SB79-SA1,2,8
3"(am) The commission shall specify in an order under this section a deadline
4at least 60 days after the date of issuance of the order for the public utility to notify
5the commission in writing about whether the public utility accepts or waives
6acceptance of the order. If public utility does not make the notification by the
7deadline specified in the order, the public utility is considered to have waived
8acceptance of the order.".
SB79-SA1,2,14
10"(b) If the public utility accepts the order, then, in all future rate-making
11proceedings regarding the public utility, the order shall be binding on the commission
12in its treatment of the recovery of the capital costs of the facility that is subject to the
13order and the commission may not consider the order or the effects of the order in its
14treatment of the recovery of any other cost of the public utility.
SB79-SA1,2,1515
(bm) If the public utility waives or is considered to have waived acceptance".
SB79-SA1,2,18
17"(c) The commission may not require a public utility to apply for or accept an
18order under this section.".