SB534,20,524 (b) If an independent transmission owner determines that there is a need for
25additional transmission facilities in a portion of the electric transmission system of

1this state that consists of transmission facilities the interest in which has been
2divested to the independent transmission owner by a transmission utility, the
3independent transmission owner shall, subject to the requirements of ss. 196.49 and
4196.491 (3), expand that portion of the electric transmission system or construct
5additional transmission facilities in that portion.
SB534,20,86 (c) An independent transmission owner or an independent system operator
7shall operate transmission facilities over which it has control in a manner that does
8each of the following:
SB534,20,119 1. To the maximum extent practicable, eliminates advantages in electric
10generation, wholesale and retail markets that are otherwise related to ownership,
11control or operation of transmission facilities over which it has control.
SB534,20,1312 2. Satisfies the reasonable needs of transmission users in this state for reliable,
13low-cost and competitively priced electric service.
SB534,20,17 14(4) Transmission utilities. (a) A transmission utility may not transfer control
15over, or divest its interest in, its transmission facilities to an independent system
16operator or independent transmission owner unless, to the satisfaction of the
17commission, each of the following requirements is satisfied:
SB534,20,2118 1. The independent system operator or independent transmission owner is the
19sole provider of all transmission service to all users of its transmission system in this
20state, including the provision of retail transmission service to users that are public
21utilities.
SB534,20,2522 2. The independent system operator or independent transmission owner has
23authority over transmission facilities that is sufficient for the independent system
24operator or independent transmission owner to ensure the reliability of its
25transmission system.
SB534,21,2
13. The independent system operator or independent transmission owner has
2sufficient authority to carry out the duties specified in sub. (3).
SB534,21,73 (b) A transmission utility that transfers control over its transmission facilities
4to an independent system operator shall, subject to the approval of the applicable
5federal agency, provide reasonable and cost-effective construction, operation and
6maintenance services to the independent system operator that are required for
7operation of the transmission facilities.
SB534, s. 31 8Section 31. 196.491 (title) of the statutes is amended to read:
SB534,21,10 9196.491 (title) Advance planning of electric Strategic energy
10assessment; electric
generating facilities and transmission lines.
SB534, s. 32 11Section 32. 196.491 (1) (a) of the statutes is repealed.
SB534, s. 33 12Section 33. 196.491 (1) (am) of the statutes is created to read:
SB534,21,1313 196.491 (1) (am) "Affiliated interest" has the meaning given in s. 196.52 (1).
SB534, s. 34 14Section 34. 196.491 (1) (bm) of the statutes is created to read:
SB534,21,1715 196.491 (1) (bm) "Cooperative association" means a cooperative association
16organized under ch. 185 for the purpose of generating, distributing or furnishing
17electric energy at retail or wholesale to its members only.
SB534, s. 35 18Section 35. 196.491 (1) (d) of the statutes is amended to read:
SB534,22,219 196.491 (1) (d) "Electric utility" means any public utility, as defined in s.
20196.01, which is involved in the generation, distribution and sale of electric energy,
21and any corporation, company, individual or association, and any cooperative
22association organized under ch. 185 for the purpose of generating, distributing or
23furnishing electric energy at retail or wholesale to its members only
, which owns or
24operates, or plans within the next 10 3 years to construct, own or operate, bulk

