
NR 425.03(7)(b)(b) Process lines subject to requirements of this chapter on which construction or modification commenced on or before August 1, 1979 shall continue to comply with the requirements of s. NR 424.03 (2) (a) during any interim period prior to the final compliance date in the applicable compliance schedule.
NR 425.03(7)(c)(c) Process lines covered under ss. NR 420.03 (6), 420.04 (1) (d), (e) and (g), (2) (c) 3., (f) and (g), (3) (b) 3., (d) and (g) 3., 420.05 (4), 421.03 (1) to (3), 421.04, 422.13 to 422.15, and 423.05, on which construction or modification commenced on or after August 1, 1979, but before April 1, 1981, shall continue to comply with the requirements of s. NR 424.03 (2) (b) during any interim period prior to the final compliance date in the applicable compliance schedule.
NR 425.03 NoteNote: The reference to s. NR 424.03 (2) (b) refers to that section as it existed prior to its repeal on May 1, 1989.
NR 425.03(7)(d)(d) Process lines covered under s. NR 421.04 on which construction or modification commenced on or after April 1, 1981 but before August 31, 1981, and process lines covered under s. NR 423.05 (1) on which construction or modification commenced on or after April 1, 1981 but before December 1, 1983, shall continue to comply with the requirements of s. NR 424.03 (2) (c) during any interim period prior to the final compliance date in the applicable compliance schedule.
NR 425.03 NoteNote: The reference to s. NR 424.03 (2) (c) refers to that section as it existed prior to May 1, 1989. As of May 1, 1989, s. NR 424.03 (2) (c) was renumbered to be s. NR 424.03 (2) (b) and amended.
NR 425.03(7)(e)(e) Where a source is not otherwise subject to requirements of this chapter and was previously unregulated under chs. NR 419 to 424, the final compliance plan shall specify reasonable measures to minimize emissions of VOCs during the interim period prior to the final compliance date.
NR 425.03(7m)(7m)Compliance schedule delays. Notwithstanding any compliance schedule approved or issued under this section, the department may approve a new compliance schedule which provides additional time for achieving compliance, provided that all of the following conditions are met:
NR 425.03(7m)(a)(a) The owner or operator of the source is able to document to the department’s satisfaction that the source is unable to meet the applicable deadline under this section due to circumstances beyond the owner or operator’s control which could not reasonably have been avoided by using all prudent planning.
NR 425.03(7m)(b)(b) The final compliance for sources covered under ss. NR 420.03 (5), 420.04 (1) (b), (c) and (f), (2) (b), (c) 1., (d), (e) and (h), (3) (b) 1. and 2., (c), (e), (f), (g) 1. and 2., (h) and (i), 420.05 (1) to (3), 422.05 to 422.08, 422.10 to 422.12 and 423.03 (3) to (5) is not later than December 31, 1982.
NR 425.03(7m)(c)(c) The final compliance for sources covered under ss. NR 420.03 (6), 420.04 (1) (d), (e) and (g), (2) (c) 3., (f) and (g), (3) (b) 3., (d) and (g) 3., 420.05 (4), 421.03 (1) to (3), 421.04, and 422.13 to 422.15 is not later than that required in this section.
NR 425.03(8)(8)New and modified sources. Any source on which construction or modification commenced on or after the date specified for the source category in the effective date table shall meet the emission limitations of chs. NR 419 to 425 upon startup unless the owner or operator of the source demonstrates, to the satisfaction of the department, that compliance upon startup would be technologically infeasible. Such sources shall instead meet a department-specified compliance schedule which provides for interim emission limitations and for ultimate compliance with the emission limitations of chs. NR 419 to 425. Ultimate compliance shall be as soon as practicable but in no event later than the final compliance date applicable to the source under this chapter or chs. NR 419 to 424.
NR 425.03(9)(9)Leather coating.
NR 425.03(9)(a)(a) This subsection applies only to a leather coating facility in existence on January 1, 1994 and which is one of the following:
NR 425.03(9)(a)1.1. Located in the county of Door, Kewaunee, Manitowoc, Sheboygan or Walworth.
NR 425.03(9)(a)2.2. Located in the county of Kenosha, Milwaukee, Ozaukee, Racine, Washington or Waukesha and which was not subject to this section prior to January 1, 1994.
NR 425.03(9)(b)(b) The owner or operator of any source identified under par. (a) shall:
NR 425.03(9)(b)1.1. Notify the department’s bureau of air management in writing by April 1, 1994. This notification shall provide the name and location of the affected facility and include VOC emission data from coating applications if necessary to support eligibility under this subsection.
NR 425.03(9)(b)2.2. Achieve final compliance with the requirements of s. NR 422.085 no later than May 31, 1995.
NR 425.03(10)(10)Sources of VOCs with vapor pressures less than or equal to 0.1 millimeters of mercury (0.0019 psia) at standard conditions.