AB426,157,1919
(d) Erosion below any conduit.
AB426,157,2020
(e) Wet areas or soggy soil on the outside of, or in natural soil below, the dam.
AB426,157,25
21(7) Record keeping related to dams. (a) The operator shall retain all records
22relating to dam monitoring, analytical, and verification activities and data,
23including all original strip chart recordings and instrumentation, calibration, and
24maintenance records, until termination of operator responsibility, except to the
25extent that copies of those records have previously been provided to the department.
AB426,158,3
1(b) The operator shall maintain in a permanent file all of the following
2construction records pertaining to any dam in case they are needed for future
3reference:
AB426,158,44
1. Aerial photos of the construction site before construction.
AB426,158,55
2. Construction drawings and modifications of the drawings.
AB426,158,66
3. Construction specifications and modifications of the specifications.
AB426,158,77
4. Results of all soil tests on foundations and fill materials.
AB426,158,88
5. Logs of borings and engineering geology reports.
AB426,158,119
6. Copies of construction progress inspections pertinent to core trench, toe
10drain, internal drains, and other significant phases of the structure including, at the
11option of the operator, photographs of various structural items.
AB426,158,1312
7. Aerial photos of the entire dam taken within 90 days after all construction
13is completed.
AB426,158,1514
8. A description of and justification for all deviations or variances from the
15construction plans and specifications.
AB426,158,21
16(8) Responses to unplanned events. If a mining waste site has an accidental
17or emergency discharge, a fire, an explosion, or other unplanned or unpredicted
18event that is likely to damage human health or the environment, the operator shall
19follow the procedures set forth in the contingency plan under s. 295.51 (6) (f) and
20shall report the incident to the department and to county, town, and tribal
21governmental agencies immediately after the operator has discovered the event.
AB426,158,23
22(9) Annual report. The operator shall submit to the department an annual
23summary report concerning the mining waste site containing all of the following:
AB426,158,2424
(a) Statistical summaries of annual and cumulative data.
AB426,159,4
1(b) A comparison of the summaries under par. (a) to mining waste
2characterization, leachate characterizations, effluent predictions, and baseline
3water quality and background water quality data as contained in the approved
4mining waste site feasibility study and plan of operation.
AB426,159,65
(c) The results of verification procedures and a presentation of the error
6associated with each parameter reported.
AB426,159,97
(d) Information from monitoring wells that have not been affected, including
8a discussion of whether the baseline values should be modified due to natural
9variability and what the new values should be.
AB426,159,11
10(10) Applicability. This section does not apply to a surface mine that is
11backfilled with mining waste.
AB426,159,18
12295.64 Mining site monitoring; general.
(1) General. The department,
13as a condition of a mining permit, shall require the operator to perform adequate
14monitoring of environmental changes during the course of the mining and for the
15additional period of time that is necessary to satisfactorily complete reclamation and
16completely release the operator from any bonds or other security required. The
17department may monitor environmental changes concurrently with the operator
18and for an additional period after the security is released.
AB426,159,23
19(2) Analyses. (a) The department shall review baseline water quality data
20with respect to groundwater and monitoring data associated with the mine, mining
21waste sites, and sites for the disposal of wastes that are not mining wastes at the time
22of each review of the mining permit or reclamation plan under s. 295.63 (3) and when
23the operator requests a modification of the mining permit or reclamation plan.
AB426,160,524
(b) An operator shall have bacteriological analyses of water samples and all
25radiological analyses associated with the mining site performed by the state
1laboratory of hygiene or at a laboratory certified or approved by the department of
2health services. An operator shall have other laboratory tests the results of which
3are submitted to the department under this subchapter performed by a laboratory
4certified or registered under s. 299.11, except that this requirement does not apply
5to any of the following:
AB426,160,66
1. Physical testing of soil.
AB426,160,77
2. Air quality tests.
AB426,160,88
3. Tests for hydrogen ion concentration (pH).
AB426,160,99
4. Tests for chlorine residual.
AB426,160,1010
5. Tests for temperature.
AB426,160,13
11295.643 Mining waste site monitoring.
(1) General. The department may
12require the monitoring of groundwater, surface water, leachate, or other physical
13features associated with a mining waste site.
AB426,160,19
14(2) Physical features. The department may require the monitoring of air
15quality, berms, embankments, vegetation growth, and drainage control structures
16associated with the mining waste site. The department may require monitoring of
17other chemical or biological conditions, if the department determines that the
18monitoring is necessary to assess the impact of the mining waste site on critical
19aquatic and terrestrial ecosystems.