1electric generating facilities, large electric generating
facilities or high-voltage
2transmission lines
in the state.
SB534, s. 36 3Section 36. 196.491 (1) (e) of the statutes is amended to read:
SB534,22,54 196.491 (1) (e) "Facility" means a bulk electric generating facility, a large
5electric generating facility or a high-voltage transmission line.
SB534, s. 37 6Section 37. 196.491 (1) (g) of the statutes is amended to read:
SB534,22,97 196.491 (1) (g) "Large electric generating facility" means electric generating
8equipment and associated facilities designed for nominal operation at a capacity of
9between 12,000 and 300,000 kilowatts 100 megawatts or more.
SB534, s. 38 10Section 38. 196.491 (1) (w) of the statutes is created to read:
SB534,22,1311 196.491 (1) (w) "Wholesale merchant plant" means electric generating
12equipment and associated facilities located in this state that do not provide service
13to any retail customer and that are owned and operated by any of the following:
SB534,22,1514 1. Subject to the approval of the commission under sub. (3m) (a), an affiliated
15interest of a public utility.
SB534,22,1616 2. A person that is not a public utility.
SB534, s. 39 17Section 39. 196.491 (2) (title) of the statutes is repealed and recreated to read:
SB534,22,1818 196.491 (2) (title) Strategic energy assessment.
SB534, s. 40 19Section 40. 196.491 (2) (a) (intro.) of the statutes is repealed and recreated to
20read:
SB534,22,2421 196.491 (2) (a) (intro.) The commission shall prepare a biennial strategic
22energy assessment that evaluates the adequacy and reliability of the state's current
23and future electrical supply. The strategic energy assessment shall do all of the
24following:
SB534, s. 41 25Section 41. 196.491 (2) (a) 1. and 2. of the statutes are repealed.
SB534, s. 42
1Section 42. 196.491 (2) (a) 3. of the statutes is amended to read:
SB534,23,102 196.491 (2) (a) 3. Identify the location of proposed and alternative specific sites
3for all bulk electric generating facilities and all
and describe large electric generating
4facilities over 200,000 kilowatts for which a certificate of public convenience and
5necessity has not been applied for under sub. (3) but the commencement of whose
6construction is planned within 3 years, or such longer period as the commission
7deems necessary and indicate the impacts of the proposed and alternative
8generating facilities on the environment and the means by which potential adverse
9effects on such values will be avoided or minimized;
on which an electric utility plans
10to commence construction within 3 years.
SB534, s. 43 11Section 43. 196.491 (2) (a) 3g. of the statutes is created to read:
SB534,23,1312 196.491 (2) (a) 3g. Assess the adequacy and reliability of purchased generation
13capacity and energy to serve the needs of the public.
SB534, s. 44 14Section 44. 196.491 (2) (a) 3m. of the statutes is amended to read:
SB534,23,1915 196.491 (2) (a) 3m. Identify the location of tentative and alternative routes for
16and describe high-voltage transmission lines on which an electric utility plans to
17commence
construction is intended to be commenced in the succeeding 18 months
18and indicate the effects of such transmission lines on the environment and the means
19by which potential adverse effects will be avoided or minimized;
within 3 years.
SB534, s. 45 20Section 45. 196.491 (2) (a) 3r. of the statutes is created to read:
SB534,23,2321 196.491 (2) (a) 3r. Identify and describe any plans for assuring that there is an
22adequate ability to transfer electric power into the state and the transmission area,
23as defined in s. 196.485 (1) (g), in a reliable manner.
SB534, s. 46 24Section 46. 196.491 (2) (a) 4. of the statutes is amended to read:
SB534,24,2
1196.491 (2) (a) 4. Indicate in detail Identify and describe the projected demand
2for electric energy and the basis for determining the projected demand ;.
SB534, s. 47 3Section 47. 196.491 (2) (a) 5. and 6. of the statutes are repealed.
SB534, s. 48 4Section 48. 196.491 (2) (a) 7. of the statutes is amended to read:
SB534,24,65 196.491 (2) (a) 7. Identify and describe existing and planned programs and
6policies
activities to discourage inefficient and excessive power use; and.
SB534, s. 49 7Section 49. 196.491 (2) (a) 8. of the statutes is repealed.
SB534, s. 50 8Section 50. 196.491 (2) (a) 9. to 13. of the statutes are created to read:
SB534,24,109 196.491 (2) (a) 9. Identify and describe existing and planned generating
10facilities that use renewable sources of energy.
SB534,24,1311 10. Consider the public interest in economic development, public health and
12safety, protection of the environment and diversification of sources of energy
13supplies.
SB534,24,1514 11. Assess the extent to which the regional bulk-power market is contributing
15to the adequacy and reliability of the state's electrical supply.
SB534,24,1716 12. Assess the extent to which effective competition is contributing to a reliable,
17low-cost and environmentally sound source of electricity for the public.
SB534,24,1918 13. Assess whether sufficient electric capacity and energy will be available to
19the public at a reasonable price.
SB534, s. 51 20Section 51. 196.491 (2) (ag) of the statutes is created to read:
SB534,24,2321 196.491 (2) (ag) The commission shall promulgate rules that establish
22procedures and requirements for reporting information that is necessary for the
23commission to prepare strategic energy assessments under par. (a).
SB534, s. 52 24Section 52. 196.491 (2) (am) of the statutes is renumbered 196.491 (2r) and
25amended to read:
SB534,25,5
1196.491 (2r) (title) Local ordinances. No local ordinance may prohibit or
2restrict testing activities undertaken by a an electric utility for purposes of preparing
3advance plans or
determining the suitability of a site for the placement of a facility.
4Any local unit of government objecting to such testing may petition the commission
5to impose reasonable restrictions on such activity.
SB534, s. 53 6Section 53. 196.491 (2) (b) (intro.) of the statutes is repealed and recreated to
7read:
SB534,25,108 196.491 (2) (b) (intro.) On or before July 1 biennially, the commission shall
9issue a draft of the biennial strategic energy assessment that it prepares under par.
10(a) to each of the following:
SB534, s. 54 11Section 54. 196.491 (2) (b) 8. of the statutes is amended to read:
SB534,25,1512 196.491 (2) (b) 8. The lower Wisconsin state riverway board if the plan draft
13includes an assessment of the construction, modification or relocation of a
14high-voltage transmission line, as defined in s. 30.40 (3r), that is located in the lower
15Wisconsin riverway as defined in s. 30.40 (15).
SB534, s. 55 16Section 55. 196.491 (2) (b) 9. and 10. of the statutes are created to read:
SB534,25,1817 196.491 (2) (b) 9. Each person that is required to report information to the
18commission under the rules promulgated under par. (ag).
SB534,25,2019 10. The clerk of each city, village, town and county that, as determined by the
20commission, is affected by the assessment.
SB534, s. 56 21Section 56. 196.491 (2) (c) and (d) of the statutes are repealed.
SB534, s. 57 22Section 57. 196.491 (2) (e) of the statutes is amended to read:
SB534,26,223 196.491 (2) (e) Any state agency, as defined in s. 16.375 (1), county,
24municipality, town or person may submit written comments on any plan to the

