21. 60.84 (1) of the statutes is renumbered 60.84 (1r) and amended to read:
60.84 (1r) Survey, contract for. The town board may contract with the county surveyor or any registered professional land surveyor to survey all or some of the sections in the town and to erect monuments under this section as directed by the board.
358,22
Section
22. 60.84 (1g) of the statutes is created to read:
60.84 (1g) Definition. In this section, "professional land surveyor" means a professional land surveyor licensed under ch. 443.
358,23
Section
23. 60.84 (2) of the statutes is amended to read:
60.84 (2) Bond. Before the town board executes a contract under sub. (1) (1r), the
county surveyor or professional land surveyor shall execute and file with the town board a surety bond or other financial security approved by the town board.
358,24
Section
24. 60.84 (3) (a) of the statutes is amended to read:
60.84 (3) (a) Monuments shall be set on section and quarter-section corners established by the United States survey. If there is a clerical error or omission in the government field notes or if the bearing trees, mounds, or other location identifier specified in the notes is destroyed or lost, and if there is no other reliable evidence by which a section or quarter-section corner can be identified, the county surveyor or professional land surveyor shall reestablish the corner under the rules adopted by the federal government in the survey of public lands. The county surveyor or professional land surveyor shall set forth his or her actions under this paragraph in the certificate U.S. public land survey monument record under sub. (4).
358,25
Section
25. 60.84 (3) (c) (intro.) and 1. of the statutes are amended to read:
60.84 (3) (c) (intro.) To establish, relocate, or perpetuate a corner, the county surveyor or professional land surveyor shall set in the proper place a monument, as determined by the town board, consisting of any of the following:
1. A stone or other equally durable material, not less than 3 feet long and 6 inches square, with perpendicular, dressed sides and a square, flat top. As prescribed by the town board, the top shall be engraved with either of the following:
a. A cross formed by lines connecting the corners of the top; or.
b. If the monument is set at a section corner, the number of the section or, if set at a quarter-section corner, "1/4S"; or.
358,26
Section
26. 60.84 (3) (c) 3. of the statutes is created to read:
60.84 (3) (c) 3. An equivalent monument agreed upon by all parties of the contract.
358,27
Section
27. 60.84 (4) of the statutes is amended to read:
60.84 (4) Certificate
U.S. public land survey monument record. The county surveyor or professional land surveyor shall prepare a certificate U.S. public land survey monument record setting forth a complete and accurate record of any survey monument erected on section and quarter section corners under this section, including the exact bearings and distances of each monument from each other monument nearest it on any line in the town. The certificate U.S. public land survey monument record and a map of any additional monuments set shall be recorded in the office of the register of deeds or filed in the office of the county surveyor of the county in which the surveyed land is located and of the adjoining county if a monument is located on the county line.
358,28
Section
28. 66.0309 (11) of the statutes is amended to read:
66.0309 (11) Matters referred to regional planning commission. The officer or public body of a local governmental unit within the region having final authority may refer to the regional planning commission, for its consideration and report, the location or acquisition of land for any of the items or facilities which that are included in the adopted regional master plan. Within 20 days after the matter is referred to the regional planning commission or a longer period as may be stipulated by the referring officer or public body, the commission shall report its recommendations to the referring officer or public body. The report and recommendations of the commission shall be advisory only. A state agency may authorize the regional planning commission with the consent of the commission to act for the agency in approving, examining, or reviewing plats, under s. 236.12 (2) (a) (ap). A regional planning commission authorized by a local unit on November 1, 1980, to act for the local unit in approving plats may continue to so act until the commission withdraws its consent or the local unit its approval. A local unit may authorize a regional planning commission, with the consent of the commission, to conduct an advisory review of plats.
358,29
Section
29. 70.27 (2) of the statutes is amended to read:
70.27 (2) Certification, approval, recording. Such plat, when completed and certified as provided by this section, and when approved by the governing body, shall be acknowledged by the clerk thereof and recorded in the office of the register of deeds. No plat may be recorded in the office of the register of deeds unless it is produced on media that is acceptable to the register of deeds.