AB426,160,24
20(3) Monitoring wells and other devices. (a) The department shall require
21the installation of groundwater monitoring wells at a mining waste site. The
22department may require installation of leachate monitoring wells, lysimeters,
23moisture probes, and similar devices and associated water quality sampling and
24analysis programs to detect the effects of leachate on groundwater.
AB426,161,6
1(b) The department shall determine the required number of groundwater
2monitoring wells based on the size of the mining waste site, the design of the mining
3waste site, the types of mining waste, and the hydrologic and geologic setting of the
4mining waste site. The department shall ensure that the number of wells is adequate
5to yield samples representative of the groundwater quality both up gradient and
6down gradient of the mining waste site.
AB426,161,97
(c) An operator shall construct all monitoring wells in accordance with ch. NR
8141, Wis. Adm. Code, and in such a manner as to prevent, to the extent practicable,
9the exchange of water between aquifers.
AB426,161,13
10(4) Destruction of monitoring devices. (a) If for any reason a monitoring well
11or other monitoring device associated with a mining waste site is destroyed or
12otherwise fails to function properly, the operator shall notify the department in
13writing within 5 days of discovering the destruction or malfunction.
AB426,161,1714
(b) The operator shall either restore the monitoring well or other device or
15properly abandon it and replace it with a functioning device within 60 days of
16notifying the department under par. (a) unless the department notifies the operator
17otherwise in writing within 30 days of receiving notice from the operator.
AB426,161,22
18(5) Sampling other wells. The department may require an operator to sample
19public or private wells as part of a regular monitoring program or to determine the
20extent of groundwater contamination associated with a mining waste site. If the
21owner of a well does not authorize access for sampling, the operator shall promptly
22notify the department.
AB426,162,6
23(6) Required monitoring and analysis. (a) An operator shall monitor
24groundwater at locations identified in the waste site feasibility study and plan of
25operation on a quarterly basis, during March, June, September, and December,
1unless the department agrees to an alternate schedule. The department may base
2an alternate schedule on the hydrogeologic system's characteristics, such as flow
3velocity and stratigraphy, and on fluctuations in quality as determined through
4background water quality or baseline water quality sampling and mining waste
5type. The operator shall analyze for the parameters listed in the approved waste site
6feasibility study and plan of operation.
AB426,162,97
(b) An operator shall use the methods for groundwater and surface water
8sample collection, preservation, and analysis that are specified in the approved
9mining waste site facility study and plan of operation.
AB426,162,11
10(7) Water elevation measurements. The operator shall make water elevation
11measurements on a quarterly basis.
AB426,162,19
12(8) Operations report. The department may require an operator to submit an
13operations report to assess the effectiveness and environmental acceptability of
14mining waste site operations. The operator may include in the report a discussion
15of confinement of the active fill area and an analysis of leachate and other
16monitoring, surface water control and erosion control, revegetation, settlement,
17volume of the mining waste site utilized, leachate quantity and quality, slope
18stability, equipment performance, volume and type of waste disposed of, and other
19relevant parameters.
AB426,162,22
20(9) Reports of monitoring data. The operator shall forward to the department,
21within 60 days after sampling, 3 copies of the monitoring data required by this
22section to be collected during each quarter.
AB426,162,24
23295.645 Groundwater quality, monitoring, and response. (1) 24Definitions. In this section:
AB426,163,3
1(a) "Alternative concentration limit" means the concentration of a substance
2in groundwater established by the department to replace a groundwater quality
3standard when the department grants an exemption.
AB426,163,64
(b) "Statistically significantly different" means an amount of change
5determined by the use of statistical tests for measuring significance at the 95 percent
6confidence level.
AB426,163,14
7(2) Design management zone. (a) Notwithstanding the rule-making authority
8in s. 160.21 (2) and except as provided under par. (b), for the purposes of ch. 160, the
9horizontal distance to the boundary of the design management zone for a mining
10operation is 1,200 feet from the limits of the engineered structures of the mining
11waste site, including any wastewater and sludge storage or treatment lagoons, the
12edge of the mine, and the adjacent mine mill and ferrous mineral processing facilities
13or at the boundary of the property owned or leased by the applicant, whichever
14distance is less.
AB426,163,2015
(b) When issuing or modifying a mining permit or issuing or reissuing any other
16approval, the department may expand the design management zone by a horizontal
17distance of up to an additional 1,200 feet in any direction as provided in this
18paragraph, but not beyond the boundary of the property owned or leased by the
19applicant. The department may not expand the design management zone unless the
20applicant demonstrates all of the following:
AB426,163,2321
1. That preventive action limits and enforcement standards or alternative
22concentration limits cannot be met at the boundary of the design management zone
23if it is not expanded.
