SB1-ASA1,14,146 (n) The department shall accept written comments on the adequacy of the final
7environmental impact statement for at least 10 days after the day on which the notice
8under par. (m) is published. The department shall make the determination of
9adequacy of the final environmental impact statement at least 10 days after
10publication of the notice of availability of the final environmental impact statement.
11The department shall make the determination of adequacy of the final
12environmental impact statement within 280 days after publication of the notice
13under par. (j) unless the time is extended by consent of the person submitting the
14environmental impact report or by the governor for good cause.
SB1-ASA1,15,415 (o) If the department determines that the environmental impact statement is
16inadequate, the department shall prepare an adequate environmental impact
17statement within 60 days of that determination. When the adequate environmental
18impact statement is complete, the department shall publish a class 1 notice, under
19ch. 985, of completion of the environmental impact statement in at least one
20newspaper of general circulation in each county where the project will occur and in
21the official state newspaper. The department shall also distribute a summary of the
22adequate environmental impact statement to the person who submitted the
23environmental impact report, the U.S. army corps of engineers, the federal
24environmental protection agency, the U.S. fish and wildlife service, the state
25historical society, any federally recognized American Indian tribe or band that may

1be affected by the proposed project, any local governmental unit in which the project
2will take place, any person that submitted substantive comments within the
3comment period on the previous version of the environmental impact statement, and
4any person requesting the summary.
SB1-ASA1,15,7 5(5) (a) The department may not issue a mining permit or any other approval
6required in connection with a nonsulfide ferrous mining project before it determines
7that the environmental impact statement for the project is adequate.
SB1-ASA1,15,128 (b) Within 90 days after the determination of adequacy of a final environmental
9impact statement, the department shall make final decisions on those approvals that
10were identified as required in the scoping process and for which information was
11developed concurrently with the preparation of the environmental impact
12statement, except as follows:
SB1-ASA1,15,1413 1. The department may extend the 90-day period with the consent of the
14applicant.
SB1-ASA1,15,1615 2. The 90-day period does not apply if a longer period is required for an
16approval by federal law or state statute.
SB1-ASA1,13 17Section 13. 293.49 (1) (a) 3. of the statutes is amended to read:
SB1-ASA1,15,2518 293.49 (1) (a) 3. In the case of a surface mine, the site is not unsuitable for
19mining. The preliminary determination that a site was not unsuitable for mining
20under s. 293.45 may not be conclusive in the determination of the site's suitability
21for mining under this section. However, for mining other than nonsulfide ferrous
22mining,
at the hearing held under this section and s. 293.43, testimony and evidence
23submitted at the prospecting permit proceeding relevant to the issue of suitability
24of the proposed mining site for surface mining may be adopted, subject to the
25opportunity for cross-examination and rebuttal, if not unduly repetitious.
SB1-ASA1,14
1Section 14. 293.495 of the statutes is created to read:
SB1-ASA1,16,4 2293.495 Process for nonsulfide ferrous mining. (1) Applicability of
3other provisions.
The following provisions do not apply to proposed nonsulfide
4ferrous mining projects:
SB1-ASA1,16,55 (a) Section 293.31.
SB1-ASA1,16,66 (b) Section 293.37 (2) (d).
SB1-ASA1,16,77 (c) Section 293.43.
SB1-ASA1,16,88 (d) The time limit in s. 293.49 (1) (a) (intro.) and (2) (intro.).
SB1-ASA1,16,99 (e) Section 293.49 (1) (a) 2.
SB1-ASA1,16,1010 (f) Section 293.55 (1) (c) to (e).
SB1-ASA1,16,1211 (g) The authority in s. 293.65 (2) (h) to conduct a hearing on a permit under s.
12293.65 as part of the hearing on the application for a mining permit.
SB1-ASA1,16,1313 (h) Section 293.65 (2) (i).
SB1-ASA1,16,18 14(2) Notice of intent. At least 12 months before submitting an application for
15a mining permit under s. 293.37 or an environmental impact report under s. 293.39
16(4) (a), whichever is earlier, a person proposing to engage in nonsulfide ferrous
17mining shall notify the department in writing of the intent to submit an application
18for a mining permit.
SB1-ASA1,17,2 19(3) Determination of completeness. After the department receives an
20application for a mining permit under s. 293.37 for nonsulfide ferrous mining, the
21department shall determine whether the application is complete. The department
22shall make the determination within 30 days after receiving the application, except
23that the department may extend the 30-day period with the consent of the applicant.
24If the department determines that the application is not complete, the department
25shall inform the applicant of the additional information that must be provided to

1complete the application. When the department determines that the application is
2complete, it shall notify the applicant.
SB1-ASA1,17,9 3(4) Notice of application. After receiving notice under sub. (3) that the
4application for a mining permit is complete, an applicant proposing to engage in
5nonsulfide ferrous mining shall publish a legal notice, under ch. 985, of the
6ownership, location, and boundaries of the proposed mining area and reclamation
7and restoration operations, at least once a week for 4 successive weeks. Within 7
8days of publication of the last notice, the person shall submit a copy of the notice to
9the department.
SB1-ASA1,17,12 10(5) Hearing. (a) No later than 30 days after the day of publication of the last
11notice required under sub. (4), any of the following may file written objections to an
12application for a permit under s. 293.37 for a nonsulfide ferrous mining project:
SB1-ASA1,17,1413 1. A person owning property that will be affected by the proposed nonsulfide
14ferrous mining operation.
SB1-ASA1,17,1615 2. Any federal, state, or local governmental agency with responsibilities
16affected by the proposed nonsulfide ferrous mining operation.
SB1-ASA1,17,2117 (b) If the department receives written objections under par. (a), the department
18shall hold a public hearing on the mining permit application in the county in which
19the majority of the mining site is located no more than 30 days after receiving the
20objections, after providing appropriate notice of the date, time, and place of the
21hearing.
SB1-ASA1,18,222 (c) The department may hold a hearing on an application for a mining permit
23under s. 293.37 for nonsulfide ferrous mining without receipt of objections no later
24than 30 days after the day of publication of the last notice required under sub. (4) if

1the department determines that a hearing is necessary to protect public health,
2safety, and welfare.
SB1-ASA1,18,6 3(6) Action on application. If s. 293.39 (5) (a) does not apply, no later than 120
4days after receiving the notice of publication under sub. (4) or, if the department
5holds a hearing under sub. (5), after holding the hearing, the department shall issue
6or deny the mining permit.
SB1-ASA1,15 7Section 15. 293.51 (3) of the statutes is amended to read:
SB1-ASA1,18,128 293.51 (3) Upon approval of the operator's bond, mining application, other
9departmental approvals that are required in connection with the mining project,
and
10certificate of insurance, the department shall issue written authorization to
11commence mining at the permitted mining site in accordance with the approved
12mining and reclamation plans.
Loading...
Loading...