30.20(2)(a)(a) The department, whenever consistent with public rights, may enter into contracts on behalf of the state for the removal of any material from the bed of any navigable lake or any of the outlying waters, and for the lease or sale of the material. Every contract shall contain such conditions as may be necessary for the protection of the public interest and the interests of the state and shall fix the compensation to be paid to the state for material so removed, except that no compensation may be paid for the material if the contract is with a municipality as defined in
s. 281.01 (6) and the material is to be used for a municipal purpose and not for resale. No contract entered into under this paragraph may run for a longer period than 5 years.
30.20(2)(b)
(b) The department, whenever consistent with public rights, may enter into contracts on behalf of the state for the removal of any mineral, ore and material from beneath the bed of navigable lakes and waters, where the waters would not be disturbed in the removal operation and for the lease and sale of such mineral, material and ore and provide the necessary regulations for all acts incident thereto. Every such contract shall contain such conditions as may be necessary for the protection of the public interest and the interests of the state, and shall fix the compensation to be paid to the state for the material, mineral and ore so removed. No contract entered into, pursuant to this paragraph, shall run for a longer period than 75 years. Should any doubt exist as to whether the state, in fact, owns such lake bed or stream bed such contract or lease shall be for such interests, if any, as the state may own. Title to the royalties to be paid when mining operations are begun shall be determined at such future time as royalties for ores so sold are paid or are due and payable.
30.20(2)(c)
(c) A permit to remove material from the bed of any lake or stream not included in
sub. (1) (a) may be issued by the department if it finds that the issuance of such a permit will be consistent with the public interest in the water involved. A permit or contract issued under this paragraph may be issued for up to 10 years if the applicant notifies the department at least 30 days before removing any material.
30.20 Cross-reference
Cross Reference: See also chs.
NR 305,
320,
346, and
347, Wis. adm. code.
30.20 Annotation
Before proceeding to remove an obstruction under s. 88.90 (3), one must obtain a permit under s. 30.20. State v. Dwyer,
91 Wis. 2d 440,
283 N.W.2d 448 (Ct. App. 1979).
30.20 Annotation
When a bulkhead line has been established, a riparian owner must nonetheless obtain a permit or contract pursuant to 30.20 prior to removing material from the bed of a navigable water landward of the bulkhead line, but within the original ordinary high water mark. 63 Atty. Gen. 445.
30.202
30.202
Dredge disposal in and near the Mississippi, St. Croix and Black rivers by the U.S. corps of engineers. 30.202(1)(1)
Memorandum of understanding. The department may enter into a memorandum of understanding with the U.S. corps of engineers concerning the dredging of the Mississippi, St. Croix and Black rivers and the disposal of these dredge spoils. Any memorandum of understanding shall specify approved sites where dredge spoils may be deposited and shall specify conditions and standards which are required for use of an approved site. A memorandum of understanding may contain recommended or required dredge disposal methods, equipment and policies.
30.202(2)
(2) Authorization for dredging and dredge spoil disposal. If the department enters into a memorandum of understanding with the U.S. corps of engineers under
sub. (1), the U.S. corps of engineers may deposit dredge spoils from dredging the Mississippi, St. Croix and Black rivers at approved sites according to specified conditions and standards including any special conditions and standards established under
sub. (4).
30.202(3)
(3) Exemption from statutes and rules. Dredge spoil disposal activities authorized under
sub. (2) are exempt from any prohibition, restriction, requirement, permit, license, approval, authorization, fee, notice, hearing, procedure or penalty specified under
s. 29.601,
30.01 to
30.20,
30.21 to
30.99,
59.692 or
87.30 or
chs. 281 to
285 or
289 to
299, except
s. 281.48, or specified in any rule promulgated, order issued or ordinance adopted under those sections or chapters.
30.202(4)
(4) Hazardous waste dredge spoil disposal. In consultation with the U.S. corps of engineers, the department shall establish special conditions and standards for the disposal of dredge spoils which are hazardous waste, as defined under
s. 291.01 (7). These special conditions and standards shall be established to ensure that public health and the environment are protected.
30.2025
30.2025
Lake Koshkonong comprehensive project. 30.2025(1)(1)
Definition. In this section, "district" means the Rock-Koshkonong public inland lake protection and rehabilitation district.
30.2025(2)
(2) Authorization. The district may implement a project developed and approved by the U.S. army corps of engineers to place structures, or fill, or both on the bed of Lake Koshkonong for any of the following purposes:
30.2025(2)(a)
(a) To improve navigation or to provide navigation aids.
