AB632,7,2215
15.795
(1) Office of the commissioner of railroads. There is created an office
16of the commissioner of railroads which is attached to the public service commission
17under s. 15.03, provided that s. 85.02
(1) does not apply to the office of the
18commissioner of railroads. The commissioner of railroads shall have expertise in
19railroad issues and may not have a financial interest in a railroad, as defined in s.
20195.02 (1). The commissioner may not serve on or under any committee of a political
21party. The commissioner shall hold office until a successor is appointed and
22qualified.
AB632, s. 3
23Section
3. 16.969 (4) of the statutes is amended to read:
AB632,8,624
16.969
(4) A county, town, village
, or city that receives a distribution under sub.
25(3) (b) may use the distribution only for park, conservancy, wetland or other similar
1environmental programs
, unless the commission approves a different use under this
2subsection. A county, town, village, or city that receives a distribution may request
3in writing at any time that the commission approve a different use. The commission
4shall make a decision no later than 14 days after receiving such a request. The
5commission shall approve a request if it finds that the request is in the public
6interest.
AB632, s. 4
7Section
4. 23.09 (22m) of the statutes is created to read:
AB632,8,128
23.09
(22m) Siting of electric transmission facilities. To the greatest extent
9feasible that is consistent with economic and engineering considerations and the
10protection of the environment, the department shall implement the policy specified
11in s. 1.12 (6) in making all decisions, orders, and rules regarding the siting of new
12electric transmission facilities.
AB632, s. 5
13Section
5. 30.02 (1) of the statutes is amended to read:
AB632,8,1614
30.02
(1) In Except as provided in s. 30.025, in any proceeding under this
15chapter where public notice is required, the department shall follow the procedures
16in subs. (3) and (4).
AB632, s. 6
17Section
6. 30.02 (2) of the statutes is amended to read:
AB632,8,2118
30.02
(2) In Except as provided in s. 30.025, in any proceeding under this
19chapter where public notice is not required, the department shall follow the
20procedures in subs. (3) and (4) if it determines that substantial interests of any party
21may be adversely affected by the proceeding.
AB632, s. 7
22Section
7. 30.025 (title) of the statutes is amended to read:
AB632,8,24
2330.025 (title)
Optional permit
Permit procedure for certain electric
24generating facilities and high-voltage transmission lines
utility facilities.
AB632, s. 8
1Section
8. 30.025 (1) of the statutes is renumbered 30.025 (1s) (a) and
2amended to read:
AB632,9,153
30.025
(1s) (a) Any
electric utility, as defined in s. 196.491 (1) (d), person 4proposing to construct a
utility facility
, as defined in s. 196.491 (1) (e), which facility
5is to be located adjacent to a waterway in such a manner as to require one or more
6permits to be issued under this chapter and ch. 31 may to which this section applies
7shall, in lieu of separate application for permits
under those chapters, submit
an
8engineering plan one application for permits together with any additional
9information required by the department.
Such plan
The application shall be filed
10with the department
within 20 days after at the same time that an application for
11a certificate
of public convenience and necessity is filed with the
public service 12commission under s.
196.49 or 196.491 (3)
and shall include the detailed information
13that the department requires to determine whether an application is complete and
14to carry out its obligations under sub. (4). The department may require
15supplemental information to be furnished thereafter.
AB632, s. 9
16Section
9. 30.025 (1b) of the statutes is created to read:
AB632,9,1717
30.025
(1b) Definitions. In this section:
AB632,9,1818
(a) "Commission" means the public service commission.
AB632,9,2219
(b) "Permit" means a permit or approval required under this chapter or ch. 31,
20a storm water discharge permit required under s. 283.33 (1) (a), or a water quality
21certification required under s. 281.36 or under rules promulgated under subch. II of
22ch. 281 to implement
33 USC 1341 (a).
AB632,9,2423
(c) "Utility facility" includes a project, as defined in s. 196.49 (3) (a), and a
24facility, as defined in s. 196.491 (1) (e).
AB632, s. 10
25Section
10. 30.025 (1e) of the statutes is created to read:
AB632,10,2
130.025
(1e) Applicability. This section applies to a proposal to construct a
2utility facility if all of the following conditions exist:
AB632,10,53
(a) The person proposing to construct the utility facility is required to obtain
4a certificate issued by the commission under s. 196.49 or 196.491 (3) before beginning
5construction.
AB632,10,66
(b) The utility facility is required to obtain one or more permits.
