Procedures for utility facility approvals
Under current law, with certain exceptions, a person may not begin the
construction of certain utility facilities before the Public Service Commission (PSC)
has issued to the person either a certificate of public convenience and necessity
(CPCN) or a certificate authorizing the person to transact public utility business
(PSC certificate). Current law also provides that a utility facility that is required to
obtain a PSC certificate and that is required to obtain one or more permits from the
Department of Natural Resources (DNR), such as a permit allowing the placement
of a structure in navigable waters, must use a procedure that requires the utility
facility to submit only one application to DNR for all of the required DNR permits
(combined permit procedure) rather than submitting separate applications to DNR
for each permit. Current law also specifies that the applicant under the combined
permit procedure must submit the combined application for permits to DNR at the
same time that the applicant files an application for a PSC certificate.
This bill makes the combined permit procedure optional for an applicant
proposing to construct a utility facility for iron mining activities and allows the
applicant to submit separate applications to DNR for each required permit. Under
the bill, if the utility facility does not use the combined permit procedure, it is not
required to file a DNR permit application at the same time that it files an application
for a PSC certificate.
Current law requires a person proposing to construct a large electric generating
facility or high-voltage transmission line (facility) to provide DNR with an
engineering plan or project plan for the facility at least 60 days before filing an
application with PSC for a CPCN. Within 30 days thereafter, DNR must provide the
person with a listing of each DNR approval that appears to be required for the
construction or operation of the facility. Current law requires the person to file the
application for these approvals within 20 days after receiving the listing from DNR.
This bill eliminates this 20-day deadline for a person proposing to construct a facility
for iron mining activities and also specifies that the person must only apply for those
approvals identified in the listing that are applicable.
Shoreland and floodplain zoning
Current law prohibits locating a solid waste facility in an area that is covered
by a shoreland or floodplain zoning ordinance unless the facility is authorized under
a permit issued by DNR. This bill requires DNR to specify in the permit the
authorized location, height, and size of the facility that may be located in the area.
This bill also specifies that DNR may not prohibit a waste site, structure, building,
fill, or other development or construction activity (activity) to be located in an area
that would otherwise be prohibited under a shoreland zoning ordinance if the
activity is authorized by DNR as part of a mining operation covered by an iron mining
permit.
Current law provides that a structure, building, fill, or development (structure)
that is placed or maintained in a floodplain in violation of a floodplain zoning
ordinance is a public nuisance and provides that any person placing or maintaining
the structure may be subject to a fine. The bill specifies that these provisions do not
apply to a structure placed or maintained as part of a mining operation covered by
an iron mining permit issued by DNR, except to the extent necessary for the
municipality to which the ordinance applies to maintain eligibility for participation
in the National Flood Insurance Program.
Local impact committees
Current law authorizes a local or tribal government likely to be substantially
affected by proposed metallic mining to establish a local impact committee for
purposes that include facilitating communications with the mining company,
reviewing and commenting on reclamation plans, and negotiating an agreement
between the local or tribal government and the mining company. The law requires
the mining company to appoint a person to be the liaison with the local impact
committee and requires the mining company to make reasonable efforts to design
and carry out mining operations in harmony with community development
objectives. Under some circumstances, a local impact committee may receive
funding from the investment and local impact fund board.
This bill provides for local impact committees for proposed iron mines in a
manner similar to the manner in which those committees are established under
current law.
Rights and conditions relating to mining contracts and leases
Current law establishes certain rights and imposes certain conditions with
respect to contracts or leases that authorize a person to dig for ores and minerals,
including the conditions under which a miner may retain ore and minerals
discovered on the land, a miner's obligation to keep and to provide certain records
concerning mine operations, and the consequences to a miner who conceals or
disposes of any ores or minerals for the purpose of defrauding a lessor. Current law
also establishes a maximum term for exploration mining leases with regard to
minerals that contain metals.
This bill limits these current law provisions to mining activities relating to
nonferrous metallic mining.
For further information see the state and local fiscal estimate, which will be
printed as an appendix to this bill.
The people of the state of Wisconsin, represented in senate and assembly, do
enact as follows:
SB1,1
1Section
1. 20.370 (2) (gh) of the statutes is amended to read:
SB1,27,62
20.370
(2) (gh)
Mining — Nonferrous metallic mining regulation and
3administration. The amounts in the schedule for the administration, regulation and
4enforcement of
nonferrous metallic mining exploration, prospecting, mining and
5mine reclamation activities under ch. 293. All moneys received under ch. 293 shall
6be credited to this appropriation.
SB1,2
7Section
2. 20.370 (2) (gi) of the statutes is created to read:
SB1,27,108
20.370
(2) (gi)
Ferrous metallic mining operations. All moneys received under
9subch. III of ch. 295 for the department of natural resource's operations related to
10ferrous metallic exploration and mining.
