SB520,7,2422 3. The total amount paid by each executive branch agency on each information
23technology project for which debt is outstanding, as compared to the total financing
24amount originally approved for that information technology project.
SB520,8,2
14. A summary of repayments made towards any master lease in the previous
2fiscal year.
SB520,8,15 3(13) (a) Except as provided in par. (b), include in each contract with a vendor
4of information technology that involves a large, high-risk information technology
5project under sub. (10) or that has a projected cost greater than $1,000,000, and
6require each executive branch agency authorized under s. 16.71 (1m) to enter into
7a contract for materials, supplies, equipment, or contractual services relating to
8information technology to include in each contract with a vendor of information
9technology that involves a large, high-risk information technology project under
10sub. (10) or that has a projected cost greater than $1,000,000 a stipulation requiring
11the vendor to submit to the department for approval any order or amendment that
12would change the scope of the contract and have the effect of increasing the contract
13price. The stipulation shall authorize the department to review the original contract
14and the order or amendment to determine all of the following and, if necessary, to
15negotiate with the vendor regarding any change to the original contract price:
SB520,8,1716 1. Whether the work proposed in the order or amendment is within the scope
17of the original contract.
SB520,8,1818 2. Whether the work proposed in the order or amendment is necessary.
SB520,8,2119 (b) The department or an executive branch agency may exclude from a contract
20described in par. (a) the stipulation required under par. (a) if all of the following
21conditions are satisfied:
SB520,8,2322 1. Including such a stipulation would negatively impact contract negotiations
23or significantly reduce the number of bidders on the contract.
SB520,9,324 2. If the exclusion is sought by an executive branch agency, that agency submits
25to the department a plain-language explanation of the reasons for excluding the

1stipulation and the alternative provisions the executive branch agency will include
2in the contract to ensure that the contract will be completed on time and within the
3contract budget.
SB520,9,74 3. If the exclusion is sought by the department, the department prepares a
5plain-language explanation of the reasons the stipulation was excluded and the
6alternative provisions the department will include in the contract to ensure that the
7contract will be completed on time and within the contract budget.
SB520,9,158 4. The department submits for approval by the joint committee on information
9policy and technology any explanation and alternative contract provisions required
10under subd. 2. or 3. If, within 14 working days after the date that the department
11submits any explanation and alternative contract provisions required under this
12subdivision, the cochairpersons of the joint committee on information policy and
13technology do not notify the department that the committee has scheduled a meeting
14for the purpose of reviewing the contract provisions, the explanation and alternative
15contract provisions shall be deemed approved.
SB520,9,21 16(14) (a) Require each executive branch agency, other than the Board of Regents
17of the University of Wisconsin system, that has entered into an open-ended contract
18for the development of information technology to submit to the department quarterly
19reports documenting the amount expended on the information technology
20development project. In this subsection, "open-ended contract" means a contract for
21information technology that includes one or both of the following:
SB520,9,2322 1. Stipulations that provide that the contract vendor will deliver information
23technology products or services but that do not specify a maximum payment amount.
SB520,10,3
12. Stipulations that provide that the contract vendor shall be paid an hourly
2wage but that do not set a maximum limit on the number of hours required to
3complete the information technology project.
SB520,10,54 (b) Compile and annually submit to the joint committee on information policy
5and technology the reports required under par. (a).
SB520, s. 6 6Section 6. 16.973 (15) of the statutes is created to read:
SB520,10,127 16.973 (15) No later than March 1 and September 1 of each year, submit to the
8joint committee on information policy and technology a report that documents for
9each executive branch agency information technology project with an actual or
10projected cost greater than $1,000,000 or that the department of administration has
11identified as a large, high-risk information technology project under sub. (10) (a) all
12of the following:
SB520,10,1313 (a) Original and updated project cost projections.
SB520,10,1514 (b) Original and updated completion dates for the project and any stage of the
15project.
SB520,10,1716 (c) An explanation for any variation between the original and updated costs and
17completion dates under pars. (a) and (b).
SB520,10,2018 (d) A copy of any contract entered into by the department or by an executive
19branch agency authorized under s. 16.71 (1m) to enter into a contract for the project
20and not provided in a previous report.
SB520,10,2121 (e) All sources of funding for the project.
SB520,10,2322 (f) The amount of any funding provided for the project through a master lease
23under s. 16.76 (4).
SB520,10,2524 (g) Information about the status of the project, including any portion of the
25project that has been completed.
SB520,11,2
1(h) Any other information about the project, or related information technology
2projects, requested by the joint committee on information policy and technology.
SB520, s. 7 3Section 7. 227.01 (13) (km) of the statutes is created to read:
SB520,11,54 227.01 (13) (km) Establishes policies for information technology development
5projects as required under s. 16.971 (2) (Lg).
SB520, s. 8 6Section 8. Nonstatutory provisions.
SB520,11,157 (1) Written policies for information technology development projects. No
8later than the first day of the 6th month beginning after the effective date of this
9subsection, the department of administration shall submit for review by the joint
10legislative audit committee and for approval by the joint committee on information
11policy and technology a preliminary draft of the policies required under section
1216.971 (2) (Lg) 1. of the statutes, as created by this act. If the joint committee on
13information policy and technology is not organized, the joint legislative audit
14committee shall approve the preliminary draft of the policies required under section
1516.971 (2) (Lg) 1. of the statutes, as created by this act.
SB520,11,2016 (2) Rules pertaining to large, high-risk information technology projects.
17The department of administration shall submit in proper form the rules required
18under section 16.973 (10) of the statutes, as created by this act, to the legislative
19council staff under section 227.15 (1) of the statutes no later than the first day of the
2012th month beginning after the effective date of this subsection.
SB520,11,2121 (End)
Loading...
Loading...