2023 - 2024 LEGISLATURE
November 9, 2023 - Introduced by Senators Cowles,
Stroebel, Ballweg and Nass,
cosponsored by Representatives
Gustafson, Neylon, Tittl, Baldeh,
Dittrich, Krug, Murphy, O'Connor, Rettinger, Rozar, Spiros and Tranel.
Referred to Committee on Utilities and Technology.
SB650,1,3
1An Act to amend 196.371 (3) (b); and
to create 196.371 (3) (bs), 196.49 (5r) (d)
2and 196.491 (3) (L) of the statutes;
relating to: amending certain orders and
3certificates issued by the Public Service Commission.
Analysis by the Legislative Reference Bureau
This bill authorizes the Public Service Commission to rescind, alter, or amend
an advance order specifying the rate-making principles applicable to a public
utility's recovery of capital costs for purchasing or constructing an electric
generating facility. Under the bill, PSC may amend such an order if it determines
that market conditions related to the facility have changed and that the actual costs
of the facility have substantially decreased since the order was issued. The public
utility has at least 60 days to accept or waive acceptance of an order altered or
amended under the bill. If the public utility waives acceptance of that order, PSC
must withdraw that order and any other prior advance order specifying rate-making
principles for recovery of the facility's capital costs, and must consider the facility's
capital costs in all future rate-making proceedings as if no advance order had been
issued.
Under current law, a public utility may apply to PSC for an advance order
specifying the rate-making principles for recovery of capital costs of a facility. If the
public utility accepts the advance order, PSC is bound by that order in its treatment
of the recovery of the facility's capital costs in all future rate-making proceedings
involving the public utility. If the public utility waives acceptance of the advance
order, PSC must withdraw the order and consider the facility's capital costs in all
future rate-making proceedings as if no advance order had been issued.
The bill also requires PSC to reopen proceedings that resulted in the issuance
of a certificate of public convenience and necessity (CPCN) or a certificate of
authority (CA) for a facility or project if it determines that the actual cost of
constructing the facility or project is 5 percent or more above the construction cost
approved by PSC in issuing the CPCN or CA. PSC must hold a public hearing and
public comment period of at least 15 days on the reasons for the increase in
construction costs. If in the public interest, PSC may rescind, alter, or amend the
CPCN or CA for the facility or project. Under current law, a person seeking to
construct a large electric generating facility or high-voltage transmission line must
obtain a CPCN from PSC. In addition, a public utility must obtain a CA from PSC
to construct certain other facilities and projects.
For further information see the state fiscal estimate, which will be printed as
an appendix to this bill.
The people of the state of Wisconsin, represented in senate and assembly, do
enact as follows:
SB650,1
1Section
1. 196.371 (3) (b) of the statutes is amended to read:
SB650,2,72
196.371
(3) (b)
If Except as provided in par. (bs), if the public utility accepts the
3order, then, in all future rate-making proceedings regarding the public utility, the
4order shall be binding on the commission in its treatment of the recovery of the
5capital costs of the facility that is subject to the order and the commission may not
6consider the order or the effects of the order in its treatment of the recovery of any
7other cost of the public utility.
SB650,2
8Section
2. 196.371 (3) (bs) of the statutes is created to read:
SB650,2,139
196.371
(3) (bs) 1. The commission may at any time, upon notice to the public
10utility and after a hearing, rescind, alter, or amend an order under this section if the
11commission determines that market conditions related to the facility have
12substantially changed and the actual costs of the facility have substantially
13decreased since the time that the order was issued.
SB650,3,414
2. The commission shall specify in an altered or amended order under this
15paragraph a deadline at least 60 days after the date of issuance of the order for the
1public utility to notify the commission in writing whether the public utility accepts
2or waives acceptance of the order. If the public utility does not make the notification
3by the deadline specified in the order, the public utility is considered to have waived
4acceptance of the order.
SB650,3,105
3. Except as provided in subd. 1., if the public utility accepts the order under
6subd. 1., then, in all future rate-making proceedings regarding the public utility, the
7order shall be binding on the commission in its treatment of the recovery of the
8capital costs of the facility that is subject to the order, and the commission may not
9consider the order or the effects of the order in its treatment of the recovery of any
10other cost of the public utility.
SB650,3,1511
4. If the public utility waives or is considered to have waived acceptance of the
12order under subd. 1., the commission shall withdraw that order and any other prior
13order under this section regarding the facility and consider the capital costs of the
14facility in all future rate-making proceedings in the same manner as the commission
15considers capital costs for which no order has been issued under this section.
SB650,3
16Section
3. 196.49 (5r) (d) of the statutes is created to read:
SB650,3,2117
196.49
(5r) (d) 1. The commission shall reopen the proceeding that resulted in
18the issuance of a certificate sub. (3) or (5) if the commission determines that the
19actual cost of constructing the project, plant, equipment, property, or facility for
20which the certificate was issued is 5 percent or more above the construction cost
21approved by the commission in issuing the certificate.
SB650,3,2522
2. The commission shall hold a public hearing on the reasons for the increase
23in construction costs of the project, plant, equipment, property, or facility for a
24proceeding reopened under subd. 1. and shall hold a public comment period of at least
2515 days on the reasons for the increase in construction costs.
SB650,4,3
13. After the hearing and comment period required under subd. 2., if in the
2public interest, the commission may rescind, alter, or amend the order issuing the
3certificate under sub. (3) or (5) for the project, plant, equipment, property, or facility.
SB650,4
4Section
4. 196.491 (3) (L) of the statutes is created to read:
SB650,4,95
196.491
(3) (L) 1. The commission shall reopen the proceeding that resulted in
6the issuance of a certificate of public convenience and necessity under this subsection
7for a facility if the commission determines that the actual cost of constructing the
8facility is 5 percent or more above the cost of the constructing the facility approved
9by the commission in issuing the certificate.
SB650,4,1310
2. The commission shall hold a public hearing on the reasons for the increase
11in construction costs of the facility for a proceeding reopened under subd. 1 and shall
12hold a public comment period of at least 15 days on the reasons for the increase in
13construction costs of the facility.
SB650,4,1614
3. After the hearing and comment period required under subd. 2., if in the
15public interest, the commission may rescind, alter, or amend the order issuing the
16certificate of public convenience and necessity under this subsection for the facility.