AB426,164,3
12. That preventive action limits and enforcement standards or alternative
2concentration limits will be met at the boundary of the expanded design
3management zone.
AB426,164,84
(c) Notwithstanding the rule-making authority in s. 160.21 (2), for the
5purposes of ch. 160, the vertical distance to the boundary of the design management
6zone for a mining site, including any mining waste site, extends no deeper than 1,000
7feet into the Precambrian bedrock or than the final depth of the mining excavation,
8whichever is greater.
AB426,164,17
9(3) Point of standards application. (a) Any point at which groundwater is
10monitored is a point of standards application to determine whether a preventive
11action limit or an alternative concentration limit to a preventive action limit has been
12attained or exceeded for an activity regulated under a mining permit or another
13approval related to the mining operation. Any of the following is a point of standards
14application to determine whether an enforcement standard or an alternative
15concentration limit to an enforcement standard has been attained or exceeded for an
16activity regulated under a mining permit or another approval related to the mining
17operation:
AB426,164,1818
1. Any point of present groundwater use.
AB426,164,2019
2. Any point beyond the boundary of the property on which the activity is
20conducted, subject to par. (b).
AB426,164,2221
3. Any point that is within the boundary of the property on which the activity
22is conducted but is beyond the design management zone, subject to par. (b).
AB426,164,2523
(b) No point at a depth of greater than 1,000 feet into the Precambrian bedrock
24or than the final depth of the mining excavation, whichever is greater, is a point of
25standards application under this subsection.
AB426,165,2
1(c) Section 160.21 (2) does not apply to an activity regulated under this
2subchapter.
AB426,165,8
3(4) Change in groundwater quality. If the analysis of samples collected
4through monitoring indicates that the quality of groundwater is statistically
5significantly different from either baseline water quality or background water
6quality and the evaluation of the data shows a reasonable probability that without
7intervention groundwater quality standards or alternative concentration limits will
8be attained or exceeded, the operator shall do all of the following:
AB426,165,109
(a) Notify the department within 10 days after the operator receives the results
10of the analysis of the samples.
AB426,165,1211
(b) Determine, if possible, the cause of the difference in water quality, such as
12a spill, a design failure, or an improper operational procedure.
AB426,165,1413
(c) Determine the extent of groundwater contamination or the potential for
14groundwater contamination.
AB426,165,1515
(d) Implement the applicable portions of the approved contingency plan.
AB426,166,10
16(5) Response concerning preventive action limits. In accordance with s. NR
17140.24 (1) to (5), Wis. Adm. Code, the department shall evaluate the range of
18responses proposed by the operator when a preventive action limit or an alternative
19concentration limit to a preventive action limit is attained or exceeded and the
20analysis of samples indicates that the quality of groundwater is statistically
21significantly different from either baseline water quality or background water
22quality at a point of standards application. In designating the appropriate response,
23the department shall evaluate the operator's proposed range of responses, including
24any alternate responses to those identified in s. NR 140.24, Wis. Adm. Code. For any
25alternate responses, the department shall consider the technical and economic
1feasibility of alternate responses, the practicality of stopping the further release of
2the substance, and the risks and benefits of continued mining operations. The
3department shall designate the appropriate response, except that, notwithstanding
4s. 160.21 (3) and the rule-making authority under s. 160.21 (1), the department may
5not prohibit a practice or activity or require closure and abandonment of a mining
6waste site, including any wastewater and sludge storage or treatment lagoon, unless
7it has followed the procedures in s. 295.78 and satisfies the requirements of s. 160.23
8(4) and (6). The department may determine that no response is necessary and that
9an exemption is not required when the requirements of s. NR 140.24 (5) (a) or (b), Wis.
10Adm. Code are met.
AB426,166,25
11(6) Response concerning enforcement standards. (a) In accordance with s.