AB632, s. 11
7Section
11. 30.025 (1m) of the statutes is created to read:
AB632,10,148
30.025
(1m) Preapplication process. Before filing an application under this
9section, a person proposing to construct a utility facility shall notify the department
10of the intention to file an application. After receiving such notice, the department
11shall confer with the person, in cooperation with the commission, to make a
12preliminary assessment of the project's scope, to make an analysis of alternatives,
13to identify potential interested persons, and to ensure that the person making the
14proposal is aware of all of the following:
AB632,10,1515
(a) The permits that the person may be required to obtain.
AB632,10,1616
(b) The information that the person will be required to provide.
AB632,10,1917
(c) The timing of information submissions that the person will be required to
18provide in order to enable the department to participate in commission review
19procedures and to process the application in a timely manner.
AB632, s. 12
20Section
12. 30.025 (1s) (title) of the statutes is created to read:
AB632,10,2121
30.025
(1s) (title)
Application for permits.
AB632, s. 13
22Section
13. 30.025 (1s) (b) of the statutes is created to read:
AB632,11,223
30.025
(1s) (b) A person who applies to the commission for a certificate under
24s. 196.49 or 196.491 (3) is eligible to apply under par. (a) for any permit that the utility
1facility may require under this chapter or ch. 31, and to receive such permit
2regardless of whether that person is a riparian owner.
AB632, s. 14
3Section
14. 30.025 (2) of the statutes is amended to read:
AB632,11,134
30.025
(2) Hearing. Once
electric utilities have met the applicant meets the
5requirements of sub.
(1) (1s) (a), the department
shall may schedule the matter for
6a public hearing. Notice of the hearing shall be given to the applicant and shall be
7published as a class 1 notice under ch. 985. The department may give such further
8notice as it deems proper, and shall give notice to persons requesting same. One copy
9of the application shall be available for public inspection at the office of the
10department, at least one copy in the district office of the department and at least one
11copy at the main public library of the area affected.
Notwithstanding s. 227.42, the
12hearing shall be an informational hearing and may not be treated as a contested case
13hearing nor converted to a contested case hearing.
AB632, s. 15
14Section
15. 30.025 (2g) of the statutes is created to read:
AB632,11,1915
30.025
(2g) Participation in commission proceedings. (a) The department
16shall review every proposed utility facility subject to this section, including each
17location, site, or route proposed for the utility facility, to assess whether each
18proposed location, site, or route can comply with the requirements of the required
19permits, and shall provide that information to the commission.
AB632,11,2420
(b) The department shall participate in commission investigations or
21proceedings under s. 196.49 or 196.491 (3) with regard to any proposed utility facility
22that is subject to this section. In order to ensure that the commission's decision is
23consistent with the department's responsibilities, the department shall provide the
24commission with information that is relevant to only the following:
AB632,11,2525
1. Environmental issues that concern the proposed utility facility.
AB632,12,2
12. Public rights in navigable waters that may be affected by the proposed utility
2facility.
AB632,12,43
3. Location, site, or route issues concerning the proposed utility facility,
4including alternative locations, sites, or routes.
AB632, s. 16
5Section
16. 30.025 (2s) of the statutes is created to read:
AB632,12,86
30.025
(2s) Consideration of alternatives. (a) The department shall treat the
7commission's decision under s. 196.49 or 196.491 (3) as concluding that there is no
8practicable alternative for the utility facility if all of the following apply:
AB632,12,109
1. The department has participated in the commission's investigations or
10proceedings under sub. (2g).
AB632,12,1311
2. The commission's decision under s. 196.49 or 196.491 (3) is consistent with
12the department's assessment and information under sub. (2g) considering those
13factors required to be considered by the commission under s. 196.49 or 196.491 (3).
AB632,12,2014
(b) If par. (a) applies, the department may not require the applicant for the
15proposed utility facility to undertake further analysis of any utility facility
16alternatives, including an analysis of alternative methods of meeting the need for the
17project or alternative locations, sites, or routes in order to satisfy the criteria under
18sub. (3). The department may identify adjustments that may be required to address
19permitting issues within the location, site, or route approved by the commission
20under s. 196.49 or 196.491 (3).
AB632, s. 17
21Section
17. 30.025 (3) (intro.) of the statutes is amended to read:
AB632,12,2322
30.025
(3) Permit issuance. (intro.) The department shall grant the necessary
23permits if
, after hearing, it finds that the applicant has shown that the proposal:
AB632, s. 18
24Section
18. 30.025 (3m) of the statutes is created to read:
AB632,13,5
130.025
(3m) Environmental assessments for certain projects. The
2department is not required to prepare an environmental impact statement under s.