30.2025(2)(b)
(b) To restore or protect wetland habitat or water quality.
30.2025(2)(c)
(c) To create, restore, or protect fish and wildlife habitat.
30.2025(2)(d)
(d) To enhance the natural aesthetic value or improve the recreational use of the lake.
30.2025(3)
(3) Location of structures and fill. Any structure or fill placed as part of the project authorized under
sub. (2) shall be located in Lake Koshkonong within the area that consists of Secs. 10, 13, 18, 19, 20, 24, 33, and 35, T 5 N., R 13.
30.2025(4)(a)(a) Before beginning any activity involving the placement of a structure or fill as part of the project authorized under
sub. (2), the district shall submit plans and specifications for the project to the department and obtain the department's approval for the project.
30.2025(4)(b)
(b) Before the department gives its approval for a project authorized under
sub. (2), the department shall do all of the following:
30.2025(4)(b)2.
2. Review the plans and specifications submitted to the department under
par. (a) and obtain any other information that it determines is necessary to effectively evaluate the structural and functional integrity of the structure or fill.
30.2025(4)(b)3.
3. Hold a public informational meeting to discuss the plans and specifications submitted under
par. (a).
30.2025(4)(b)4.
4. Determine that the structure or fill is structurally and functionally sound and that the structure or fill will comply with the requirements under
sub. (5).
30.2025(5)
(5) Requirements for structures and fill. A structure or fill placed as part of a project authorized under
sub. (2) shall meet all of the following requirements:
30.2025(5)(a)
(a) It may not materially affect the flood flow capacity of the Rock River.
30.2025(5)(c)
(c) It may not cause material injury to the rights of an owner of lands underlying the structure or fill or to the rights of a riparian owner who owns lands affected by the project.
30.2025(5)(e)
(e) It may not be detrimental to the public interest.
30.2025(6)(a)(a) The district shall maintain the structures and the fill that are part of the project authorized under
sub. (2) to ensure that the structures and fill do not impair the safety of the public.
30.2025(6)(b)
(b) The district shall maintain the structures and the fill that are part of the project authorized under
sub. (2) so that the structures and fill remain in compliance with the requirements listed under
sub. (5).
30.2025(6)(c)
(c) If the department determines that any structure or any fill that is part of the project authorized under
sub. (2) does not comply with the requirements under
sub. (5), the department may require the district to modify the structure or fill to bring it into compliance or to remove the structure or fill.
30.2025(7)
(7) Use of structures or fill. Any structure or fill placed as part of the project authorized under
sub. (2) may be used only for any of the following:
30.2025(7)(a)
(a) As a site for the placement of navigation aids approved by the department.
30.2025(7)(b)
(b) Activities to protect or improve wildlife or fish habitat, including the placement of fish or wildlife habitat structures approved by the department.
30.2025(8)(a)(a) The structures or fill that are part of the project authorized under
sub. (2) are owned by the district. Except as provided in
par. (b), the district may not transfer ownership of any structure or any fill that is part of the project authorized under
sub. (2).
30.2025(8)(b)
(b) The district may transfer ownership of any structure or fill that is part of the project authorized under
sub. (2) if all of the following apply:
30.2025(8)(b)1.
1. The district transfers ownership of the structure or fill to a public entity, as defined by the department by rule.
30.2025(8)(b)2.
2. Before transferring ownership of the structure or fill, the district obtains written approval of the transfer from the department.
30.2025(9)
(9) Access to property. An employee or agent of the department shall have free access during reasonable hours to the structures or fill that are part of the project authorized under
sub. (2) for the purpose of inspecting the structures or fill to ensure that the project is in compliance with the requirements of this section. If the department determines that any structure or any fill that is part of the project authorized under
sub. (2) does not comply with the requirements of this section, the department may require the owner of the structure or fill to modify the structure or fill to bring it into compliance or to remove the structure or fill.
30.2025(10)
(10) Exemptions. Section 30.12 does not apply to activities that are necessary for the implementation or maintenance of the project authorized under
sub. (2).
30.2025 History
History: 2001 a. 16.
30.2026
30.2026
Lake Belle View and Sugar River project. 30.2026(1)(a)(a) Subject to the restrictions under
sub. (2), the village of Belleville may place fill on all or part of the portion of the bed of Lake Belle View located in Dane County for any of the following purposes:
30.2026(1)(a)3.