12NR 140.26 (1) and (2), Wis. Adm. Code, the department shall evaluate the range of
13responses proposed by the operator based on the responses listed in Table 6 of s. NR
14140.26, Wis. Adm. Code, when an enforcement standard or an alternative
15concentration limit to an enforcement standard is attained or exceeded and the
16analysis of samples indicates that the quality of groundwater is statistically
17significantly different from either baseline water quality or background water
18quality at a point of standards application. In designating the appropriate response,
19the department shall evaluate the operator's proposed range of responses against
20those identified in Table 6 of s. NR 140.26, Wis. Adm. Code. The department shall
21designate the appropriate response, except that, notwithstanding ss. 160.21 (3) and
22160.25 (1) (a) and the rule-making authority under s. 160.21 (1), the department may
23not prohibit a practice or activity or require closure and abandonment of a mining
24waste site, including any wastewater and sludge storage or treatment lagoon, unless
25it has followed the procedures in s. 295.78 and all of the following apply:
AB426,167,1
11. The department bases its decision upon reliable test data.
AB426,167,42
2. The department determines, to a reasonable certainty, by the greater weight
3of the credible evidence, that no other remedial action would prevent the violation
4of the enforcement standard at the point of standards application.
AB426,167,65
3. The department establishes the basis for the boundary and duration of the
6prohibition.
AB426,167,97
4. The department ensures that any prohibition imposed is reasonably related
8in time and scope to maintaining compliance with the enforcement standard at the
9point of standards application.
AB426,167,1710
5. If the substance involved is naturally occurring, unless the substance
11involved is carcinogenic, teratogenic, or mutagenic in humans, the department
12considers the existence of the background concentration of the substance in
13evaluating response options to the noncompliance with the enforcement standard or
14alternative concentration limit for that substance and determines that the proposed
15prohibition will result in the protection of or substantial improvement in
16groundwater quality notwithstanding the background concentrations of the
17substance.
AB426,167,2318
(b) The department may only require a remedial action to be taken if the
19remedial action is reasonably related in time and scope to the substance, activity, or
20practice that caused the enforcement standard or alternative concentration limit to
21an enforcement standard to be attained or exceeded and the quality of groundwater
22to be statistically significantly different from either baseline water quality or
23background water quality at the point of standards application.
AB426,168,1024
(c) If nitrates or any substance of welfare concern attains or exceeds an
25enforcement standard and if the analysis of samples indicates that the quality of
1groundwater is statistically significantly different from either baseline or
2background water quality, then the department shall evaluate whether the
3enforcement standard was attained or exceeded in whole or in part due to high
4background water quality concentrations of the substance and whether the
5additional concentrations represent a public welfare concern before it designates the
6appropriate response and, notwithstanding ss. 160.21 (3) and 160.25 (1) (a) and the
7rule-making authority under s. 160.21 (1), the department may not prohibit a
8practice or activity or require closure and abandonment of a mining waste site,
9including any wastewater and sludge storage or treatment lagoon, unless it has
10followed the procedures in s. 295.78 and par. (a) 1. to 4. apply.
AB426,168,1211
(d) If compliance with an enforcement standard is achieved at a point of
12standards application, then sub. (5) applies.
AB426,168,14
13(7) Environmental analysis not required. An action under sub. (5) or (6) with
14respect to a specific site does not constitute a major state action under s. 1.11 (2).
AB426,168,18
15(8) Exemptions to groundwater quality standards. When issuing or
16modifying a mining permit or issuing or reissuing any other approval, the
17department may grant an exemption from a groundwater quality standard and
18establish an alternative concentration limit to a groundwater quality standard.
AB426,168,21
19(9) Applicability of other law. Chapter NR 140, Wis Adm. Code, applies to
20mining operations and mining sites, including mining waste sites, only to the extent
21that it does not conflict with this section.
AB426,169,2
22295.65 Successors. (1) When one operator succeeds to the interest of another
23in an uncompleted mining operation by sale, assignment, lease, or otherwise, the
24department shall release the first operator from the duties imposed upon the first
25operator by this subchapter as to the mining operation and transfer the mining
1permit and any approvals under ss. 295.60, 295.605, and 295.61 to the successor
2operator if all of the following apply:
AB426,169,43
(a) The successor operator agrees to comply with the requirements of this
4subchapter.
AB426,169,85
(b) The successor operator discloses whether it has forfeited any performance
6security because of noncompliance with any mining laws within the previous 10
7years, posts any bond or other security required under s. 295.59, and assumes all
8responsibilities of all applicable approvals granted to the predecessor operator.
AB426,169,10
9(2) The department is not required to prepare an environmental impact
10statement or an environmental assessment for the purposes of this section.
