NR 132.115(1)(c)1.
1. Landslides or substantial deposition from the proposed operation in stream or lake beds which cannot be feasibly prevented.
NR 132.115(1)(c)2.
2. Significant surface subsidence that cannot be reclaimed because of the geologic characteristics present at the proposed site.
NR 132.115(1)(c)3.
3. Hazards resulting in irreparable damage to any of the following that cannot be prevented under the requirements of this chapter, avoided to the extent applicable by removal from the area of hazard, or mitigated by purchase or by obtaining the consent of the owner:
NR 132.115(1)(c)4.
4. Irreparable environmental damage to lake or stream bodies despite adherence to the requirements of this chapter. This subdivision does not apply to an activity that the department has authorized pursuant to statute, except that the destruction or filling in of a lakebed shall not be authorized notwithstanding any other provision of law.
NR 132.115(1)(d)
(d) That the applicant, principal shareholder of the applicant, or a related person has, within 10 years before the application is submitted, forfeited a mining reclamation bond that was posted in accordance with a permit or other approval for a mining operation in the United States, unless the forfeiture was by agreement with the person for whose benefit the bond was posted and the amount of the bond was sufficient to cover all costs of reclamation.
NR 132.115(1)(e)
(e) That the applicant, a related person, or an officer or director of the applicant has, within 10 years before the application is submitted, been convicted of more than one felony for violations of laws for the protection of the natural environment arising out of the operation of a mining site in the United States, unless any of the following applies:
NR 132.115(1)(e)2.
2. The person convicted is a related person or an officer or director of the applicant with whom the applicant terminates its relationship.
NR 132.115(1)(e)3.
3. The applicant included in its permit application under s.
NR 132.107 plans to prevent the occurrence in this state of events similar to the events that directly resulted in the convictions.
NR 132.115(1)(f)
(f) That the applicant or a related person has, within 10 years before the application is submitted, filed a petition for bankruptcy or undergone dissolution that resulted in the failure to reclaim a mining site in the United States in violation of a state or federal law and that failure has not been remedied and is not being remedied.
NR 132.115(1)(g)
(g) That, within 10 years before the application is submitted, a mining permit or other mining approval issued to the applicant or a related person was permanently revoked because of a failure to reclaim a mining site in the United States in violation of state or federal law and that failure has not been and is not being remedied.
NR 132.115(2)
(2) The department may not deny a mining permit under sub.
(1) (d) to
(g) if the person subject to the convictions, forfeiture, permanent revocation, bankruptcy, or dissolution is a related person but the applicant shows that the person was not the parent corporation of the applicant, a person that holds more than a 30 percent ownership in the applicant, or a subsidiary or affiliate of the applicant in which the applicant holds more than a 30 percent interest at the time of the convictions, forfeiture, permanent revocation, bankruptcy, or dissolution.
NR 132.115(3)
(3) If the department denies an application for a mining permit, the department shall furnish the operator findings of fact, conclusions of law, and an order setting forth the reasons for denial.
NR 132.115 History
History: CR 20-043: cr. Register December 2021 No. 792, eff. 1-1-22. NR 132.116
NR 132.116 Reclamation bond and other financial assurance securities. NR 132.116(1)(a)
(a) Upon notification that a mining permit has been issued by the department but prior to commencing mining, the operator shall file with the department a bond conditioned on faithful performance of all of the requirements of this chapter and ch.
293, Stats. In lieu of a bond, the operator may deposit cash, certificates of deposit, or government securities with the department. Interest received on certificates of deposit and government securities shall be paid to the operator. The amount of the bond or other security required shall be equal to the estimated cost to the state of fulfilling the reclamation plan, in relation to that portion of the site that will be disturbed by the end of the following year. The department shall determine the estimated cost of reclamation of each mining site on the basis of relevant factors including expected changes in the price index, topography of the site, methods being employed, depth and composition of overburden, and depth of nonferrous metallic mineral deposit being mined.
NR 132.116(1)(b)
(b) The department, as provided under s.
293.53 (1) (a), Stats., may increase the amount of the bond, cash, certificates of deposit, or government security filed under par.