3. Improving the water quality of Lake Belle View and the Sugar River.
30.2026(1)(a)4.
4. Enhancing the recreational use and aesthetic enjoyment of Lake Belle View and the Sugar River.
30.2026(1)(a)5.
5. Separating Lake Belle View from the Sugar River by creating an artificial barrier from lake bottom sediments or by other means.
30.2026(1)(a)6.
6. Creating suitable lake bottom depths or contours in Lake Belle View.
30.2026(1)(b)
(b) Any lake bottom sediments that are unsuitable for the creation of an artificial barrier under
par. (a) 5. may be placed in any agricultural field that is adjacent to Lake Belle View.
30.2026(1)(c)
(c) If the village of Belleville creates an artificial barrier from lake bottom sediments under
par. (a) 5., the village of Belleville shall also place lake bottom sediments in adjacent areas for the purpose of creating and enhancing wetlands.
30.2026(2)(a)(a) The village of Belleville shall obtain approval from the department for any placement of fill material as authorized under
sub. (1).
30.2026(2)(b)
(b) The village of Belleville shall submit to the department any plans or other information that the department considers necessary for it to effectively determine whether to grant approval under
par. (a).
30.2026(2)(c)
(c) The village of Belleville shall ensure that all of the following apply to any artificial barrier created as authorized under
sub. (1).
30.2026(2)(c)1.
1. The barrier does not materially obstruct navigation or reduce the effective flood flow capacity of a stream.
30.2026(2)(c)3.
3. The barrier is owned by a public entity and the public is granted free access to the barrier.
30.2026(2)(c)4.
4. Access by the public to the barrier is limited to use as open space for recreational purposes.
30.2026(2)(c)5.
5. The barrier remains in as natural a condition as is practicable, as determined by the department.
30.2026(2)(c)6.
6. No structure, except those necessary in order to effectuate a purpose specified in
sub. (1) (a), are placed on the barrier.
30.2026(2)(d)
(d) The village of Belleville shall create any artificial barrier under this section in compliance with all state laws that relate to navigable bodies of water, except
s. 30.12 (1) and
(2).
30.2026(3)(a)(a) The village of Belleville shall maintain any artificial barrier created as authorized under
sub. (1). If a landowner of more than 500 feet of Lake Belle View shoreline, a portion of which is located within 1,000 feet of any such artificial barrier, is dissatisfied with the manner in which the village of Belleville is maintaining the barrier, the owner may maintain the barrier in lieu of the village, upon approval of the department. The village or a landowner who maintains the barrier shall comply with all state laws that relate to navigable bodies of water, except
s. 30.12 (1) and
(2). The department may require the village of Belleville or the landowner to maintain the barrier in a structurally and functionally adequate condition.
30.2026(3)(b)
(b) The village of Belleville shall ensure that any construction draw down of Lake Belle View related to the creation of any artificial barrier authorized under
sub. (1) occurs only once.
30.2026(4)
(4) Costs. Any costs incurred by the state to construct, maintain, improve, or remove any artificial barrier created as authorized under
sub. (1) shall be paid by the village of Belleville or its successors or assigns.
30.2026(5)
(5) Immunity. The state and its officers, employees, and agents are immune from liability for acts or omissions that cause damage or injury and that relate to the construction, maintenance, or use of any artificial barrier created as authorized under
sub. (1).
30.2026 History
History: 2001 a. 16.
30.203
30.203
Lake Winnebago comprehensive project. 30.203(1)(1)
Authorization. The department may implement a project to place structures or fill or both on the beds of lakes Winnebago, Butte des Morts, Winneconne and Poygan for any of the following purposes:
30.203(1)(a)
(a) To improve navigation or to provide navigation aids.
30.203(1)(b)
(b) To restore or protect wetland habitat or water quality.
30.203(1)(c)
(c) To create, restore or protect fish and wildlife habitat.
30.203(1)(d)
(d) To enhance the natural aesthetic value or improve the recreational use of these lakes.
30.203(2)
(2) Location of structures and fill. Any structure or fill placed as part of the project authorized under
sub. (1) shall be located in Winnebago County as follows:
30.203(2)(a)
(a) In Lake Winnebago within the area that consists of the S-1/2 of Sec. 14, T. 17 N., R. 17 E., and the N-1/2 of Sec. 23, T. 17 N., R. 17 E.