358,30
Section
30. 70.27 (5) of the statutes is amended to read:
70.27 (5) Surveys, reconciliations. The surveyor making the plat shall be a professional land surveyor licensed under ch. 443 and shall survey and lay out the boundaries of each parcel, street, alley, lane, roadway, or dedication to public or private use, according to the records of the register of deeds, and whatever evidence that may be available to show the intent of the buyer and seller, in the chronological order of their conveyance or dedication, and set temporary monuments to show the results of such survey which shall be made permanent upon recording of the plat as provided for in this section. The map shall be at a scale of not more than 100 feet per inch, unless waived in writing by the department of administration under s. 236.20 (2) (L). The owners of record of lands in the plat shall be notified by certified letter mailed to their last-known address, in order that they shall have opportunity to examine the map, view the temporary monuments, and make known any disagreement with the boundaries as shown by the temporary monuments. It is the duty of the professional land surveyor making the plat to reconcile any discrepancies that may be revealed, so that the plat as certified to the governing body is in conformity with the records of the register of deeds as nearly as is practicable. When boundary lines between adjacent parcels, as evidenced on the ground, are mutually agreed to in writing by the owners of record, such lines shall be the true boundaries for all purposes thereafter, even though they may vary from the metes and bounds descriptions previously of record. Such written agreements shall be recorded in the office of the register of deeds. On every assessor's plat, as certified to the governing body, shall appear the volume, page, and document number of the metes and bounds description of each parcel, as recorded in the office of the register of deeds, which shall be identified with the number by which such parcel is designated on the plat, except that lots which have been conveyed or otherwise acquired but upon which no deed is recorded in the office of register of deeds may be shown on an assessor's plat and when so shown shall contain a full metes and bounds description.
358,31
Section
31. 70.27 (6) of the statutes is amended to read:
70.27 (6) Monuments, plat requirements. The provisions of s. 236.15 as to monuments, and the provisions of s. 236.20 as to form and procedure, insofar as they are applicable to the purposes of assessors' plats, shall apply. Any stake or monument found and accepted as correct by a professional land surveyor laying out an assessor's plat shall be indicated as "stake found" or "monument found" when mapping the plat and such stake or monument shall not be removed or replaced even though it is inconsistent with the standards of s. 236.15.
358,32
Section
32. 70.27 (7) (intro.) of the statutes is amended to read:
70.27 (7) Certificate. (intro.) When completed, the assessor's plat shall be filed with the clerk of the governing body that ordered the plat. On its title page shall appear the sworn certificate of the professional land surveyor who made the plat, which shall state and contain:
358,33
Section
33. 70.27 (7) (d) of the statutes is amended to read:
70.27 (7) (d) A statement that the professional land surveyor has fully complied with the provisions of this section in filing the same.
358,34
Section
34. 84.095 (5) of the statutes is amended to read:
84.095 (5) Surveyor's
Professional land surveyor's certificate. A plat prepared for filing or recording under this section shall include a certificate of a professional land surveyor registered licensed under s. 443.06 that the plat is a correct representation of the project described and that the identification and location of each parcel can be determined from the plat. This subsection does not apply to plats prepared by the department.
358,35
Section
35. 157.061 (13m) of the statutes is created to read:
157.061 (13m) "Professional land surveyor" means a professional land surveyor licensed under ch. 443.
358,36
Section
36. 157.07 (1) of the statutes is amended to read:
157.07 (1) A cemetery authority shall cause to be surveyed and platted by a professional land surveyor
registered in this state those portions of the lands that are from time to time required for burial, into cemetery lots, drives, and walks, and record a plat or map of the land in the office of the register of deeds. The plat or map may not be recorded unless laid out and platted to the satisfaction of the county board of the county, and the town board of the town in which the land is situated, or, if the land is situated within a 1st class city, then only by the common council of that city.