(a), to assure adequate financing for the reclamation plan.
NR 132.116(1)(c)
(c) A bond filed under par.
(a) shall be issued by a surety company licensed to do business in Wisconsin. If the surety company's license to do business is revoked or suspended, the operator, within 30 days after receiving written notice thereof from the department, shall substitute surety underwritten by a surety company licensed to do business in Wisconsin. Upon failure of the operator to make a substitution, the department shall suspend the operator's mining permit until an acceptable substitute surety has been submitted.
NR 132.116(1)(d)
(d) A bond filed under par.
(a) shall provide that the bond shall not be canceled by the surety, except after not less than 90 days' notice to the department in writing by registered or certified mail. Not less than 30 days prior to the expiration of the 90-day notice of cancellation, the operator shall deliver to the department a replacement bond in the absence of which all mining shall cease.
NR 132.116(2)
(2) Upon notification that a mining permit has been issued by the department but prior to commencing mining, the operator shall file with the department a bond issued by a surety company licensed to do business in this state, cash, certificates of deposit, or government security, to cover unforeseen remedial contingencies not otherwise covered by the bonds or other security required under sub.
(1) or
(5), including for the provision of a replacement water supply if required under s.
293.65 (4) (d), Stats. The amount of the bond or other security required shall be 10 percent of the total amount of the bonds or other security required under subs.
(1) and
(5). The operator shall increase, and may decrease, the amount of the bond or other security under this subsection according to any increase or decrease in the amount of the bonds or other security required under sub.
(1) or
(5) until the operator ceases to extract material from the mining site, at which point the amount of the bond or other security under this subsection shall remain the same until released by the department. The bond or other security under this subsection shall be released no later than 40 years after the operator ceases to extract material from the mining site.
NR 132.116(3)
(3) The applicant shall submit a certificate of insurance certifying that the applicant has in force a liability insurance policy issued by an insurer authorized to do business in this state, or in lieu of a certificate of insurance evidence that the applicant has satisfied state or federal self-insurance requirements, covering all mining operations of the applicant in this state and affording personal injury and property damage protection in a total amount deemed adequate by the department but not less than $50,000.
NR 132.116(4)
(4) Upon approval of the financial instruments related to cost of reclamation under sub.
(1) and unforeseen remedial contingency costs under sub.
(2), and the certificate of insurance under sub.
(3), the department shall issue written authorization to commence mining at the permitted mining site in accordance with the mining permit and approved mining and reclamation plans.
NR 132.116(5)
(5) If the department approves a mining
waste site as part of a permitted mining project, the owner shall maintain proof of financial responsibility ensuring the availability of funds for compliance with the long-term care requirements specified in the waste site feasibility study and plan of operation in accordance with ss.
293.51 (1g) and
289.41, Stats., and ch.
NR 182. Proof of financial responsibility for long term care shall be submitted prior to operation of the mining waste facility.
NR 132.116(6)
(6) The operator shall provide and maintain proof of financial responsibility as required under s.
293.51 (1r), Stats., related to replacement of engineered cover systems or water management control systems used at the mining site or mining waste site to avoid adverse environmental consequences following closure of the mining waste site. The department shall determine the amount of the security required under this subsection as provided in s.
293.51 (1r), Stats., and shall specify the amount as part of the mining permit and reclamation plan approval. An operator shall submit proof of financial responsibility under this subsection at the time of closure of the mining waste site and in accordance with provisions of ch.
NR 182.
NR 132.116 History
History: CR 20-043: cr. Register December 2021 No. 792, eff. 1-1-22; correction in (5) made under s. 35.17, Stats., Register December 2021 No. 792. NR 132.117(1)(1)
An operator shall monitor the mining site and adjacent areas in accordance with the monitoring plan approved as part of the mining permit. The department may require the operator to perform additional monitoring of environmental changes during the course of the permitted activity and for such additional periods of time as is necessary to satisfactorily complete reclamation of the mining site and long-term care of the mining waste facility.
NR 132.117(2)
(2) The department may monitor environmental changes concurrently with the operator as stated in sub.
(1) and for an additional period after the full reclamation bond is released under s.
