293.495293.495 Subsequently filed applications for other approvals. 293.495(1)(a)1.1. For purposes of this subsection, an application for an approval other than a mining or prospecting permit is considered to be complete on the 30th day after the department receives the application unless, before that day, the department requests additional information, in which case the application is considered to be complete when the applicant provides the information. 293.495(1)(a)2.2. For purposes of this subsection, an application for a mining or prospecting permit is considered to be complete on the 30th day after the department receives the application unless the department requests additional information under s. 293.40 (2) or (3), in which case the application is considered to be complete when the applicant provides the information. 293.495(1)(b)(b) Except as provided in par. (d), if an applicant files an application for an approval other than a mining or prospecting permit no later than 60 days after the day on which the application for the mining or prospecting permit is complete under par. (a) 2., or more than 60 days after that day but in time to allow the application to be considered at the public informational hearing for the mining or prospecting permit under s. 293.43 (3m), the department shall approve the application and issue the approval, or deny the application, no later than the deadline under s. 293.45 (1) or (2) or 293.49 (1) or (2). 293.495(1)(c)1.1. Except as provided in subd. 2., if an applicant files an application for an approval other than a mining or prospecting permit too late to allow the application to be considered at the public informational hearing for the mining or prospecting permit under s. 293.43 (3m) but before the department issues the decision to grant or deny the application for the mining or prospecting permit, the department shall approve the application and issue the approval, or deny the application, after the separate public informational hearing for the approval required under s. 293.43 (3m) and no later than 75 days after the application for the approval is complete under par. (a) 1. 293.495(1)(c)2.2. Except as provided in par. (d), the department shall approve or deny the application for an approval described in subd. 1. that is an individual permit for which federal law requires the opportunity for public comment or the ability to request a public hearing prior to issuance of the approval after the separate public informational hearing required for the approval under s. 293.43 (3m) and no later than 180 days after the application is complete under par. (a) 1. 293.495(1)(d)(d) The deadlines in pars. (b) and (c) do not apply to an application for an air pollution control permit under s. 285.62 for which the department receives an objection from the federal environmental protection agency under s. 285.62 (6). 293.495(1)(e)(e) The department shall incorporate any approval other than a mining or prospecting permit into a single document with the mining or prospecting permit, unless the application for the approval was filed more than 60 days after the day on which the application for the mining or prospecting permit is complete under par. (a) 2. 293.495(2)(2) The provisions of this chapter concerning public notice, comment, and hearing; issuance of department decisions; effective date of department decisions; review of department decisions; and the duration of approvals apply to any approval, regardless of whether the application is filed before or after the department issues the decision to grant or deny the application for the mining or prospecting permit, notwithstanding any provisions related to those matters in s. 44.40 or 169.25, subch. I or VI of ch. 77, ch. 23, 29, 30, 31, 169, 281, 283, 285, 289, or 291, or rules promulgated under those provisions, except as provided in s. 281.343 (7r) and except that if a withdrawal of surface water or groundwater is subject to regional review or council approval under s. 281.346, the applicable provisions related to regional review or council approval apply. 293.495 HistoryHistory: 2017 a. 134. 293.51293.51 Bonds and other security. 293.51(1)(1) Upon notification that an application for a prospecting or mining permit has been approved by the department but prior to commencing prospecting or mining, the operator shall file with the department a bond conditioned on faithful performance of all of the requirements of this chapter and all rules adopted by the department under this chapter. The bond shall be furnished by a surety company licensed to do business in this state. In lieu of a bond, the operator may deposit cash, certificates of deposit or government securities with the department. Interest received on certificates of deposit and government securities shall be paid to the operator. The amount of the bond or other security required shall be equal to the estimated cost to the state of fulfilling the reclamation plan, in relation to that portion of the site that will be disturbed by the end of the following year. The estimated cost of reclamation of each prospecting or mining site shall be determined by the department on the basis of relevant factors including, but not limited to, expected changes in the price index, topography of the site, methods being employed, depth and composition of overburden and depth of nonferrous metallic mineral deposit being mined. 293.51(1g)(1g) An operator shall maintain proof of financial responsibility ensuring the availability of funds for compliance with the long-term care requirements specified in the waste site feasibility study and plan of operation consistent with the requirements under s. 289.41 except that, notwithstanding s. 289.41 (3), the operator shall furnish the proof of financial responsibility in the form of a bond, cash, certificates of deposit, government securities, or insurance. 