358,37
Section
37. 157.07 (2) of the statutes is amended to read:
157.07 (2) The plat or map location of the lands shall show the exact location of the tract being subdivided with reference to a corner or corners established in the United States public land survey by bearings and distances be indicated on the plat or map by bearing and distance from a boundary line of a government lot, quarter section, recorded private claim, or federal reservation in which the subdivision is located. The monumentation at the ends of the boundary line shall be described and the bearing and distance between them shown, and the plat or map shall show a small scale drawing of the section or government subdivision of the section in which the cemetery plat is situated, with the cemetery plat indicated. The plat or map shall include the certificate of the professional land surveyor containing the name of the cemetery authority, the date of the survey, the professional land surveyor's stamp or seal and signature, and the professional land surveyor's statement that the survey is true and correct to the professional land surveyor's best knowledge and belief.
358,38
Section
38. 157.07 (3) of the statutes is amended to read:
157.07 (3) The plat or map shall be made on a durable white media that is 22 inches wide by 30 inches long, or on any other media that is acceptable to the register of deeds, with a permanent nonfading black image. Seals or signatures that are reproduced on images that comply with this subsection have the force and effect of original seals and signatures. When more than one sheet is used for any one plat or map, they shall be numbered consecutively and each sheet shall contain a notation showing the whole number of sheets in the plat, and its relation to the other sheets. The sheets may be provided by the county through the register of deeds on terms determined by the county board. The professional land surveyor shall leave a binding margin of 1.5 inches on the left side of the 30-inch length and a one-inch margin one inch on all other sides.
358,39
Section
39. 236.02 (2m) of the statutes is amended to read:
236.02 (2m) "Correction instrument" means an instrument drafted by a licensed professional land surveyor that complies with the requirements of s. 236.295 and that, upon recording, corrects a subdivision plat or a certified survey map.
358,40
Section
40. 236.02 (9b) of the statutes is created to read:
236.02 (9b) "Professional land surveyor" means a professional land surveyor licensed under ch. 443.
358,41
Section
41. 236.025 of the statutes is created to read:
236.025 Ordinary high water marks. (1) For purposes of ss. 236.15 (1) (ag) and (d) and 236.20 (2) (g), a professional land surveyor may do any of the following:
(a) Incorporate into a map, plat, or survey an ordinary high water mark that has been determined by the department of natural resources or otherwise determined pursuant to law.
(b) Approximate the ordinary high water mark and incorporate that mark into a map, plat, or survey.
(2) For purposes of sub. (1) (b), the location of the approximate ordinary high water mark shall be the point on the bank of a navigable stream or on the shore of a lake up to which the presence and action of surface water is so continuous as to leave a distinctive mark by erosion, destruction of terrestrial vegetation, or other easily recognized characteristics. If the approximate location of the ordinary high water mark is difficult to determine, a professional land surveyor may consider other points on the bank or shore for purposes of approximating the location of the ordinary high water mark.
(3) For purposes of this section, a map, plat, or survey that shows an approximate ordinary high water mark shall state on its face that the mark is shown for reference only.
358,42
Section
42. 236.03 (2) of the statutes is amended to read:
236.03 (2) This chapter does not apply to cemetery plats made under s. 157.07 and assessors' plats made under s. 70.27, but such assessors' plats shall, except in counties having a population of 500,000 or more, comply with ss. 236.15 (1) (a) (ac) to (g) and 236.20 (1) and (2) (a) to (e), unless waived under s. 236.20 (2) (L).
358,43
Section
43. 236.11 (2) of the statutes is renumbered 236.11 (2) (a) and amended to read:
236.11 (2) (a) The subdivider or subdivider's agent shall submit to the body or bodies having authority to approve plats an electronic copy of the final plat or a copy of the final plat that is capable of legible reproduction. The approving authority or authorities shall approve or reject the final plat within 60 days of its submission, unless the time is extended by agreement with the subdivider or subdivider's agent. When the approving authority is a municipality and determines to approve the plat, it shall give at least 10 days' prior written notice of its intention to the clerk of any municipality whose boundaries are within 1,000 feet of any portion of such proposed plat but failure to give such notice shall not invalidate any such plat. If a plat is rejected, the reasons therefor shall be stated in the minutes of the meeting and a copy thereof or a written statement of the reasons shall be supplied to the subdivider or subdivider's agent. If the approving authority fails to act within 60 days and the time has not been extended by agreement and if no unsatisfied objections have been filed within that period, the plat shall be deemed approved, and, upon demand, a certificate to that effect shall be made on the face of the plat by the clerk of the authority which that has failed to act.