1commission on a strategic energy assessment within 180 90 days after the plan is
2filed
copies of the draft are issued under par. (b).
SB534, s. 58 3Section 58. 196.491 (2) (f) of the statutes is amended to read:
SB534,26,234 196.491 (2) (f) Because the planning process for facilities siting otherwise
5incorporates consideration and analysis of environmental impact, s.
Section 1.11 (2)
6(c) shall not apply to advance plans a strategic energy assessment prepared under
7par. (a) but the commission shall prepare a single environmental assessment on all
8plans submitted for approval under par. (a)
the strategic energy assessment, which
9shall include a discussion of generic issues related thereto. Such and environmental
10impacts. The commission shall make the environmental
assessment shall be made
11available to the public at least 30 days prior to the hearing under par. (g). The
12assessment on the plans is different from an environmental impact statement on a
13particular facility in that it need not identify the environmental effects of proposed
14sites for facilities in the plan with the same degree of detail as is required when a
15particular facility is considered for a certificate of public convenience and necessity
16under sub. (3). The assessment need not repeat information included in an
17assessment prepared for a plan submitted under par. (a) on a prior reporting date and
18with respect to which no material additional data is required or as to which there has
19been no material change in circumstances. Applicable portions of such assessment
20may be included by reference in any environmental impact statement prepared by
21the commission, including a statement prepared in connection with the
22consideration of an application for a certificate of public convenience and necessity
23under sub. (3).
SB534, s. 59 24Section 59. 196.491 (2) (g) of the statutes, as affected by 1997 Wisconsin Act
2535
, is amended to read:
SB534,28,2
1196.491 (2) (g) Within 180 No sooner than 30 and no later than 90 days after
2the plan is filed copies of the draft are issued under par. (b), the commission shall hold
3a hearing thereon on the draft which may not be a hearing under s. 227.42 or 227.44.
4The hearing shall be held in an administrative district, established by executive
5order 22, issued August 24, 1970, which the commission determines will be
6significantly affected by facilities proposed in the plan to be constructed in the
7following
on which an electric utility plans to commence construction within 3 years.
8The commission may thereafter adjourn the hearing to other locations or may
9conduct the hearing by interactive video conference or other electronic method.
10Notice of such hearing shall be given by class 1 notice, under ch. 985, published in
11the official state newspaper and such other regional papers of general circulation as
12may be designated by the commission. At such hearing the commission shall briefly
13describe the plan strategic energy assessment and give all interested persons an
14opportunity, subject to reasonable limitations on the presentation of repetitious
15material, to express their views on any aspect of the plan. The presentation of such
16views need not be under oath nor subject to cross-examination. The commission
17shall advise all persons present of their right to express their views orally or in
18writing, under oath or otherwise, and of the legal effect of each such form of testimony