31.11 (2) (c) for the construction of a project that is specified in s. 196.491 (4) (c) 1. and
4for which one or more permits are required, but shall prepare an environmental
5assessment regarding the construction.
AB632, s. 19
6Section
19. 30.025 (4) of the statutes is amended to read:
AB632,13,127
30.025
(4) Permit conditions. The permit may be issued upon stated
8conditions deemed necessary to assure compliance with the criteria designated
9under sub. (3). The department shall grant or deny the application
within the time
10limit applicable under s. 196.491 (3) (a) 3. b. for a permit for the utility facility within
1130 days of the date on which the commission issues its decision under s. 196.49 or
12196.491 (3).
AB632, s. 20
13Section
20. 30.206 (1m) of the statutes is created to read:
AB632,13,1614
30.206
(1m) The department shall issue a general permit under this section
15for the construction of projects for which the commission is considered to have issued
16a certificate of public convenience and necessity under s. 196.491 (3b).
AB632, s. 21
17Section
21. 66.0119 (1) (a) of the statutes is amended to read:
AB632,13,2518
66.0119
(1) (a) "Inspection purposes"
include includes such purposes as
19building, housing, electrical, plumbing, heating, gas, fire, health, safety,
20environmental pollution, water quality, waterways, use of water, food, zoning,
21property assessment, meter and obtaining data required to be submitted in an initial
22site report or feasibility report under subch. III of ch. 289 or s. 291.23, 291.25, 291.29
23or 291.31 or an environmental impact statement related to one of those reports.
24"Inspection purposes" also includes purposes for obtaining information specified in
25s. 196.02 (5m) by or on behalf of the public service commission.
AB632, s. 22
1Section
22. 79.04 (6) (c) 3. of the statutes is created to read:
AB632,14,72
79.04
(6) (c) 3. For the purpose of determining the amount of the payment
3under par. (b), if a production plant is located in more than one county, the payment
4amount under par. (b) shall be divided among the counties in which the plant is
5located based on the net book value of that portion of the plant located in each county
6as of December 31, 2004, or as of the date on which the plant is operational,
7whichever is later.
AB632,14,1910
79.04
(7) (c) 1m. Beginning with payments in 2005, if a cogeneration production
11plant, as described in sub. (6) (a), is built and completed after December 31, 2003, and
12has a name-plate capacity of at least one megawatt, each municipality and county
13in which such a cogeneration production plant is located shall receive annually from
14the public utility account a payment in an amount that is equal to the number of
15megawatts that represents the cogeneration production plant's name-plate capacity,
16multiplied by $1,000. Any municipality or county that receives a payment under this
17subdivision in any year may not receive a payment under subd. 1. in that year
, if the
18payment under subd. 1. is based on the same production plant as the payment under
19this subdivision.
AB632, s. 24
20Section
24. 79.04 (7) (d) of the statutes is created to read:
AB632,15,221
79.04
(7) (d) For the purpose of determining the amount of any payment under
22this subsection, if a production plant is located in more than one municipality or
23county, the payment amount shall be divided among the municipalities or counties
24in which the plant is located based on the net book value of that portion of the plant
1located in each municipality or county as of December 31, 2004, or as of the date on
2which the plant is operational, whichever is later.
AB632, s. 25
3Section
25. 85.02 of the statutes is renumbered 85.02 (1).
AB632, s. 26
4Section
26. 85.02 (2) of the statutes is created to read:
AB632,15,85
85.02
(2) To the greatest extent feasible that is consistent with economic and
6engineering considerations and protection of the environment, the department shall
7implement the policy specified in s. 1.12 (6) in making all decisions, orders, and rules
8regarding the siting of new electric transmission facilities.
AB632, s. 27
9Section
27. 91.75 (4) of the statutes is amended to read:
AB632,15,1310
91.75
(4) Such ordinances shall be considered local ordinances for purposes of
11s. 196.491 (3) (i)
and (4) (c) 3. and shall provide that gas and electric utility uses not
12requiring authorization under s. 196.491 (3) are special exceptions or permitted or
13conditional uses and are uses that are consistent with agricultural use.
AB632, s. 28
14Section
28. 196.02 (5m) of the statutes is created to read:
AB632,15,1915
196.02
(5m) Property inspections. The commission may inspect property for
16the purpose of obtaining any information related to the preparation or review of an
17application for a certificate under s. 196.49 or 196.491 (3), including any information
18necessary to evaluate any environmental features or effects that are relevant to such
19an application.