293.51(1m)(1m) Upon notification that an application for a mining permit has been approved by the department but prior to commencing mining, the operator shall file with the department a bond issued by a surety company licensed to do business in this state, cash, certificates of deposit, or government security, to cover unforeseen remedial contingencies not otherwise covered by the bonds or other security required under sub. (1) or (1g), including for the provision of a replacement water supply if required under s. 293.65 (4) (d). The amount of the bond or other security required shall be 10 percent of the total amount of the bonds or other security required under subs. (1) and (1g). The operator shall increase, and may decrease, the amount of the bond under this subsection according to any increase or decrease in the amount of the bonds or other security required under subs. (1) or (1g) until the operator ceases to extract material from the mining site, at which point the amount of the bond under this subsection shall remain the same until released by the department. The bond or other security under this subsection shall be released no later than 40 years after the operator ceases to extract material from the mining site. 293.51(1r)(1r) At the time of closure of the mining waste site, the operator shall provide proof of financial responsibility to the department in an amount equal to the reasonably anticipated costs during the period between 40 and 250 years after closure of the mining waste site to repair or replace any engineered cover systems or tailings water management control systems used at the mining site or mining waste site to avoid adverse environmental consequences. At the time that the application for a mining permit is approved, the department shall determine the amount to be paid at the time of closure based on the net present value discounted at a rate of at least 5 percent per year, and identify the reasonably anticipated costs that the amount is intended to cover. The operator shall provide the proof of financial responsibility in the form of a cash deposit, which the department shall segregate and invest in an interest-bearing account; certificates of deposit, government securities, or other interest-bearing forms of security; or proof of establishment of an interest-bearing account, including an escrow account or trust account. The operator or any successor in interest may use the funds or request the department release the funds to cover any reasonably anticipated costs that were identified by the department. The department shall release any remaining funds to the operator or the operator’s successor in interest after all of the reasonably anticipated costs that were identified by the department have been incurred, or upon determining that the reasonably anticipated costs are no longer applicable. 293.51(2)(2) The applicant shall submit a certificate of insurance certifying that the applicant has in force a liability insurance policy issued by an insurer authorized to do business in this state, or in lieu of a certificate of insurance evidence that the applicant has satisfied state or federal self-insurance requirements, covering all mining operations of the applicant in this state and affording personal injury and property damage protection in a total amount deemed adequate by the department but not less than $50,000. 293.51(3)(3) Upon approval of the operator’s bond or other security under subs. (1), (1g), (1m), and (1r), mining application, and certificate of insurance, the department shall issue written authorization to commence mining at the permitted mining site in accordance with the approved mining and reclamation plans. 293.51(4)(4) Any operator who obtains mining permits from the department for 2 or more mining sites may elect, at the time the 2nd or any subsequent site is approved, to post a single bond in lieu of separate bonds on each site. Any single bond so posted shall be in an amount equal to the estimated cost to the state determined under sub. (1) of reclaiming all sites the operator has under mining permits. When an operator elects to post a single bond in lieu of separate bonds previously posted on individual sites, the separate bonds may not be released until the new bond has been accepted by the department. 293.51(5)(5) The department may not require an operator to provide a type or form of financial assurance other than those specified in this section. 293.51(6)(6) Any person who is engaged in mining on July 3, 1974 need not file a bond or deposit cash, certificates of deposits or government securities with the department under this section to obtain the written authorization to commence mining under sub. (3). 293.53293.53 Review of permits; periodic reports. 293.53(1)(a)(a) Eighteen months after the issuance of a prospecting permit, and annually thereafter until prospecting ceases, the department shall review the permit, reclamation plan and bond to ascertain adequacy, compliance with state or federal laws enacted after the issuance of the permit and technological currency. If the department after review determines that the plan should be modified or the bond amount changed, it shall notify the permit holder of the necessary modifications or changes. If the permit holder does not request a hearing within 30 days, the modifications or changes shall be deemed accepted. 293.53(1)(b)(b) If the permit holder desires to modify the permit, an amended application shall be submitted to the department, which shall process the amendment as if it were an original application if the proposed modification substantially broadens or changes the scope of the original prospecting proposal. 293.53(1)(c)(c) To the extent that testimony and evidence submitted at the original prospecting permit proceedings or from previous modification hearings is relevant to the issues of modification or granting or denial of the amendment, it may be adopted in the subsequent proceedings, subject to the opportunity for cross-examination and rebuttal, if not unduly repetitious.