SB488-SSA2,103,24 23295.57 Application procedure. (1) Submission. (a) An applicant shall
24submit the application for a mining permit as provided in s. 295.47.
SB488-SSA2,104,6
1(b) The department and the state geologist shall protect as confidential any
2information, other than effluent data, contained in an application for a mining
3permit, upon a showing that the information is entitled to protection as a trade
4secret, as defined in s. 134.90 (1) (c), and any information relating to production or
5sales figures or to processes or production unique to the applicant or that would tend
6to adversely affect the competitive position of the applicant if made public.
SB488-SSA2,104,13 7(2) Determination of administrative completeness. (a) The department shall
8review an application for a mining permit and, within 30 days after the application
9is submitted, shall determine either that the application is complete or that
10additional information is needed. If the department determines that the application
11is complete, the department shall notify the applicant in writing of that fact within
12the 30-day period and the date on which the department sends the notice is the day
13on which the application is administratively complete.
SB488-SSA2,104,2114 (b) If the department determines under par. (a) that an application is
15incomplete, the department shall notify the applicant in writing and may make one
16request for additional information during the 30-day period specified in par. (a).
17Within 10 days after receiving additional requested information from the applicant,
18the department shall notify the applicant in writing as to whether it has received all
19of the requested information. The day on which the department sends the 2nd notice
20under this paragraph is the day on which the application is administratively
21complete.
SB488-SSA2,104,2422 (c) If the department fails to meet the 30-day time limit under par. (a) or the
2310-day time limit under par. (b), the application is administratively complete on the
24last day of the 30-day time limit or 10-day time limit.
SB488-SSA2,105,4
1(d) The department may request additional information needed to process a
2mining application from the applicant after the application is administratively
3complete, but the department may not delay the determination of administrative
4completeness based on a request for additional information.
SB488-SSA2,105,8 5(3) Notice of additional approvals. Within 30 days after the mining permit
6is administratively complete under sub. (2), the department shall notify the
7applicant in writing of any approval required for the construction or operation of the
8mining site that was not previously identified by the department.
SB488-SSA2,105,13 9(3m) Receipt of certain approvals. If a storm water discharge permit under
10s. 283.33 (1) (a) or a water quality certification under rules promulgated under subch.
11II of ch. 281 to implement 33 USC 1341 (a) is needed for a mining operation, the
12person applying for the mining permit may apply for and be issued the permit or
13certification.
SB488-SSA2,105,16 14(4) Public information and notice. (a) The department shall make available
15for review in the city, village, or town in which the proposed mining site is located,
16information concerning the proposed mining, including all of the following:
SB488-SSA2,105,1817 1. The application for the mining permit, including the mining plan,
18reclamation plan, and mining waste site feasibility study and plan of operation.
SB488-SSA2,105,1919 2. Any of the following relating to an approval other than the mining permit:
SB488-SSA2,105,2020 a. The application.
SB488-SSA2,105,2121 b. A draft approval.
SB488-SSA2,105,2222 c. Information or summaries relating to the approval.
SB488-SSA2,105,2523 3. The environmental impact statement, environmental impact report, and any
24additional supporting information used in the department's evaluation of the
25proposed mining.
SB488-SSA2,106,2
14. The department's analyses and preliminary determinations relating to any
2approval.
SB488-SSA2,106,103 (b) The department shall distribute a notice that describes the availability of
4the information under par. (a); the opportunity for written public comment, including
5an invitation for the submission of written comments by any person within 45 days
6after the notice is published; and the date, time, and location of the public
7informational hearing and that includes any additional information that a law
8concerning any approval requires to be provided. The department shall publish the
9notice as a Class I notice under ch. 985. The department shall also send the notice
10to all of the following:
SB488-SSA2,106,1211 1. The clerk of any city, village, town, or county with zoning jurisdiction over
12the proposed mining site.
SB488-SSA2,106,1413 2. The clerk of any city, village, town, or county within whose boundaries any
14portion of the proposed mining site is located.
SB488-SSA2,106,1615 3. The clerk of any city, village, or town, contiguous to any city, village, or town
16within whose boundaries any portion of the proposed mining site is located.
SB488-SSA2,106,1917 4. The main public library of each city, village, town, or county with zoning
18jurisdiction over the proposed mining site or within whose boundaries any portion
19of the proposed mining site is located.
SB488-SSA2,106,2120 5. Any regional planning commission for the area within which the proposed
21mining site lies.
SB488-SSA2,106,2422 6. Any state agency that the department knows is required to grant a permit
23or other authorization necessary for the construction or operation of the proposed
24mining project.
SB488-SSA2,107,4
17. The federal environmental protection agency, U.S. Army Corps of Engineers,
2and states potentially affected by the proposed discharge if a water discharge permit
3under ch. 283 or a water quality certification for a federal wetland under s. 295.60
4(4) is to be considered at the public informational hearing.