AB426,169,25
11295.66 Cessation of mining or reclamation. If there is a cessation of
12mining or reclamation for 30 days or more that is not set forth in either the mining
13plan or the reclamation plan, the operator shall notify the department of the
14cessation within 48 hours of the cessation of mining and shall begin stabilization of
15the mining site. The department may require the operator to provide technical,
16engineering, and any other information that the operator believes shows that its
17actions to stabilize the mining site are adequate. If the department determines, after
18reviewing the information provided by the operator, that the proposed stabilization
19of the mining site will result in a substantial adverse impact to the environment, the
20department shall order the operator to begin additional measures to protect the
21environment, including, if the cessation is reasonably anticipated to extend for a
22protracted period of time, reclamation according to the reclamation plan or part of
23the reclamation plan. Usual and regular shutdown of operations on weekends, for
24maintenance or repair of equipment or facilities, or for other customary reasons do
25not constitute a cessation of mining.
AB426,170,4
1295.67 Determination of abandonment of mining. (1) Except as provided
2in sub. (2), abandonment of mining occurs if there is a cessation of mining, not set
3forth in an operator's mining plan or reclamation plan or by any other sufficient
4written or constructive notice, extending for more than 6 consecutive months.
AB426,170,5
5(2) Abandonment of mining does not occur if all of the following apply:
AB426,170,76
(a) The cessation of mining is due either to labor strikes or to unforeseen
7developments such as adverse market conditions.
AB426,170,98
(b) The cessation of mining does not continue beyond the time, not to exceed
95 years, specified by the department.
AB426,170,1110
(c) The mining site is maintained in an environmentally stable manner during
11the cessation of mining.
AB426,170,1312
(d) The reclamation of the mining site continues according to the reclamation
13plan during the cessation of mining to the extent practicable.
AB426,170,23
14295.68 Certificates of completion and release of security. (1) Upon the
15petition of the operator, but not less than 4 years after notification to the department
16by the operator of the completion of the reclamation plan or not less than one year
17after notification to the department by the operator of the completion of the
18reclamation plan as to a portion of the mining site, if the department finds that the
19operator has completed reclamation of any portion of the mining site in accordance
20with the reclamation plan and this subchapter, the department shall issue a
21certificate of completion setting forth a description of the area reclaimed and a
22statement that the operator has fulfilled its duties under the reclamation plan as to
23that area.
AB426,171,4
24(2) Upon the issuance of any certificate of completion under sub. (1) for any
25portion of the mining site, but not for the entire mining site, the department shall
1allow the operator to reduce the amount of the bond or other security provided under
2s. 295.59 (1) to an amount equal to the estimated cost of reclamation of the portion
3of the mining site that is disturbed or for which reclamation has been completed but
4no certificate of completion has been issued.
AB426,171,10
5(3) Upon issuance of a certificate or certificates of completion of reclamation
6for the entire mining site, the department shall require the operator to maintain a
7bond or other security under s. 295.59 (1) equal to at least 10 percent of the cost to
8the state of reclamation of the entire mining site, except that if the mining site in the
9mining plan is less than 10 acres, the department may release the bond or other
10security after issuance of the certificate of completion for the entire mining site.
AB426,171,14
11(4) After 10 years after the issuance of a certificate or certificates of completion
12for the entire mining site, the department shall release the remaining bond or other
13security provided under s. 295.59 (1) if the department finds that the reclamation
14plan has been complied with.
AB426,172,4
15295.69 Termination of proof of financial responsibility for long-term
16care of mining waste site. (1) One year after closure, and annually thereafter
17until the department terminates the obligation to maintain proof of financial
18responsibility for long-term care of a mining waste site under sub. (2) (c), an operator
19who has carried out all necessary long-term care during the preceding year, may
20apply to the department for a reduction in the amount of the proof of financial
21responsibility provided under s. 295.59 (2m) equal to the costs of long-term care for
22that year. The operator shall provide an itemized list of costs incurred. If the
23department determines that the costs incurred are in accordance with the long-term
24care requirements in the approved waste site feasibility study and plan of operation
25and that adequate funds exist to complete required long-term care for the remainder
1of the 40-year period on which the amount of the proof of financial responsibility was
2originally determined, the department shall authorize in writing a reduction in the
3amount of proof of financial responsibility provided. The department shall make its
4determinations within 90 days of an application.
AB426,172,14
5(2) (a) An operator may apply to the department for termination of its
6obligation to maintain proof of financial responsibility for long-term care of the
7mining waste site under s. 295.59 (2m) at any time after the mining waste site has
8been closed for 20 years by submitting an application that demonstrates that
9continuation of the obligation to maintain proof of financial responsibility for
10long-term care is not necessary for adequate protection of public health or the
11environment. The burden is on the operator to prove by a preponderance of the
12evidence that continuation of the obligation to maintain proof of financial
13responsibility for long-term care is not necessary for adequate protection of public
14health or the environment.