SB1,3
11Section
3. 20.455 (1) (gh) of the statutes is amended to read:
SB1,28,212
20.455
(1) (gh)
Investigation and prosecution. Moneys received under ss. 23.22
13(9) (c), 49.49 (6), 100.263, 133.16, 281.98 (2), 283.91 (5), 289.96 (3) (b), 291.97 (3),
1292.99 (2), 293.87 (4) (b), 295.19 (3) (b) 2.,
295.79 (4) (b), and 299.97 (2), for the
2expenses of investigation and prosecution of violations, including attorney fees.
SB1,4
3Section
4. 20.566 (7) (e) of the statutes is amended to read:
SB1,28,64
20.566
(7) (e)
Investment and local impact fund supplement. The amounts in
5the schedule to supplement par. (v) for the purposes of ss. 70.395, 293.33 (4)
and,
6293.65 (5) (a)
, 295.443, and 295.61 (9) (a) and (c).
SB1,5
7Section
5. 20.566 (7) (v) of the statutes is amended to read:
SB1,28,118
20.566
(7) (v)
Investment and local impact fund. From the investment and local
9impact fund, all moneys received under s. 70.395 (1e) and (2) (dc) and (dg), less the
10moneys appropriated under s. 20.370 (2) (gr), to be disbursed under ss. 70.395 (2) (d)
11to (g), 293.33 (4)
and, 293.65 (5) (a)
, 295.443, and 295.61 (9) (a) and (c).
SB1,6
12Section
6. 23.321 (2g) of the statutes is created to read:
SB1,28,1813
23.321
(2g) Services for mining operations. In addition to those persons
14authorized to request a wetland identification or confirmation under sub. (2) (b) or
15(c), a holder of an easement may request such an identification or confirmation if the
16identification or confirmation is associated with an application for a wetland
17individual permit or other approval for which a wetland impact evaluation is
18required and that is subject to s. 295.60.
SB1,7
19Section
7. 25.46 (7) of the statutes is amended to read:
SB1,28,2220
25.46
(7) The fees imposed under s. 289.67 (1) for environmental management,
21except that
for each ton of waste, of the fees imposed under s. 289.67 (1) (cp) or (cv),
22$3.20
for each ton of waste is for nonpoint source water pollution abatement.
SB1,8
23Section
8. 25.49 (2m) of the statutes is created to read:
SB1,28,2424
25.49
(2m) The moneys transferred under s. 70.395 (1e).
SB1,9
25Section
9. 29.604 (4) (intro.) of the statutes is amended to read:
SB1,29,2
129.604
(4) Prohibition. (intro.) Except as provided in sub. (6r)
and (7m) or as
2permitted by departmental rule or permit:
SB1,10
3Section
10. 29.604 (4) (c) (intro.) of the statutes is amended to read:
SB1,29,84
29.604
(4) (c) (intro.) No person may do any of the following to any wild plant
5of an endangered or threatened species that is on public property or on property that
6he or she does not own or lease, except in the course of forestry or agricultural
7practices
or, in the construction, operation
, or maintenance of a utility facility
, or as
8part of bulk sampling activities under s. 295.45:
SB1,11
9Section
11. 29.604 (7m) of the statutes is created to read:
SB1,29,1610
29.604
(7m) Bulk sampling activities. A person may take, transport, or
11possess a wild animal on the department's endangered and threatened species list
12without a permit under this section if the person avoids and minimizes adverse
13impacts to the wild animal to the extent practicable, if the taking, transporting, or
14possession does not result in wounding or killing the wild animal, and if the person
15takes, transports, or possesses the wild animal for the purpose of bulk sampling
16activities under s. 295.45.
SB1,12
17Section
12. 30.025 (1e) (a) of the statutes is amended to read:
SB1,29,2018
30.025
(1e) (a) Except as provided in
par. pars. (b)
and (c), this section applies
19to a proposal to construct a utility facility if the utility facility is required to obtain,
20or give notification of the wish to proceed under, one or more permits.
SB1,13
21Section
13. 30.025 (1e) (c) of the statutes is created to read:
SB1,29,2522
30.025
(1e) (c) This section does not apply to a proposal to construct a utility
23facility for ferrous mineral mining and processing activities governed by subch. III
24of ch. 295, unless the person proposing to construct the utility facility elects to
25proceed in the manner provided under this section.
SB1,14
1Section
14. 30.025 (1m) (intro.) of the statutes is amended to read:
SB1,30,92
30.025
(1m) Preapplication process. (intro.) Before filing
an a combined 3application
under this section for permits under sub. (1s) with the department in lieu
4of separate applications, a person proposing to construct a utility facility shall notify
5the department of the intention to file
an a combined application
under sub. (1s).