AB632, s. 29
20Section
29. 196.025 (1m) of the statutes is created to read:
AB632,15,2421
196.025
(1m) To the greatest extent feasible that is consistent with economic
22and engineering considerations and protection of the environment, the commission
23shall implement the policy specified in s. 1.12 (6) in making all decisions, orders, and
24rules regarding the siting of new electric transmission facilities.
AB632, s. 30
25Section
30. 196.025 (2) (intro.) of the statutes is amended to read:
AB632,16,4
1196.025
(2) (intro.) The commission shall promulgate rules establishing
2requirements and procedures for the commission to carry out the duties under s.
31.11. Rules promulgated under this subsection shall include requirements and
4procedures for
the commission to comply with sub. (2m) and for each of the following:
AB632, s. 31
5Section
31. 196.025 (2m) of the statutes is created to read:
AB632,16,66
196.025
(2m) (a) In this subsection:
AB632,16,77
1. "Department" means the department of natural resources.
AB632,16,98
2. "Project" means a project or construction requiring a certificate under s.
9196.49 or 196.491 (3).
AB632,16,1210
(b) The commission and the department shall coordinate the execution of their
11respective duties under s. 1.11 for any action of the commission or department
12regarding a project as follows:
AB632,16,1613
1. If the rules of either the commission or the department require the
14commission or the department to prepare an environmental impact statement on the
15project, the commission and the department shall cooperatively prepare an
16environmental impact statement.
AB632,16,2017
2. If subd. 1. does not apply and the rules of either the commission or the
18department require the commission or the department to prepare an environmental
19assessment on the project, the commission and the department shall prepare an
20environmental assessment.
AB632,16,2321
3. The environmental impact statement or environmental assessment required
22under subd. 1. or 2. shall include all of the information required for both the
23commission and the department to carry out their respective duties under s. 1.11.
AB632,17,524
(c) Paragraph (b) does not waive any duty of the commission or the department
25to comply with s. 1.11 or to take any other action required by law regarding a project,
1except that, notwithstanding s. 1.11 (2) (c) 3. and (e), the commission and the
2department are required to consider only the project identified in the application for
3the certificate under s. 196.49 or 196.491 (3) and one alternative to the project and
4that alternative shall consist of any alternative location, site, or route for the project
5that is specified by the person proposing the project.
AB632, s. 32
6Section
32. 196.20 (7) of the statutes is created to read:
AB632,17,137
196.20
(7) (a) In this subsection, "mitigation payment" means, as approved by
8the commission, an unrestricted or recurring monetary payment to a local unit of
9government in which an electric generating facility is located to mitigate the impact
10of the electric generating facility on the local unit of government. "Mitigation
11payment" does not include payments made or in-kind contributions for restricted
12purposes to directly address health or safety impacts of the electric generating
13facility on the local unit of government.
AB632,17,1514
(b) Except as provided in par. (c), an electric public utility may not recover in
15rates any of the following:
AB632,17,1616
1. The cost of mitigation payments paid by the utility.
AB632,17,2117
2. The cost of mitigation payments paid by the owner or operator of an electric
18generating facility that the owner or operator recovers from the utility by selling
19electricity to the utility, by leasing the facility to the utility, or by any agreement
20between the owner or operator of the electric generating facility and the public
21utility.
AB632,17,2422
(c) The commission shall only approve a mitigation payment agreement that
23is received by the commission before June 10, 2003, and, if the commission finds the
24agreement to be reasonable, shall not subsequently modify the agreement.
AB632, s. 33
25Section
33. 196.491 (3) (a) 1. of the statutes is amended to read:
AB632,18,10
1196.491
(3) (a) 1.
No Except as provided in sub. (3b), no person may commence
2the construction of a facility unless the person has applied for and received a
3certificate of public convenience and necessity
from the commission as provided in
4this section under this subsection. An application
for a certificate issued under this
5subsection shall be in the form and
containing
contain the information required by
6commission rules
for such certificate and shall be filed with the commission not less
7than 6 months prior to the commencement of construction of a facility. Within 10
8days after filing
the an application
under this subdivision, the commission shall send
9a copy of the application to the clerk of each municipality and town in which the
10proposed facility is to be located and to the main public library in each such county.
AB632, s. 34
11Section
34. 196.491 (3) (a) 3. a. of the statutes is amended to read: