ATCP 93.230(11)(a)(a) When damage has occurred to underground pressurized tank system components or to underground vent and remote fill lines, the affected portion of the tank system shall be removed from service, and the following actions shall be taken before that portion of the system is put back into service, except as provided in par. (b): ATCP 93.230(11)(a)4.4. Perform any additional monitoring, processes, or procedures needed to verify system integrity. ATCP 93.230(11)(a)6.6. Notify the authorized agent or the department if the damage resulted in a release. ATCP 93.230 NoteNote: This notification can be part of the notice that is submitted under s. ATCP 93.400 (8) (c) or 93.500 (7) (d) when repairs are made because of a release from an AST or UST system. ATCP 93.230(11)(b)(b) The actions in par. (a) 1. to 4. are not required where the damage is limited to dispenser system components that are isolated from the rest of the dispenser or tank system through the use of pressure-retaining components. ATCP 93.230 NoteNote: In addition to these requirements, other additional safety or environmental protection actions or repairs may be necessary.
ATCP 93.230(12)(12) Product color coding for fill pipe caps and manhole covers. ATCP 93.230(12)(a)1.1. All fill pipe caps and manhole covers for underground fuel tanks at distribution terminals, bulk plants and motor fuel dispensing facilities shall be identified by the standard color and symbol coding in API 1637. ATCP 93.230(12)(a)2.2. Products containing extenders such as ethanol shall be designated by the addition of a black border around white symbols and a white border around other colored symbols. ATCP 93.230 NoteNote: Extenders or oxygenates are added to gasoline and typically comprise a maximum of 15 percent of the fuel by volume.
ATCP 93.230(12)(a)4.a.a. Observation and monitoring wells shall be marked with a black triangle on a white background. ATCP 93.230(12)(a)4.b.b. The well shall be provided with a durable label warning against the introduction of petroleum products into the well. ATCP 93.230(12)(b)1.1. The color coding required in par. (a) shall be applied to the fill pipe cap and manhole cover or within the spill containment. ATCP 93.230(12)(b)2.2. At all facilities with more than one tank, the color coding applied to the fill cap or manhole cover shall extend at least 12 inches beyond the edge of the cap or cover onto adjacent concrete or pavement. ATCP 93.230 NoteNote: See s. ATCP 93.340 for additional information on product identification at bulk plants and terminals. ATCP 93.230(13)(13) Disconnecting and discontinuing vapor recovery. Disconnecting or discontinuing use of a stage II vapor-recovery system or a portion thereof shall comply with PEI RP300 chapter 14, be completed within five days after it begins, and be reported to the department on form TR-WM-122 within 15 business days after the completion. ATCP 93.230 NoteNote: Each connection of a tank to deactivated, unremoved vapor-recovery pipe should be capped or plugged at the tank, if readily accessible, to minimize the potential for water intrusion from the pipe.
ATCP 93.230(14)(14) Removing water and other contaminants from storage tanks. Water and other contaminants shall be removed from storage tanks in accordance with STI R111. ATCP 93.230 NoteNote: See s. ATCP 93.605 (1) (g) for related requirements for water in storage tanks at motor fuel dispensing facilities. ATCP 93.230(15)(15) Preparing tanks for changes in fuel type. Converting a tank from storing a different type of liquid that is regulated by this chapter shall include complying with STI R111. ATCP 93.230 NoteNote: See ss. ATCP 93.450, 93.550, and 93.680 for related requirements for changing the type of liquid stored in a tank. ATCP 93.230 HistoryHistory: CR 17-092: cr. Register October 2019 No. 766, eff. 11-1-19. ATCP 93.240(1)(1) Certifications. Persons and firms providing or supervising any of the following services shall be credentialed by the department in accordance with this chapter: ATCP 93.240(1)(c)(c) The cleaning and removal of underground storage tank systems and stationary shop-built aboveground storage tank systems. ATCP 93.240(1)(d)(d) Storage tank system precision tightness testing using equipment that is not permanently installed on the tank system. ATCP 93.240 NoteNote: All methods of precision tightness testing are required to be approved by the department in accordance with s. ATCP 93.130. ATCP 93.240(1)(f)(f) Installation of underground storage tank systems, underground piping, and shop-built aboveground storage tank systems, except this requirement does not apply to any of the following tank systems: ATCP 93.240(1)(f)2.2. Tanks or piping that are installed or constructed under the direct supervision of a registered professional engineer. ATCP 93.240 NoteNote: “Under the direct supervision of a registered professional engineer” means the registered professional engineer must be on the site during, and responsible for, the key installation and test activities described in sub. (16) (e) or (17) (e).