SB488-SSA2,107,75 8. The federal environmental protection agency and appropriate agencies in
6other states that may be affected if an air pollution control permit under ch. 285 is
7to be considered at the public informational hearing.
SB488-SSA2,107,108 9. If a water withdrawal permit under s. 295.61 for a withdrawal of surface
9water is to be considered at the public informational hearing, the persons specified
10in s. 30.18 (4) (a).
SB488-SSA2,107,1611 10. If an individual permit under s. 30.12 for a structure through which water
12transferred from the Great Lakes basin would be returned to the source watershed
13through a stream tributary to one of the Great Lakes is to be considered at the public
14informational hearing, the governing body of each city, village, and town through
15which the stream flows or that is adjacent to the stream downstream from the point
16at which the water would enter the stream.
SB488-SSA2,107,1717 11. Any person upon request.
SB488-SSA2,107,1818 12. The applicant.
SB488-SSA2,107,2119 13. Any other person to whom the department is required to give notice of any
20proposed determination, application, or hearing concerning an approval under the
21laws relating to the issuance of any approval or under s. 1.11.
SB488-SSA2,108,222 (c) The department shall coordinate the public comment period for the mining
23permit with the public comment period for any other approval for the mining
24operation, except that if an application for an approval is filed too late to allow public
25comment within the public comment period for the mining permit, the department

1shall issue separate notice, as described in par. (b), for the approval after the
2application is filed.
SB488-SSA2,108,16 3(5) Informational hearing. The department shall hold a public informational
4hearing before issuing or denying a mining permit and not less than 30 days after
5publishing the notice under sub. (4) (b). The department shall hold the public
6informational hearing in the county where the majority of the proposed mining site
7is located. The department shall hold a single public informational hearing covering
8the mining permit, all other approvals, and the environmental impact statement,
9except that if an application for an approval is filed too late to allow the application
10to be considered at the public informational hearing for the mining permit, the
11department shall hold a separate public informational hearing on the approval in the
12county where the proposed site is located not less than 30 days after publishing the
13notice under sub. (4) (b) for the approval. The public informational hearing under
14this subsection is not a contested case hearing under ch. 227. At the hearing, the
15department shall take testimony on all of the following with regard to any proposed
16withdrawal of groundwater or surface water:
SB488-SSA2,108,1817 (a) The public rights in any body of water and the related environment that may
18be injured by the proposed withdrawal of groundwater or surface water.
SB488-SSA2,108,2019 (b) The public benefits provided by increased employment, economic activity,
20and tax revenues from the proposed mining operation.
SB488-SSA2,108,2221 (c) The direct and indirect social and economic costs and benefits of the
22proposed mining operation.
SB488-SSA2,108,2423 (d) Whether the proposed withdrawal of groundwater or surface water will
24consume nonsurplus water.
SB488-SSA2,108,2525 (e) The rights of competing users of the groundwater or surface water.
SB488-SSA2,109,2
1(f) Any other water withdrawal issues identified by the department as relevant
2to the decision of whether to issue or deny a permit.
SB488-SSA2,109,6 3(6) Summary. After considering the comments received under subs. (4) and (5)
4and before acting on the application for the mining permit, the department shall
5prepare a summary of the comments and the department's response to the
6comments.
SB488-SSA2,109,14 7(7) Deadline for acting on mining permit application. (a) No more than 420
8days after the day on which the application for a mining permit is administratively
9complete under sub. (2), the department shall approve the application, and issue a
10mining permit, or deny the application, in accordance with s. 295.58, unless the
11department and the applicant agree to extend the deadline. The department and the
12applicant may agree to not more than one extension and that extension may not
13exceed 60 days. The department and the applicant may enter into an extension only
14if one of the following applies:
SB488-SSA2,109,1615 1. An extension is necessary to enable the department and the U.S. Army Corps
16of Engineers to jointly prepare their environmental impact statements.
SB488-SSA2,109,1817 2. New information or a change to the mining proposal necessitates additional
18time to review the application.
SB488-SSA2,109,2119 (b) If the department does not comply with the deadline under par. (a),
20including any extension agreed to by the applicant, the department shall refund the
21fees under s. 295.73 (3) (a) and (d) that were paid by the applicant.
SB488-SSA2,110,222 (c) If the department does not comply with the deadline under par. (a),
23including any extension agreed to by the applicant, the applicant may bring an action
24for mandamus to compel the department to approve or deny the application.
25Notwithstanding s. 814.04 (1), in an action under this paragraph the court shall

1award the applicant its costs, including reasonable attorney fees, if it determines
2that the department did not comply with the deadline under par. (a).
SB488-SSA2,110,8 3(8) Deadline for acting on other approvals. (a) Except as provided in par.