358,44
Section
44. 236.11 (2) (b) of the statutes is created to read:
236.11 (2) (b) The approval of the approving authority or authorities may be based on the copy submitted under par. (a) but the approval must be inscribed on the recordable plat document. Before inscribing its approval, the approving authority shall require the subdivider or subdivider's agent to certify the respects in which the recordable plat document differs from the copy, if any. An approving authority must approve all modifications in the final plat before it gives final approval to the plat. No approving authority may inscribe its final approval on a plat before the affixing of the certificate by the department under s. 236.12 (3).
358,45
Section
45. 236.12 (2) (intro.) and (a) of the statutes are consolidated, renumbered 236.12 (2) (ap) and amended to read:
236.12 (2) (ap) Within 2 days after a preliminary or final plat is submitted for approval, legible copies, together with a list of the authorities to which the plat must be submitted for approval under s. 236.10 or objection under this subsection, furnished by the subdivider at the subdivider's expense, shall be sent, by the clerk or secretary of the approving authority to which the plat is submitted, to the following agencies which have authority under par. (ac), the department shall transmit an electronic copy of the plat, or, if the department prefers, 2 legible hard copies of the plat, to each state agency authorized to object to the plat: (a) Two copies for each of the state agencies required to review the plat to the department which shall examine the plat for compliance with ss. 236.15, 236.16, 236.20 and 236.21 (1) and (2) under this paragraph. If the subdivision abuts or adjoins a state trunk highway or connecting highway, the department shall transmit 2 a copy or copies of the plat to the department of transportation so that the agency may determine whether it has any objection to the plat on the basis of its rules as provided in s. 236.13. If the subdivision is not served by a public sewer and provision for that service has not been made, the department shall transmit 2 a copy or copies of the plat to the department of safety and professional services so that that the agency may determine whether it has any objection to the plat on the basis of its rules as provided in s. 236.13. In lieu of this procedure the agencies may designate local officials to act as their agents in examining the plats for compliance with the statutes or their rules by filing a written delegation of authority with the approving body.
358,46
Section
46. 236.12 (2) (ac) of the statutes is created to read:
236.12 (2) (ac) The subdivider or subdivider's agent shall submit an electronic copy of the preliminary or final plat, or a copy of the preliminary or final plat that is capable of clearly legible reproduction, to the department, which shall examine the plat for compliance with ss. 236.15, 236.16, 236.20, and 236.21 (1) and (2).
358,47
Section
47. 236.12 (2) (b) of the statutes is amended to read:
236.12 (2) (b) Four copies Within 2 days after a preliminary or final plat is submitted under par. (ac), the department shall transmit an electronic copy of the plat, or, if the department prefers, 4 legible hard copies of the plat, to the county planning agency, if the agency employs on a full-time basis a professional engineer, a planner, or other person charged with the duty of administering planning legislation and adopts a policy requiring submission so that the body may determine if it has any objection to the plat on the basis of a conflict with park, parkway, expressway, major highways, airports, drainage channels, schools, or other planned public developments. If no county planning agency exists, then 2 copies to the county park commission except that in a county with a county executive or county administrator, 2 copies to the county park manager, if the subdivision abuts a county park or parkway so that the body may determine if it has any objection to the plat on the basis of a conflict with the park or parkway development.
