30.208(4)(b)
(b) If a public hearing is held, the period for public comment shall end on the 10th day following the date on which the public hearing is completed.
30.208(4)(d)
(d) The department shall promulgate rules to establish procedures for the conduct of public hearings held under this subsection. Notwithstanding
s. 227.42, a public hearing held under this subsection shall be an informational hearing and may not be treated as, nor converted to, a contested case under
s. 227.01 (3).
30.208(5)(a)(a) The department shall, by rule, establish procedures for providing notices of complete applications and notices of public hearings to be provided under
sub. (3), and notices of administrative hearings to be provided under
s. 30.209 (1m). The procedures shall require all of the following:
30.208(5)(a)2.
2. That the notice be mailed to any person or group upon request.
30.208(5)(b)
(b) The department shall, by rule, prescribe the form and content of notices of complete applications and notices of public hearings to be provided under
sub. (3), and notices of administrative hearings to be provided under
s. 30.209 (1m). Each notice shall include all of the following information:
30.208(5)(b)1.
1. The name and address of each applicant or permit holder.
30.208(5)(b)2.
2. A brief description of each applicant's activity or project that requires the permit.
30.208(5)(b)3.
3. The name of the waterway in or for which the activity or project is planned.
30.208(5)(b)4.
4. For a notice of complete application and a notice of public hearing under
sub. (3), a statement of the tentative determination to issue, modify, or deny a permit for the activity or project described in the application.
30.208(5)(b)5.
5. For a notice of complete application and a notice of public hearing under
sub. (3), a brief description of the procedures for the formulation of final determinations, including a description of the comment period required under
sub. (4).
30.208(5)(c)
(c) The department may delegate the department's requirement to provide notice under
sub. (3) or
s. 30.209 (1m) by doing any of the following:
30.208(5)(c)1.
1. Requiring that the applicant for the permit or contract provide by publication, mailing, or other distribution one or more of the notices.
30.208(5)(c)2.
2. That the applicant for the permit or contract pay for the publication, mailing, or any other distribution costs of providing one or more of the notices.
30.208 History
History: 2003 a. 118 ss.
6,
149.
30.209
30.209
Contracts and individual permits; administrative and judicial review. 30.209(1)
(1)
Definition. In this section, "applicant" means any person applying to receive a permit or contract under this subchapter or any person who has received a permit or contract under this subchapter.
30.209(1m)
(1m) Request for administrative review. 30.209(1m)(a)(a) Any interested person may file a petition with the department for administrative review within 30 days after any of the following decisions given by the department:
30.209(1m)(a)1.
1. The issuance, denial, or modification of any individual permit issued or contract entered into under this subchapter.
30.209(1m)(a)2.
2. The imposition of, or failure to impose, a term or condition on any individual permit issued or contract entered into under this subchapter.
30.209(1m)(b)
(b) If the petitioner is not the applicant, the petition shall describe the petitioner's objection to the permit or contract and shall contain all of the following:
30.209(1m)(b)1.
1. A description of the objection that is sufficiently specific to allow the department to determine which provisions of this subchapter may be violated if the proposed activity or project under the permit or contract is allowed to proceed.
30.209(1m)(b)2.
2. A description of the facts supporting the petition that is sufficiently specific to determine how the petitioner believes the activity or project, as proposed, may result in a violation of the provisions of this subchapter.
30.209(1m)(b)3.
3. A commitment by the petitioner to appear at the administrative hearing and present information supporting the petitioner's objection.
30.209(1m)(c)
(c) The activity or project shall be stayed pending an administrative hearing under this section, if the petition contains a request for the stay showing that a stay is necessary to prevent significant adverse impacts or irreversible harm to the environment.
30.209(1m)(d)
(d) If a stay is requested under
par. (c), the stay shall be in effect until either the department denies the request for an administrative hearing or the hearing examiner determines that the stay is not necessary.
30.209(1m)(e)
(e) The petitioner shall file a copy of the petition with the department. If the petitioner is not the applicant, the petitioner shall simultaneously provide a copy of the petition to the applicant. The applicant may file a response to the petition with the department. If the applicant files a response under this paragraph, it shall be filed within 15 days after the petition is filed.
30.209(1m)(f)
(f) The department shall grant or deny the petition within 30 days after the petition is filed. The failure of the department to dispose of the petition within this 30-day period is a denial. The department shall deny the petition if any of the following applies:
30.209(1m)(f)1.
1. The petitioner is not the applicant and the petition does not comply with the requirements of
par. (b).
30.209(1m)(f)2.