4(c), if an applicant files an application for an approval other than a mining permit
5no later than 60 days after the day on which the application for the mining permit
6is administratively complete under sub. (2), the department shall approve the
7application, and issue the approval or deny the application no later than the deadline
8under sub. (7) (a), including any extension agreed to by the applicant.
SB488-SSA2,110,159 (b) Except as provided in par. (c) if an applicant files an application for an
10approval other than a mining permit more than 60 days after the day on which the
11application for the mining permit is administratively complete under sub. (2), the
12deadline for acting on the application is extended beyond the deadline under sub. (7)
13(a), including any extension agreed to by the applicant, by the number of days beyond
14the 60th day after the day on which the application for the mining permit is
15administratively complete that the applicant files the application for the approval.
SB488-SSA2,110,1716 (c) Paragraphs (a) and (b) do not apply to the application for an air pollution
17control permit under s. 285.62.
SB488-SSA2,110,2118 (d) The department shall incorporate an approval other than a mining permit
19into a single document with the mining permit, unless the application for the
20approval was filed more than 60 days after the day on which the application for the
21mining permit is administratively complete under sub. (2).
SB488-SSA2,111,2 22(8m) Submission of technical review to Great Lakes regional body. If an
23applicant files an application under s. 281.346 for an approval for a withdrawal of
24surface water or groundwater that is subject to regional review or council approval,
25the department shall provide its technical review, as defined in s. 281.346 (1) (u), to

1the regional body, as defined in s. 281.346 (1) (q), no later than 90 days after the
2applicant files the application for the approval.
SB488-SSA2,111,12 3(9) Applicable procedure. The provisions of this section and ss. 295.58 (5) and
4(6) and 295.77 concerning public notice, comment, and hearing; issuance of
5department decisions; effective date of department decisions; and review of
6department decisions; and the duration of approvals apply to any approval,
7notwithstanding any provisions related to those matters in s. 44.40 or 169.25, subch.
8I or VI of ch. 77, ch. 23, 29, 30, 169, 281, 283, 285, 289, or 291, or rules promulgated
9under those provisions, except as provided in s. 281.343 (7r) and except that if a
10withdrawal of surface water or groundwater is subject to regional review or council
11approval under s. 281.346, the applicable provisions related to regional review or
12council approval apply.
SB488-SSA2,111,16 13295.58 Mining; department grant or denial of permit. (1) Criteria for
14approval.
(a) Except as provided in sub. (2) and except with respect to property
15specified in s. 41.41 (11), the department shall issue a mining permit if it finds all of
16the following:
SB488-SSA2,111,1817 1. That the mining plan and reclamation plan are reasonably certain to result
18in reclamation of the mining site consistent with this subchapter.
SB488-SSA2,111,2019 2. That the waste site feasibility study and plan of operation complies with s.
20295.51.
SB488-SSA2,111,2221 3. That the applicant has committed to conducting the proposed mining in
22compliance with the mining permit and any other approvals issued for the mining.
SB488-SSA2,112,223 3m. That the proposed mining is likely to meet or exceed the regulations that
24apply to municipal floodplain zoning ordinances contained in the uniform rules

1promulgated by the department for preparation and implementation of municipal
2floodplain zoning ordinances.
SB488-SSA2,112,43 4. That the proposed mining is not likely to result in substantial adverse
4impacts to public health, safety, or welfare.
SB488-SSA2,112,65 5. That the proposed mining will result in a net positive economic impact in the
6area reasonably expected to be most impacted by the mining.
SB488-SSA2,112,87 6. That the applicant has applied for all necessary zoning approvals applicable
8to the proposed mining.
SB488-SSA2,112,189 (b) The department shall approve or deny an application for a mining permit
10in writing and shall include the reasons for its decision with clarity and in detail.
11The department may modify the applicant's proposed mining plan, reclamation plan,
12or mining waste site feasibility study and plan of operation in order to meet the
13requirements of this subchapter, and, as modified, approve the application. The
14approval of the application for a mining permit constitutes the approval of the
15mining plan, reclamation plan, and waste site feasibility study and plan of operation.
16In its decision on the application for a mining permit, the department shall include
17a final decision on compliance with s. 1.11 and the requirements of s. 295.53,
18discussing all of the following:
SB488-SSA2,112,2019 1. Whether the department has considered the environmental impact
20statement and comments received on it.
SB488-SSA2,112,2121 2. Whether the department has complied with ss. 1.11 and 295.53.
SB488-SSA2,112,2422 3. Whether, consistent with social, economic, and other essential
23considerations, the department has adopted all practicable means within its
24authority to avoid or minimize any harm to the environment and, if not, why not.
SB488-SSA2,113,2
1(2) Criteria for denial. The department shall deny the mining permit if it
2finds any of the following:
SB488-SSA2,113,33 (a) That the site is unsuitable for mining.