358,48
Section
48. 236.12 (3) and (6) of the statutes are consolidated, renumbered 236.12 (3) and amended to read:
236.12 (3) Within 20 days of after the date of receiving the copies of the plat any agency having authority to object under sub. (2) shall notify the subdivider or subdivider's agent and all approving or objecting authorities other agencies having the authority to object of any objection based upon failure of the plat to comply with the statutes or rules which that its examination under sub. (2) is authorized to cover, or, if there is no objection, it shall so certify on the face of a copy of the plat and return that copy to the approving authority from which it was received. The plat shall not be approved or deemed approved until any objections have been satisfied. If the objecting agency fails to act within the 20-day limit it shall be deemed to have no objection to the plat. No approving authority may inscribe its approval on a plat prior to the affixing of the certificates under either sub. (4) or (6). (6) In lieu of the procedure under subs. (2) to (5), the subdivider or the subdivider's agent may submit the original plat to the department which shall forward 2 copies to each of the agencies authorized by sub. (2) to 9 department shall have the required number of copies made at the subdivider's expense. Within 20 days of the date of receiving the copies of the plat any agency having authority to object under sub. (2) shall notify the subdivider, and all agencies having the authority to object, of any objection based upon failure of the plat to comply with the statutes or rules which its examination under sub. (2) is authorized to cover, or, if there is no objection, it shall so certify on the face of a copy of the plat and return that copy to the department. After each agency and the department have certified that they have no objection or that their objections have been satisfied, the department shall so certify on the face of the plat. If an agency fails to act within 20 days from the date of the receipt of on which it received the copy or copies of the plat, and the department fails to act within 30 days of receipt of the original from the date on which it received the copy of the plat, it shall be deemed that there are no objections to the plat and, upon demand, it the department shall be so certified certify on the face of the plat by the department.
358,49
Section
49. 236.12 (4) of the statutes is repealed.
358,50
Section
50. 236.12 (5) of the statutes is repealed.
358,51
Section
51. 236.12 (8) of the statutes is renumbered 236.12 (4m) and amended to read:
236.12 (4m) In order to facilitate approval of the final plat where whenever more than one approval is required, the subdivider may or subdivider's agent shall file a true copy of the plat with the each approving authority or authorities with which the original of the final plat has not been filed. The approval of such authorities may be based on such copy but shall be inscribed on the original of the final plat. Before inscribing its approval, the approving authority shall require the surveyor or the owner to certify the respects in which the original of the final plat differs from the copy. All modifications in the final plat shall be approved before final approval is given a true copy of the plat that the subdivider or subdivider's agent submitted to the department.
358,52
Section
52. 236.13 (2) (a) of the statutes is amended to read:
236.13 (2) (a) As a further condition of approval, the governing body of the town or municipality within which the subdivision lies may require that the subdivider make and install any public improvements reasonably necessary or that the subdivider execute a surety bond or provide other security to ensure that he or she will make those improvements within a reasonable time. The subdivider may construct the project in such phases as the governing body approves, which approval may not be unreasonably withheld. If the subdivider's project will be constructed in phases, the amount of any surety bond or other security required by the governing body shall be limited to the phase of the project that is currently being constructed. The governing body may not require that the subdivider provide any security for improvements sooner than is reasonably necessary before the commencement of the installation of the improvements. This paragraph applies to all preliminary and final plats, regardless of whether submitted for approval before, on, or after the effective date of this paragraph .... [LRB inserts date].
358,53
Section
53. 236.13 (2m) of the statutes is amended to read:
236.13 (2m) As a further condition of approval when lands included in the plat lie within 500 feet of the ordinary high-water mark of any lake, any navigable stream, lake or any other body of navigable water or if land in the proposed plat involves lake or navigable stream shorelands referred to in s. 236.16, the department of natural resources, to prevent pollution of navigable waters, or the department of safety and professional services, to protect the public health and safety, may require assurance of adequate drainage areas for private on-site wastewater treatment systems and building setback restrictions, or provisions by the owner for public sewage disposal facilities for waters of the state, as defined in s. 281.01 (18), industrial wastes, as defined in s. 281.01 (5), and other wastes, as defined in s. 281.01 (7). The public sewage disposal facilities may consist of one or more systems as the department of natural resources or the department of safety and professional services determines on the basis of need for prevention of pollution of the waters of the state or protection of public health and safety.
358,54
Section
54. 236.15 (1) (intro.) of the statutes is renumbered 236.15 (1) (ac) and amended to read:
236.15 (1) (ac) All of the monuments required in pars. (a) (ag) to (h) shall be placed flush with the ground where if practicable. Whenever placement of a monument under this subsection is required at a corner or point that falls within a street or proposed future street, the monument shall be placed in the side line of the street if practicable.