6After receiving such notice, the department shall confer with the person, in
7cooperation with the commission, to make a preliminary assessment of the project's
8scope, to make an analysis of alternatives, to identify potential interested persons,
9and to ensure that the person making the proposal is aware of all of the following:
SB1,15
10Section
15. 30.025 (1m) (c) of the statutes is amended to read:
SB1,30,1411
30.025
(1m) (c) The timing of information submissions that the person will be
12required to provide in order to enable the department to participate in commission
13review procedures and to process the
combined application
for permits in a timely
14manner.
SB1,16
15Section
16. 30.025 (1s) (a) of the statutes is amended to read:
SB1,30,2516
30.025
(1s) (a) Any person proposing to construct a utility facility to which this
17section applies shall, in lieu of separate application for permits, submit one
combined 18application for permits together with any additional information required by the
19department. The
combined application
for permits shall be filed with the
20department at the same time that an application for a certificate is filed with the
21commission under s. 196.49 or in a manner consistent with s. 196.491 (3) and shall
22include the detailed information that the department requires to determine whether
23an a combined application
for permits is complete and to carry out its obligations
24under sub. (4). The department may require supplemental information to be
25furnished thereafter.
SB1,17
1Section
17. 30.025 (2) of the statutes is amended to read:
SB1,31,212
30.025
(2) Hearing. Once the applicant meets the requirements of sub. (1s) (a),
3the department may schedule the matter for a public hearing. Notice of the hearing
4shall be given to the applicant and shall be published as a class 1 notice under ch.
5985 and as a notice on the department's Internet Web site. The department may give
6such further notice as it deems proper, and shall give notice to interested persons
7requesting same. The department's notice to interested persons may be given
8through an electronic notification system established by the department. Notice of
9a hearing under this subsection published as a class 1 notice, as a notice on the
10department's Internet Web site, and through the electronic notification system
11established by the department shall include the time, date, and location of the
12hearing, the name and address of the applicant, a summary of the subject matter of
13the
combined application
for permits, and information indicating where a copy of the
14combined application
for permits may be viewed on the department's Internet Web
15site. The summary shall contain a brief, precise, easily understandable, plain
16language description of the subject matter of the application. One copy of the
17combined application
for permits shall be available for public inspection at the office
18of the department, at least one copy in the regional office of the department, and at
19least one copy at the main public library, of the area affected. Notwithstanding s.
20227.42, the hearing shall be an informational hearing and may not be treated as a
21contested case hearing nor converted to a contested case hearing.
SB1,18
22Section
18. 30.025 (2g) (b) (intro.) of the statutes is amended to read:
SB1,32,423
30.025
(2g) (b) (intro.) The department shall participate in commission
24investigations or proceedings under s. 196.49 or 196.491 (3) with regard to any
25proposed utility facility
that is subject to this section for which a combined
1application for permits is filed under sub. (1s). In order to ensure that the
2commission's decision is consistent with the department's responsibilities, the
3department shall provide the commission with information that is relevant to only
4the following:
SB1,19
5Section
19. 30.025 (4) of the statutes is amended to read:
SB1,32,116
30.025
(4) Permit conditions. The permit may be issued, or the authority to
7proceed under a permit may be granted, upon stated conditions deemed necessary
8to assure compliance with the criteria designated under sub. (3). The department
9shall grant or deny the
combined application for
a permit permits for the utility
10facility within 30 days of the date on which the commission issues its decision under
11s. 196.49 or 196.491 (3).
SB1,20
12Section
20. 30.025 (4m) of the statutes is created to read:
SB1,32,2013
30.025
(4m) Procedure for a single permit application. A person proposing
14to construct a utility facility that is related to mining, as defined in s. 295.41 (26), and
15for which not more than one permit is required, may submit an application for that
16single permit with the department in the same manner as a combined application
17for permits may be submitted under sub. (1s). If the applicant elects to submit the
18application in the same manner as a combined application for permits, the
19procedures under this section that apply to a combined application for permits shall
20apply to that application for a single permit.
SB1,21
21Section
21. 30.12 (3m) (c) (intro.) of the statutes is amended to read:
SB1,32,2422
30.12
(3m) (c) (intro.) The department shall issue an individual permit to a
23riparian owner for a structure or a deposit pursuant to an application under par. (a)
24if the department finds that all of the following
apply requirements are met:
SB1,22
1Section
22. 30.123 (8) (c) of the statutes is renumbered 30.123 (8) (c) (intro.)
2and amended to read:
SB1,33,53
30.123
(8) (c) (intro.) The department shall issue an individual permit
4pursuant to an application under par. (a) if the department finds that
the all of the
5following requirements are met:
SB1,33,6
61. The bridge or culvert will not materially obstruct navigation
,.