ATCP 93.240(2)(a)(a) Application for a certification or registration, or a certification or registration examination covered under this section shall be submitted on a form prescribed by the department. ATCP 93.240(2)(b)(b) An application for a certification or registration which either requires or recognizes the attendance at or completion of educational courses as a qualification for the certification or registration shall be accompanied by such evidence, including but not limited to transcripts, that verifies fulfillment of the prerequisite. ATCP 93.240(2)(c)(c) Applicants for any certification or registration under this chapter shall include the applicant’s social security number, or in the case of a certification or registration for a business, the applicant shall include the federal employer identification number. The department shall consider the failure by the applicant to provide a social security number or a federal employer identification number as an incomplete application and may not process the application further until the appropriate number is provided. ATCP 93.240(2)(d)(d) A business having multiple locations covered under one federal employer identification number applying for a tank specialty firm registration need not obtain a separate registration for each location. ATCP 93.240(3)(a)(a) Fees required for the various certifications or registrations and their processing under this section shall be determined in accordance with Table 93.240. Table 93.240 - Fees
ATCP 93.240 NoteNote: No application fee if application is submitted through the online application system on https://myDATCP.wi.gov. ATCP 93.240(4)(4) Processing times. An application for a certification or registration covered under this chapter shall be granted or denied by the department within 21 calendar days after the department receives all of the application materials necessary to obtain the certification or registration. If the certification or registration application information is insufficient, the department shall request additional information within 21 calendar days of receipt of the application. If an applicant does not respond to a request by the department for additional information within 3 months after the date of the request, the department shall make a determination on the application based upon the information on hand. ATCP 93.240(5)(a)(a) Unless otherwise provided by law, all orders, notices and other papers may be served by the department by 1st class mail at the address on file with the department. ATCP 93.240(5)(b)(b) A certification or registration holder shall be responsible for notifying the department of any change in mailing address. ATCP 93.240(6)(a)(a) All certifications or registrations issued under this subsection shall be valid for a period of 2 years. ATCP 93.240(6)(b)(b) All certifications or registrations issued under this subsection shall expire at 11:59 p.m. on the date of expiration. Certifications and registrations expire on the two-year anniversary of the original date of issuance. ATCP 93.240(7)(a)1.1. A notice of renewal shall be mailed by the department to a certification or registration holder at least 30 calendar days prior to the expiration of the certification or registration. ATCP 93.240(7)(a)2.2. Failure to receive a notice for renewal of a certification or registration may not be considered as an excuse or good cause for failure to renew a certification or registration prior to the expiration of the certification or registration. ATCP 93.240(7)(b)1.1. Except as provided in subd. 2. b., upon receipt of the renewal notice from the department, a person may apply to renew a certification or registration provided an application, a certification or registration fee and evidence of all renewal obligations, if any, are submitted to the department prior to the expiration date of the certification or registration. ATCP 93.240 NoteNote: Qualification obligations for renewal are specified under the appropriate certification or registration category sections.
ATCP 93.240(7)(b)2.ag.ag. A person may apply to renew a certification or registration in accordance with subd. 2. ar. no later than one two-year term after expiration of the certification or registration. An application fee as specified in Table 93.240 shall accompany the renewal application. ATCP 93.240(7)(b)2.ar.ar. A person who files for renewal after the expiration date of a certification or registration issued under subs. (13) to (20), shall comply with this chapter’s requirements for initially receiving that certification or registration. ATCP 93.240(7)(b)2.b.b. A person who files for renewal of a certification or registration issued under sub. (13), (16), or (17), and who has not obtained all continuing education credit required for renewal shall comply with this chapter’s requirements for initially receiving that certification or registration. ATCP 93.240(7)(b)2.c.c. For a certification or registration issued under sub. (13), (16), or (17), the time period for obtaining continuing education credits shall extend from the beginning date to the expiration date of that certification or registration. ATCP 93.240(8)(a)1.1. Only courses, programs, and seminars approved in writing by the department shall be used for credit to fulfill continuing education requirements. ATCP 93.240(8)(a)2.a.a. Requests for a course, program or seminar to be recognized for approval shall be submitted in writing to the department. ATCP 93.240(8)(a)2.b.b. Requests for approval shall include sufficient information to determine if the course, program or seminar complies with this subsection. ATCP 93.240(8)(a)2.c.c. The department shall review and make a determination on a request for approval within 21 calendar days of receipt of the request and information necessary to complete the review. ATCP 93.240(8)(a)3.a.a. Thirty minutes of attendance in an approved course, program or seminar shall be deemed equal to 0.5 hours of acceptable continuing education. ATCP 93.240(8)(a)3.b.b. Continuing education credit for attendance in approved continuing education courses, programs or seminars in other than 30 minute increments shall be rounded down to the next half hour. ATCP 93.240(8)(a)3.c.c. Courses, programs and seminars to be considered for approval towards continuing education credit shall relate to the skills and knowledge of one or more certification categories.
/code/admin_code/atcp/090/93
true
administrativecode
/code/admin_code/atcp/090/93/ii/230/14
Department of Agriculture, Trade and Consumer Protection (ATCP)
Chs. ATCP 90-139; Trade and Consumer Protection
administrativecode/ATCP 93.230(14)
administrativecode/ATCP 93.230(14)
section
true