SB488-SSA2,113,54 (b) That the proposed mining may reasonably be expected to create any of the
5following situations:
SB488-SSA2,113,96 1. Hazards resulting in irreparable, substantial physical damage to any of the
7following that cannot be prevented under the requirements of this subchapter,
8avoided to the extent practicable by removal from the area of hazard, or mitigated
9by purchase or by obtaining the consent of the owner:
SB488-SSA2,113,1010 a. A dwelling house.
SB488-SSA2,113,1111 b. A public building.
SB488-SSA2,113,1212 c. A school.
SB488-SSA2,113,1313 d. A church.
SB488-SSA2,113,1414 e. A cemetery.
SB488-SSA2,113,1515 f. A commercial or institutional building.
SB488-SSA2,113,1616 g. A public road.
SB488-SSA2,113,2117 2. Irreparable substantial environmental damage to lake or stream bodies
18despite adherence to the requirements of this subchapter. This subdivision does not
19apply to an activity that the department has authorized under statute, except that
20the destruction or filling in of a lake bed may not be authorized unless it is authorized
21under s. 295.60, 295.605, or 295.61.
SB488-SSA2,113,2422 3. Landslides or substantial deposition from the proposed mining operation in
23stream or lake beds which cannot feasibly be prevented and which have not been
24authorized under s. 295.60 or 295.605.
SB488-SSA2,114,2
1(c) That the applicant has violated, and continues to fail to comply with, this
2subchapter.
SB488-SSA2,114,83 (d) Subject to sub. (3), that the applicant, principal shareholder of the
4applicant, or a related person has within 10 years before the application is submitted
5forfeited a mining reclamation bond that was posted in accordance with a permit or
6other authorization for a mining operation in the United States, unless the forfeiture
7was by agreement with the entity for whose benefit the bond was posted and the
8amount of the bond was sufficient to cover all costs of reclamation.
SB488-SSA2,114,139 (e) Subject to sub. (3), that the applicant, a related person, or an officer or
10director of the applicant has, within 10 years before the application is submitted,
11been convicted of more than one felony for violations of laws for the protection of the
12natural environment arising out of the operation of a mining site in the United
13States, unless one of the following applies:
SB488-SSA2,114,1414 1. The person convicted has been pardoned for all of the felonies.
SB488-SSA2,114,1615 2. The person convicted is a related person or an officer or director of the
16applicant with whom the applicant terminates its relationship.
SB488-SSA2,114,1917 3. The applicant included in its permit application under s. 295.47 a plan to
18prevent the occurrence in this state of events similar to the events that directly
19resulted in the convictions.
SB488-SSA2,114,2420 (f) Subject to sub. (3), that the applicant or a related person has, within 10 years
21before the application is submitted, declared bankruptcy or undergone dissolution
22that resulted in the failure to reclaim a mining site in the United States in violation
23of a state or federal law and that failure has not been remedied and is not being
24remedied.
SB488-SSA2,115,5
1(g) Subject to sub. (3), that, within 10 years before the application is submitted,
2a mining permit or other authorization for mining issued to the applicant or a related
3person was permanently revoked because of a failure to reclaim a mining site in the
4United States in violation of state or federal law and that failure has not been and
5is not being remedied.
SB488-SSA2,115,13 6(3) Exception from denial criteria. The department may not deny a mining
7permit under sub. (2) (d) to (g) if the person subject to the convictions, forfeiture,
8permanent revocation, bankruptcy, or dissolution is a related person but the
9applicant shows that the person was not the parent corporation of the applicant, a
10person that holds more than a 30 percent ownership in the applicant, or a subsidiary
11or affiliate of the applicant in which the applicant holds more than a 30 percent
12interest at the time of the convictions, forfeiture, permanent revocation, bankruptcy,
13or dissolution.
SB488-SSA2,115,16 14(4) Statement. The department shall send a statement as to whether the
15applicant has satisfied the requirements of this subchapter to the applicant and to
16the other persons specified in s. 295.57 (4) (b) 1. to 9.
SB488-SSA2,115,18 17(5) Duration of approvals. (a) A mining permit is valid for the life of the
18mining project, subject to the enforcement provisions under s. 295.79.
SB488-SSA2,115,2019 (b) An approval under s. 295.60 or 295.61 remains valid for the life of the
20mining, subject to the enforcement provisions under s. 295.79.
SB488-SSA2,115,2421 (c) An approval issued for a mining project under ch. 23, 29, 30, 169, 281, 283,
22285, 289, or 291, except for a permit under ch. 283 or 285 that is subject to a federal
23requirement limiting its duration, remains valid for the life of the mining project,
24subject to the enforcement provisions applicable to the approval.
SB488-SSA2,116,2
1(6) Effective date of approvals. A mining permit and any other approval is
2issued upon mailing and is final and effective upon issuance.
Loading...
Loading...