2. The objection contained in the petition is not substantive. The department shall determine that an objection is substantive if the supporting facts contained in the objection appear to be substantially true and raise reasonable grounds to believe that the provisions of this subchapter may be violated if the activity or project is undertaken.
30.209(1m)(fm)
(fm) If the department denies the petition, the department shall send the petitioner the denial in writing, stating the reasons for the denial.
30.209(1m)(g)
(g) If the department grants a petition under this subsection, the department shall refer the matter to the division of hearings and appeals in the department of administration within 15 days after granting the petition unless the petitioner and the applicant agree to an extension.
30.209(2)(a)(a) An administrative hearing under this subsection shall be treated as a contested case under
ch. 227.
30.209(2)(b)
(b) If a stay under
sub. (1m) (c) is in effect, the hearing examiner shall, within 30 days after receipt of the referral under
sub. (1m) (g), determine whether continuation of the stay is necessary to prevent significant adverse impacts or irreversible harm to the environment pending completion of the hearing. The hearing examiner shall make the determination based on the request under
sub. (1m) (c), any response from the applicant under
sub. (1m) (e), and any testimony at a public hearing or any public comments. The determination shall be made without a hearing.
30.209(2)(c)
(c) A hearing under this section shall be completed within 90 days after receipt of the referral of the petition under
sub. (1m) (g), unless all parties agree to an extension of that period. In addition, a hearing examiner may grant a one-time extension for the completion of the hearing of up to 60 days on the motion of any party and a showing of good cause demonstrating extraordinary circumstances justifying an extension.
30.209(2)(d)
(d) Notwithstanding
s. 227.44 (1), the department shall provide a notice of the hearing at least 30 days before the date of the hearing to all of the following:
30.209(3)(a)(a) Any person whose substantial interest is affected by a decision of the department under
sub. (1m) (a) 1. or
2. may commence an action in circuit court to review that decision.
30.209(3)(b)
(b) Any party aggrieved by a decision of a hearing examiner under
sub. (2) may commence an action in circuit court to review that decision.
30.209 History
History: 2003 a. 118,
326,
327.
30.2095
30.2095
Limits and conditions for permits and contracts. 30.2095(1)(a)(a) Except as provided in
par. (b), every permit or contract issued under
ss. 30.01 to
30.29 for which a time limit is not provided by
s. 30.20 (2) is void unless the activity or project is completed within 3 years after the permit or contract was issued.
30.2095(1)(b)
(b) The department may specify a time limit of less than 3 years for a permit or contract issued under
ss. 30.01 to
30.29. For good cause, the department may extend the time limit for a permit or contract issued under
ss. 30.01 to
30.29 for no longer than 2 years if the grantee requests an extension prior to expiration of the initial time limit.
30.2095(2)
(2) For good cause, the department may modify or rescind any permit or contract issued under
ss. 30.01 to
30.29 before its expiration.
30.2095 History
History: 1987 a. 374;
2003 a. 118 s.
15; Stats. 2003 s. 30.2095.
30.21
30.21
Use of beds of Great Lakes by public utilities. 30.21(1)(1)
Water intake facilities. Upon compliance with such applicable regulations as may be imposed by the government of the United States and subject to
chs. 196 and
197 and rules and orders of the public service commission issued pursuant thereto, any public utility may, pursuant to permit granted by resolution of the governing body of any city, village or town situated on any waters of Lake Michigan or Lake Superior or in the Great Lakes basin, construct, maintain and operate, upon and under the bed thereof adjoining such city, village or town, all cribs, intakes, basins, pipes and tunnels necessary or convenient for securing an adequate supply of water suitable for the purposes of such utility, provided only, that concurrently with the construction of facilities for the withdrawal of water from the lakes, the city, town or village must construct sewage treatment and disposal works adequate to treat completely all sewage of the municipality. Any city, village or town, the limits of which are within 50 miles of any such waters and any public utility serving the same shall be deemed to be situated on such waters within the meaning of this section and such municipality or public utility serving the same shall, subject to this section, have authority to acquire and own or lease sufficient real estate, not to exceed 50 miles beyond the corporate limits of such municipality, for the purpose of constructing, maintaining and operating thereon or thereunder, transmission facilities and structures, including cribs, intakes, basins, pipes and tunnels, necessary or convenient for securing an adequate supply of water suitable for the purposes of such municipality or utility. Such facilities shall be so constructed, maintained and operated as to avoid material obstruction to existing navigation or the use of private property not owned by such utility.
30.21(2)
(2) Harbor facilities; public utility structures. Pursuant to the authority and conditions specified in
sub. (1), any such utility may also:
30.21(2)(a)
(a) Improve the navigability of any of the waters specified in
sub. (1) and construct upon the shore and the adjoining bed of such waters, harbor facilities adapted for the reception, docking, unloading and loading of vessels carrying supplies required for the operation of such utility.