358,55
Section
55. 236.15 (1) (a) of the statutes is renumbered 236.15 (1) (ag) and amended to read:
236.15 (1) (ag) The external boundaries of a subdivision shall be monumented in the field by monuments of concrete containing a ferrous rod one-fourth inch in diameter or greater imbedded its full length, not less than 18 inches in length, not less than 4 inches square or 5 inches in diameter, and marked on the top with a cross, brass plug, iron rod, or other durable material securely embedded; or by iron rods or pipes at least 18 inches long and 2 inches in diameter weighing not less than 3.65 pounds per lineal foot. Solid round or square iron bars of equal or greater length or weight per foot may be used in lieu of pipes wherever pipes are specified in this section. These monuments shall be placed at all corners, at each end of all curves, at the point where a curve changes its radius, at all angle points in any line and at all angle points along the meander line, said points to be not less than 20 feet back from the determined or approximated ordinary high water mark of the lake or from the bank of the stream, except that when such corners or points fall within a street, or proposed future street, the monuments shall be placed in the side line of the street.
358,56
Section
56. 236.15 (1) (b) of the statutes is amended to read:
236.15 (1) (b) All internal boundaries and those corners and points not required to be marked by par. (a)
(ag) shall be monumented in the field by like monuments as defined in par. (a) (ag). These monuments shall be placed at all block corners, at each end of all curves, at the point where a curve changes its radius, and at all angle points in any line.
358,57
Section
57. 236.15 (1) (d) of the statutes is amended to read:
236.15 (1) (d) The lines of lots, outlots, parks and public access and land dedicated to the public that extend to lakes or to navigable streams shall be monumented in the field by iron pipes at least 18 inches long and one inch in diameter weighing not less than 1.13 pounds per lineal foot, or by round or square iron bars at least 18 inches long and weighing not less than 1.13 pounds per lineal foot. These monuments shall be placed at the point of intersection of the lake or navigable stream lot line with a meander line established not less than 20 feet back from the determined or approximated ordinary high water mark of the lake or from the bank of the stream.
358,58
Section
58. 236.15 (2) of the statutes is amended to read:
236.15 (2) Accuracy of survey. The survey shall be performed by a professional land surveyor registered in this state and if the error in the latitude and departure closure of the survey or any part thereof is greater than the ratio of one in 3,000, the plat may be rejected.
358,59
Section
59. 236.16 (3) (title) of the statutes is amended to read:
236.16 (3) (title) Lake and navigable stream shore plats; public access.
358,60
Section
60. 236.16 (3) (a) of the statutes is amended to read:
236.16 (3) (a) All subdivisions abutting on a navigable lake or a navigable stream shall provide public access at least 60 feet wide providing access to the low watermark water's edge so that there will be public access, which is connected to existing public roads, at not more than one-half mile intervals as measured along the lake or the navigable stream shore except where greater intervals and wider access is agreed upon by the department of natural resources and the department, and excluding shore areas where public parks or open-space streets or roads on either side of a the navigable stream are provided.
358,61
Section
61. 236.16 (3) (b) of the statutes is amended to read:
236.16 (3) (b) No public access established under this chapter may be vacated except by circuit court action as provided in s. 236.43, except that such public access may be discontinued under s. 66.1003, subject to s. 66.1006.
358,62
Section
62. 236.16 (4) of the statutes is amended to read:
236.16 (4) Lake and navigable stream shore plats; land between meander line and water's edge. The lands lying between the meander line, established in accordance with s. 236.20 (2) (g), and the water's edge, and any otherwise unplattable lands which lie between a proposed subdivision and the water's edge shall be included as part of lots, outlots or public dedications in any plat abutting a lake or a navigable stream. This subsection applies not only to lands proposed to be subdivided but also to all lands under option to the subdivider or in which the subdivider holds any interest and which are contiguous to the lands proposed to be subdivided and which abut a lake or a navigable stream.