SB55-ASA1-AA59,1,5
3"(6x)
Traffic control signals in Oak Creek. No later than June 30, 2003, the
4department of transportation shall install traffic control signals at the intersection
5of STH 38 and Oakwood Road in the city of Oak Creek in Milwaukee County.".
SB55-ASA1-AA59,2,2
7"(7y)
Noise attenuation barrier in Milwaukee County; I 94 at Grange Avenue.
8The department of transportation shall install a noise attenuation barrier along the
9west side of I 94 from the intersection of I 94 and Grange Avenue and extending to
10the south, in Milwaukee County. The department shall expend funds not to exceed
1$200,000 from the appropriation under section 20.395 (3) (cq), (cv), and (cx) of the
2statutes, as affected by this act, for the installation required under this subsection.".