30.21(2)(b)
(b) Place any public utility structure, including all or part of any plant for the generation of electricity and the appurtenances, upon the bed of any of the waters specified in
sub. (1), provided the utility first obtains approval under this chapter and obtains the approval of the public service commission as required by
s. 196.49 or rules or orders of the public service commission issued pursuant thereto, and also obtains the approval of the department to the making of any payment to be made to the municipality with respect to the erection of such structure.
30.21(3)
(3) Compliance with other permit requirements. 30.21(3)(a)(a) Each public utility operating under a permit under this section on January 1, 1986, shall comply with
s. 281.35 (2), if applicable.
30.21(3)(b)
(b) On and after January 1, 1986, no city, village or town may issue a permit under
sub. (1) unless the public utility applying for the permit complies with
s. 30.18 (2) (b), if applicable.
30.21 History
History: 1985 a. 60;
1995 a. 227.
30.24
30.24
Bluff protection. 30.24(1)(1)
Definitions. In this section:
30.24(2)
(2) Authorization. For the purposes of protecting bluff land, the department may expend money from the appropriation under
s. 20.866 (2) (ta) for a program under which the department may do all of the following:
30.24(2)(a)
(a) Acquire bluff land or interests in bluff land along the Great Lakes.
30.24(2)(b)
(b) Award grants to nonprofit conservation organizations to acquire these lands or interests under
s. 23.096.
30.24(3)
(3) Ban on location restrictions. In exercising its authority under
sub. (2) (a), the department may not limit acquisitions of bluff lands to bluff lands that are within the boundaries of projects established by the department.
30.24(4)
(4) Limit on grants. A grant awarded under this section or under
s. 23.096 to protect bluffs may not exceed 50% of the acquisition costs.
30.24(5)
(5) Rules. The department shall promulgate rules to administer and implement this section, including standards for awarding grants to protect bluffs under this section and under
s. 23.096 grants. The department by rule shall define "bluff land" for purposes of this section.
30.24 History
History: 1999 a. 9.
30.25
30.25
Wolf River protection. 30.25(1)
(1) Except as provided under
sub. (2), no person may make any effort to improve the navigation on the Wolf River north of the southern boundary of Shawano County nor shall any dam be authorized for construction in that portion of the Wolf River. Any permit issued or in effect by virtue of or under authority of any order or law authorizing the construction of any dam in the Wolf River in Langlade County is void. This declaration does not affect permits for or the operation or maintenance of any dam in existence on August 24, 1963.
30.25(2)
(2) A person may engage in a minor dredging project to improve access to or to improve the aesthetics of the Wolf River in Shawano County if a permit issued by the department under
s. 30.20 authorizes the project.
30.25 History
History: 1987 a. 374.
30.26(1)(1)
Legislative intent. In order to afford the people of this state an opportunity to enjoy natural streams, to attract out-of-state visitors and assure the well-being of our tourist industry, it is in the interest of this state to preserve some rivers in a free flowing condition and to protect them from development; and for this purpose a system of wild rivers is established, but no river shall be designated as wild without legislative act.
30.26(2)
(2) Designation. The Pike River in Marinette County, and the Pine River and its tributary Popple River in Florence and Forest counties are designated as wild rivers and shall receive special management to assure their preservation, protection and enhancement of their natural beauty, unique recreational and other inherent values in accordance with guidelines outlined in this section.
30.26(3)
(3) Duties of department. The department in connection with wild rivers shall:
30.26(3)(a)
(a) Provide active leadership in the development of a practical management policy.
30.26(3)(b)
(b) Consult other state agencies and planning committees.
30.26(3)(c)
(c) Collaborate with county and town boards and local development committees or boards in producing a mutually acceptable program for the preservation, protection and enhancement of the rivers.
30.26(3)(e)
(e) Seek the cooperation of the U.S. forest service, timber companies, county foresters and private landowners in implementing land use practices to accomplish the objectives of the management policy.
30.26(3)(f)
(f) Act as coordinator under this subsection.
30.26(4)(a)(a) The department may not prohibit the crossing of a bridge over a wild river by an all-terrain vehicle traveling on an all-terrain vehicle trail, as defined under
s. 23.33 (1) (d), or by a snowmobile traveling on a snowmobile trail, as defined under
s. 350.01 (17) that is constructed in any of the following locations:
30.26(4)(a)1.
1. Along the Nicolet State Trail where the trail crosses the existing railroad trestle over the Pine River and the Popple River.