SB1,33,8
72. The bridge or culvert will not materially reduce the effective flood flow
8capacity of a stream
, and.
SB1,33,9
93. The bridge or culvert will not be detrimental to the public interest.
SB1,23
10Section
23. 30.133 (2) of the statutes is amended to read:
SB1,33,1611
30.133
(2) This section does not apply to riparian land located within the
12boundary of any hydroelectric project licensed or exempted by the federal
13government, if the conveyance is authorized under any license, rule or order issued
14by the federal agency having jurisdiction over the project.
This section does not apply
15to riparian land that is associated with an approval required for bulk sampling or
16mining that is required under subch. III of ch. 295.
SB1,24
17Section
24. 30.19 (4) (c) (intro.) of the statutes is amended to read:
SB1,33,2018
30.19
(4) (c) (intro.) The department shall issue an individual permit pursuant
19to an application under par. (a) if the department finds that all of the following
apply 20requirements are met:
SB1,25
21Section
25. 30.195 (2) (c) (intro.) of the statutes is amended to read:
SB1,33,2422
30.195
(2) (c) (intro.) The department shall issue an individual permit applied
23for under this section to a riparian owner if the department determines that all of the
24following
apply requirements are met:
SB1,26
25Section
26. 31.23 (3) (e) of the statutes is created to read:
SB1,34,3
131.23
(3) (e) This subsection does not apply to a bridge that is constructed,
2maintained, or operated in association with mining or bulk sampling that is subject
3to subch. III of ch. 295.
SB1,27
4Section
27. 32.02 (12) of the statutes is amended to read:
SB1,34,85
32.02
(12) Any person operating a plant which creates waste material which,
6if released without treatment would cause stream pollution, for the location of
7treatment facilities. This subsection does not apply to a person
licensed with a
8permit under ch. 293
or subch. III of ch. 295.
SB1,28
9Section
28. 70.375 (1) (as) of the statutes is amended to read:
SB1,34,1210
70.375
(1) (as) "Mine" means an excavation in or at the earth's surface made
11to extract metalliferous minerals for which a permit has been issued under s. 293.49
12or 295.58.
SB1,29
13Section
29. 70.375 (1) (bm) of the statutes is amended to read:
SB1,34,2114
70.375
(1) (bm) "Mining-related purposes" means activities which are directly
15in response to the application for a mining permit under s. 293.37
or 295.47; directly
16in response to construction, operation, curtailment of operation or cessation of
17operation of a metalliferous mine site; or directly in response to conditions at a
18metalliferous mine site which is not in operation. "Mining-related purposes" also
19includes activities which anticipate the economic and social consequences of the
20cessation of mining. "Mining-related purposes" also includes the purposes under s.
2170.395 (2) (g).
SB1,30
22Section
30. 70.375 (4) (h) of the statutes is amended to read:
SB1,34,2423
70.375
(4) (h) The cost of premiums for bonds required under s. 293.51
, 295.45
24(5), or 295.59.
SB1,31
25Section
31. 70.38 (2) of the statutes is amended to read:
SB1,35,4
170.38
(2) Combined reporting. If the same person extracts metalliferous
2minerals from different sites in this state, the net proceeds for each site for which a
3permit has been issued under s. 293.49
or 295.58 shall be reported separately for the
4purposes of computing the amount of the tax under s. 70.375 (5).
SB1,32
5Section
32. 70.395 (1e) of the statutes is amended to read:
SB1,35,136
70.395
(1e) Distribution. Fifteen days after the collection of the tax under ss.
770.38 to 70.39, the department of administration, upon certification of the
8department of revenue, shall transfer the amount collected in respect to mines not
9in operation on November 28, 1981, to the investment and local impact fund
, except
10that the department of administration shall transfer 60 percent of the amount
11collected from each person extracting ferrous metallic minerals to the investment
12and local impact fund and 40 percent of the amount collected from any such person
13to the economic development fund.
SB1,33
14Section
33. 70.395 (2) (dc) 1. of the statutes is amended to read:
SB1,35,1915
70.395
(2) (dc) 1. Each person intending to submit an application for a mining
16permit
under s. 293.37 or 295.47 shall pay
$50,000 $75,000 to the department of
17revenue for deposit in the investment and local impact fund at the time that the
18person notifies the department of natural resources under s. 293.31 (1)
or 295.465 19of that intent.
SB1,34
20Section
34. 70.395 (2) (dc) 2. of the statutes is amended to read:
SB1,35,2321
70.395
(2) (dc) 2. A person making a payment under subd. 1. shall pay an
22additional
$50,000 $75,000 upon notification by the board that the board has
23distributed 50% of the payment under subd. 1.