293.63, Stats.
NR 132.117(3)(a)(a) The department shall review baseline data, monitoring data, and the monitoring plan at the time of annual permit review or at such time as the operator requests any modification of the mining permit, mining plan, reclamation plan, or monitoring plan.
NR 132.117(3)(b)
(b) The department shall consider baseline data and monitoring data in all enforcement actions including issuance of a stop order to an operator, requiring an immediate cessation of mining, in whole or in part, at any time that the department determines that there exists an immediate and substantial threat to public health and safety or the environment.
NR 132.117(3)(c)
(c) If the analyses of samples indicate the quality of the groundwater is statistically significantly different from either baseline or background, the operator shall notify the department immediately and implement applicable provisions of the contingency plan submitted under s.
NR 182.109 (2) (d).
NR 132.117(4)
(4) Any request for modification of the scope of the monitoring plan approved as part of the mining permit, including sampling parameters, monitoring locations and frequency and duration of sampling, shall comply with the procedures in s.
NR 132.120. Changes in monitoring equipment and sampling and analytical protocols may be reviewed and approved by the department and are not subject to the modification procedural requirements of s.
NR 132.120.
NR 132.117(5)
(5) An operator shall ensure that all laboratory chemical analyses required under the monitoring plan are conducted by a laboratory certified under s.
299.11, Stats., and ch.
NR 149 or other certification program applicable to specific test categories.
NR 132.117 History
History: CR 20-043: cr. Register December 2021 No. 792, eff. 1-1-22. NR 132.118(1)(1)
Subject to applicable state and federal safety rules or regulations, any authorized officer, employee, or representative of the department may enter and inspect any property, premises or place on or at which any mining operation or facility is located or is being constructed or installed at any reasonable time for the purpose of ascertaining the state of compliance with this chapter and chs.
30,
281,
283,
285,
289 to
292, and
299, Stats., and rules adopted under those chapters.
NR 132.118(2)
(2) No operator may refuse entry or access to any authorized representative of the department who requests entry for purposes of inspection, and who presents appropriate credentials, nor may any person obstruct, hamper, or interfere with any such inspection.
NR 132.118(3)
(3) The department shall furnish to the operator a written report on any inspection setting forth all observations, relevant information, and data that relate to compliance status.
NR 132.118 History
History: CR 20-043: cr. Register December 2021 No. 792, eff. 1-1-22. NR 132.119
NR 132.119 Reporting and mining permit review.
NR 132.119(1)(1)
Reclamation reporting. An operator shall submit all the following reports to the department documenting plans, progress, and evaluation of reclamation activities at the mining site. For each report, the operator shall provide the department with a quantity of paper copies specified by the department and shall provide a complete electronic version in a format specified by the department:
NR 132.119(1)(a)
(a) In January of each year, a report detailing planned reclamation activities the operator intends to complete in that calendar year. The plan shall document the extent of new surface disturbance, areas of the mining site that will be temporarily and permanently reclaimed during the year, site preparation activities, reclamation materials, including seed mixes, bare root stock and other materials, mining site maintenance activities, ongoing reclamation monitoring and test plot evaluation, and any other information specified by the department in the mining permit and reclamation plan approval.
NR 132.119(1)(b)
(b) By November 30 of each year, a report summarizing the extent of reclamation activities completed at the mining site during the calendar year. The report shall include descriptions, maps, and photographs documenting temporary and permanent reclamation and ongoing site maintenance activities that were completed during the year, a summary of reclamation monitoring results, an evaluation of completed reclamation as related to the reclamation success criteria specified in the approved reclamation plan, and an assessment of the effectiveness of specific reclamation activities conducted that year and recommendations for changes to specific reclamation protocols to consider for future work.
NR 132.119(2)
(2)
Annual report. By January 31 of each year, an operator of a permitted mining site shall submit an annual report to the department summarizing the extent of mining and other activities conducted at the mining site in the preceding calendar year. The operator shall provide the department with a quantity of paper copies specified by the department and shall provide a complete electronic version in a format specified by the department. The annual report shall include text, maps, tabular summaries and graphics as appropriate, documenting all of the following:
NR 132.119(2)(a)
(a) The extent of additional surface disturbance during the year and total acres of disturbed area on the mining site.