19strategic energy assessment. A record of unsworn testimony the hearing shall be
20made and considered by the commission as comments on the plan strategic energy
21assessment
under par. (e). Persons presenting such views shall not be parties. The
22utility, any state agency, county, municipality, town, or any person whose substantial
23rights may be adversely affected by the testing for or construction of facilities
24described in an advance plan, shall, upon filing written notice setting forth its

1interest at least 10 days in advance, be afforded all the rights of a party in a contested
2case.
SB534, s. 60 3Section 60. 196.491 (2) (gm) of the statutes is created to read:
SB534,28,84 196.491 (2) (gm) Based on comments received on a draft, the commission shall
5prepare a final strategic energy assessment within 90 days after a hearing under par.
6(g). The commission shall provide copies of the final strategic energy assessment to
7any state agency, county, municipality, town or other person who submitted
8comments on the draft under par. (e) and to the persons specified in par. (b).
SB534, s. 61 9Section 61. 196.491 (2) (i) to (m) of the statutes are repealed.
SB534, s. 62 10Section 62. 196.491 (2m) (title) of the statutes is repealed.
SB534, s. 63 11Section 63. 196.491 (2m) of the statutes is renumbered 196.491 (3) (a) 3. a. and
12amended to read:
SB534,29,713 196.491 (3) (a) 3. a. At least 120 days prior to the filing of an application for a
14certificate of public convenience and necessity under sub. (3) for a bulk or large
15electric generating facility, the applicant shall notify the department and the
16commission of its intention to make such application and
At the same time that a
17person files an application under subd. 1., the person shall
provide the department
18with an engineering plan showing the location of the facility, a description of the
19facility, including the major components thereof having of the facility that have a
20significant air, water or solid waste pollution potential, and a description of the
21anticipated effects of such the facility on air and water quality. Within 60 30 days
22thereafter after a person provides an engineering plan, the department shall provide
23the applicant person with a listing of each department permit or approval which, on
24the basis of the information contained in the engineering plan, appears to be required
25for the construction or operation of the facility. The department shall, in consultation

1with the commission, also designate which permits and approvals, or portions
2thereof, must be obtained prior to the issuance of the certificate of public convenience
3and necessity. Such designation shall be based on a finding by the department that
4the granting or denial of the same could significantly affect overall facility design or
5location. At any time prior to the issuance of the certificate of public convenience and
6necessity, the department may, in consultation with the commission, waive the
7necessity of obtaining any such permit or approval in advance of such certificate.
SB534, s. 64 8Section 64. 196.491 (3) (a) of the statutes is renumbered 196.491 (3) (a) 1. and
9amended to read:
SB534,30,310 196.491 (3) (a) 1. No person may commence the construction of a facility unless
11such the person has applied for and received a certificate of public convenience and
12necessity from the commission as provided in this section. An application in the form
13and containing the information required by commission rules for such certificate
14shall be filed with the commission not less than 18 months prior to the
15commencement of construction of a bulk electric generating facility, and not less than