NR 132.119(2)(b)
(b) A summary of construction, mine development, and reclamation activities completed on the mining site.
NR 132.119(2)(c)
(c) The volume of material removed, stockpiled, or disposed of on the mining site including ore, concentrates, mining wastes by category, topsoil, merchantable by-product, and non-mining solid waste.
NR 132.119(2)(d)
(d) A summary of mine dewatering statistics including monthly pumping totals.
NR 132.119(2)(e)
(e) A summary of water treatment activities including monthly totals of water treated and discharged.
NR 132.119(2)(f)
(f) A summary of any incidents and related responses concerning spills, pond overflows, embankment failures or leakage, liner failures, pipeline failures or leaks, or other unforeseen environmental releases that occurred at the mining site.
NR 132.119(2)(g)
(g) A summary of any plan or permit modifications and any deviations from approved plans not subject to a modification.
NR 132.119(2)(h)
(h) A summary of environmental monitoring activities and results required under the approved monitoring plan, including an analysis of the data to determine the development of any observable trends and a comparison of the data to background values and predicted values, if predictive modeling or similar analyses were conducted as part of the mining permit review process.
NR 132.119(2)(i)
(i) A discussion of the extent of additional surface disturbance to be expected by the end of the next calendar year including estimates of the volumes of topsoil, ore, mining waste, merchantable by-products, and other materials to be removed.
NR 132.119(2)(j)
(j) An assessment of the adequacy of the amount of the financial surety posted under s.
NR 132.116 (1) considering the anticipated condition of the mining site at the end of the next calendar year, applicable provisions of the approved reclamation plan, any changes in reclamation costs or changes in state, federal or local regulatory requirements applicable to the mining operation. This analysis shall clearly identify the amount of financial security necessary to fulfill the reclamation plan relative to the mining site as it is projected to exist at the end of the calendar year.
NR 132.119(3)
(3)
Permit review. The department shall review the mining permit, mining plan, reclamation plan, and required financial securities annually after issuance of the mining permit, or as part of a review as provided in s.
NR 132.117 (3), to ascertain adequacy, compliance with state or federal laws enacted after the issuance of the permit, and technological currency. The department shall provide its findings to the operator within 30 days after receipt of the annual report submitted under sub.
(2). If the department, after review, determines that the plans should be modified or the bond amount changed, it shall notify the operator of the necessary modifications or changes and establish a schedule for submitting modified plans.
NR 132.119 History
History: CR 20-043: cr. Register December 2021 No. 792, eff. 1-1-22. NR 132.120
NR 132.120 Mining permit and plan modifications. NR 132.120(1)(1)
Modification of mining permit and associated plans. NR 132.120(1)(a)(a) Application. An operator, at any time, may apply for amendment or cancellation of a mining permit or for a change in the mining plan, reclamation plan, or monitoring plan for any mining operation that the operator owns or leases. The operator shall submit any application for the amendment, cancellation, or change in a format specified by the department. The request shall identify the tract of land to be added to or removed from the permitted mining site or to be affected by a change in the mining or reclamation plans. The request shall clearly identify any proposed changes in the mining plan, reclamation plan, or monitoring plan, reasons for the changes and anticipated environmental and economic impacts of the proposed changes.
NR 132.120(1)(b)
(b)
Procedure. Except as provided under par.
(d), the department shall process the application for an increase or decrease in the area of a mining site or for a substantial change in the mining plan, reclamation plan, or monitoring plan in the same manner as an original application for a mining permit.
NR 132.120(1)(c)
(c)
Substantial changes. The department shall determine if any change in the mining plan, reclamation plan, or monitoring plan is substantial and provide notice of its determination in the same manner as specified under s.
293.43 (2m) (b), Stats.
NR 132.120(1)(d)
(d)
Notice. The department shall provide notice of any modification that involves an increase or decrease in the area of a mining site or a substantial change in the mining plan, reclamation plan, or monitoring plan in the same manner as an original application for a mining permit under s.
293.43 (2m), Stats. If the department receives less than 5 requests in writing from interested persons for a public hearing within 30 days of notice, no hearing is required on the modification. The notice shall include a statement to this effect.
NR 132.120(1)(e)
(e)
Hearing. If the department holds a hearing, it shall be conducted as an informational hearing and shall be subject to the notice and procedural provisions under s.
293.43 (3m), Stats. The department may offer any information presented in a prior hearing on either the original application or any previous modification as part of the hearing record on the proposed modification.
NR 132.120(1)(f)
(f)
Removal. If the application cancels any portion of the unmined area of a mining site, the department shall verify that mining has not occurred on the portion of the mining site identified in the request. If the department finds that no mining has occurred, the department shall modify the mining permit and the operator's written authorization to conduct mining on the mining site accordingly and, if applicable, shall authorize the operator to modify the financial securities required under s.
NR 132.116 to reflect the decrease in the mining site.
NR 132.120(2)
(2)
Department request for modification of mining or reclamation plan. The department, as provided under s.
293.55 (2), Stats., may require an operator to submit amended mining and reclamation plans if the department determines the existing plans are no longer sufficient to reasonably provide for reclamation of the mining site.
NR 132.120 History
History: CR 20-043: cr. Register December 2021 No. 792, eff. 1-1-22. NR 132.121
NR 132.121 Temporary cessation of mining. NR 132.121(1)(1)
If there is a cessation of mining or reclamation expected to last 30 days or more that is not set forth in either the mining plan or the reclamation plan, the operator shall notify the department of the cessation within 48 hours of the cessation of mining and shall begin stabilization of the mining site. If the cessation of mining extends for more than 6 consecutive months, the operator shall begin final reclamation of the mining site in accordance with the approved reclamation plan unless all of the following apply:
NR 132.121(1)(a)
(a) The cessation of mining is due either to labor strikes or to such unforeseen developments as adverse market conditions, as determined by the department.
NR 132.121(1)(b)
(b) The cessation of mining does not continue beyond the time specified by the department. The time limit specified by the department may not exceed 5 years.
NR 132.121(1)(c)
(c) The operator maintains the site in an environmentally stable manner, as determined by the department, during the cessation of mining.
NR 132.121(1)(d)
(d) The operator continues the reclamation of the site according to appropriate provisions of the reclamation plan during the cessation of mining.
NR 132.121(1)(e)
(e) The operator continues environmental monitoring in accordance with the monitoring plan during the cessation of mining, as determined by the department.
NR 132.121(2)
(2) The operator shall identify in the notice provided under sub.
(1) the reasons for the temporary shutdown, the anticipated duration of the shutdown, the measures that will be taken to ensure environmental stability of the mining site during the shutdown, procedures required to resume operation of project facilities following the shutdown, and which specific environmental monitoring activities, if any, will be discontinued during the shutdown.
NR 132.121(3)
(3) Temporary cessation of mining described in a notice submitted under sub.
(1) shall constitute a substantial modification of the mining plan under s.
293.55, Stats., and the department shall process the modification in accordance with the applicable procedures under s.
NR 132.120 and s.
293.55, Stats.
NR 132.121(4)
(4) The department's decision on the request for temporary cessation of mining status shall specify the approved duration of the cessation of mining, required stabilization and reclamation measures to be implemented during the cessation, required environmental monitoring activities, and any other conditions necessary to ensure environmental protection during the temporary shutdown and anticipated resumption of mining activities.
NR 132.121 History
History: CR 20-043: cr. Register December 2021 No. 792, eff. 1-1-22; correction in (1) (intro.), (b) made under s. 35.17, Stats., Register December 2021 No. 792. NR 132.122
NR 132.122 Certificate of completion of reclamation and reclamation bond release. NR 132.122(1)(1)
Upon completion of final reclamation in accordance with the approved reclamation plan for a portion of the mining site or the entire mining site the operator may provide notice to the department that final reclamation has been completed. The notice shall include all of the following:
NR 132.122(1)(a)
(a) Clear delineation of the portion of the mining site addressed by the notification.