166 months prior to the commencement of construction of a large electric generating
17facility or a high-voltage transmission line. Within 10 days after filing the
18application, the commission shall send a copy of the application to the clerk of each
19municipality and town in which the proposed facility is to be located and to the main
20public library in each such county. The applicant shall apply for any permits or
21approvals required by the department prior to the issuance of a certificate of public
22convenience and necessity within 20 days after the application to the commission.
23An applicant shall make a preliminary application for all other permits and
24approvals specified under sub. (2m). Such preliminary application shall be sufficient
25if it identifies the permits and approvals applied for and contains so much of the

1information required for each such permit or approval as is then available to the
2applicant. Thereafter the applicant shall supply necessary additional engineering
3and design information as it becomes available.
SB534, s. 65 4Section 65. 196.491 (3) (a) 2. of the statutes is created to read:
SB534,30,135 196.491 (3) (a) 2. The commission shall determine whether an application filed
6under subd. 1. is complete and, no later than 30 days after the application is filed,
7notify the applicant about the determination. If the commission determines that the
8application is incomplete, the notice shall state the reason for the determination. An
9applicant may supplement and refile an application that the commission has
10determined to be incomplete. There is no limit on the number of times that an
11applicant may refile an application under this subdivision. If the commission fails
12to determine whether an application is complete within 30 days after the application
13is filed, the application shall be considered to be complete.
SB534, s. 66 14Section 66. 196.491 (3) (a) 3. b. of the statutes is created to read:
SB534,31,515 196.491 (3) (a) 3. b. Within 20 days after the department provides a listing
16specified in subd. 3. a. to a person, the person shall apply for the permits and
17approvals identified in the listing. The department shall determine whether an
18application under this subd. 3. b. is complete and, no later than 30 days after the
19application is filed, notify the applicant about the determination. If the department
20determines that the application is incomplete, the notice shall state the reason for
21the determination. An applicant may supplement and refile an application that the
22department has determined to be incomplete. There is no limit on the number of
23times that an applicant may refile an application under this subd. 3. b. If the
24department fails to determine whether an application is complete within 30 days
25after the application is filed, the application shall be considered to be complete. The

1department shall complete action on an application under this subd. 3. b. within 90
2days after the date on which the application is determined or considered to be
3complete. If the department fails to take final action within the 90-day period, the
4department is considered to have issued the permits and approvals identified in the
5listing.
SB534, s. 67 6Section 67. 196.491 (3) (b) of the statutes is amended to read:
SB534,31,107 196.491 (3) (b) The commission shall hold a public hearing on the an
8application that is determined or considered to be complete in the area affected
9pursuant to s. 227.44. A class 1 notice, under ch. 985, shall be given at least 30 days
10prior to the hearing.
SB534, s. 68 11Section 68. 196.491 (3) (d) (intro.) of the statutes is amended to read:
SB534,31,1512 196.491 (3) (d) (intro.) Except as provided under par. (e) and s. 196.493, the
13commission shall approve an application for a certificate of public convenience and
14necessity shall be approved only if the commission determines that all of the
15following
:
SB534, s. 69 16Section 69. 196.491 (3) (d) 1. of the statutes is repealed.
SB534, s. 70 17Section 70. 196.491 (3) (d) 2. of the statutes is amended to read:
SB534,31,2018 196.491 (3) (d) 2. The proposed facility is necessary to satisfy satisfies the
19reasonable needs of the public for an adequate supply of electric energy. This
20subdivision does not apply to a wholesale merchant plant.
SB534, s. 71 21Section 71. 196.491 (3) (d) 3. of the statutes is amended to read:
Loading...
Loading...