ATCP 93.400(11)(b) (b) Availability of records.
ATCP 93.400(11)(b)1.1. Operators shall maintain the required records at the site, except as provided in subds. 2. and 3., and par. (c) 9.
ATCP 93.400(11)(b)2. 2. Operators of unattended sites shall make the records available for inspection at the site when given 72 hours of prior notice.
ATCP 93.400(11)(b)3. 3. The approved plans and specifications and approval letter shall be kept on site and available to the authorized agent or the department during all phases of installation. After installation is completed, the approved plans and specifications and approval letter shall be made available to the authorized agent or the department upon request.
ATCP 93.400(11)(b)4. 4. Records may be kept electronically, provided they are in a format acceptable to the department.
ATCP 93.400(11)(c) (c) Maintenance of records. Records shall be maintained for the following periods from the date of the most recent test, inspection or upgrade:
ATCP 93.400(11)(c)1. 1. Monthly leak detection monitoring for underground piping — one year.
ATCP 93.400(11)(c)2. 2. Annual precision tightness testing for underground piping — one year.
ATCP 93.400(11)(c)3. 3. Impressed current corrosion protection system, 60-day inspection — the previous 3 inspections.
ATCP 93.400(11)(c)4. 4. Corrosion protection system, annual test — the previous 3 tests.
ATCP 93.400(11)(c)5. 5. Annual performance verification of leak detection equipment and flow restrictor, for underground piping — 2 years.
ATCP 93.400(11)(c)6. 6. Results of functional testing of impact and emergency shutoff valves and electrical continuity testing for dispensers — 2 years.
ATCP 93.400(11)(c)7. 7. The owner's manual provided by the leak detection equipment manufacturer — until the leak detection system is replaced or no longer used.
ATCP 93.400(11)(c)8. 8. Any tank or pipe system modification or repair — the operational life of the system.
ATCP 93.400(11)(c)9. 9. Inspection or testing records — 3 years or the interval between required inspections or testing, whichever is longer.
ATCP 93.400(11)(c)10. 10. Tank-system site assessments and other environmental assessments, such as assessments for property transactions — 3 years after completion of any permanent closure, upgrade, repair, or change in service. These records shall be maintained at one of the following locations:
ATCP 93.400(11)(c)10.a. a. With the owner or operator who took the AST system out of service.
ATCP 93.400(11)(c)10.b. b. With the current operator of the AST system site.
ATCP 93.400(11)(c)10.c. c. With the department if records cannot be maintained at the closed facility.
ATCP 93.400(11)(c)11. 11. Leak detection alarm investigation — 2 years.
ATCP 93.400 Note Note: All leak detection records should be retained. The documentation could be helpful to exclude the site as a possible source of contamination at a later date.
ATCP 93.400(11)(c)12. 12. One set of stamped, approved plans and specifications and a copy of the approval letter — the operational life of the system.
ATCP 93.400(11)(c)13. 13. Equipment or component compatibility for ethanol or biodiesel blends under s. ATCP 93.680 (3) (c) 1. or (6) (c) 1. — the operational life of the equipment or component.
ATCP 93.400(12) (12)Tanks at remediation sites.
ATCP 93.400(12)(a)1.1. Recovery systems using oil water separators or recovery systems pumping free product at the rate of 60 gallons or more per week shall comply with this paragraph.
ATCP 93.400(12)(a)2. 2. Recovery product piping and storage tanks shall comply with either the plan review requirements in s. ATCP 93.100 or the design and construction requirements in s. ATCP 93.350 (2) for hazardous substances.
ATCP 93.400(12)(a)3. 3. Tanks shall be registered in accordance with s. ATCP 93.140.
ATCP 93.400(12)(a)4. 4. Tank construction and marking shall comply with ss. ATCP 93.250 and 93.400 (7).
ATCP 93.400(12)(b) (b) Tanks used in recovery systems that pump free product at the rate of less than 60 gallons per week shall be constructed and marked in accordance with ss. ATCP 93.250 and 93.400 (7).
ATCP 93.400 History History: CR 17-092: cr. Register October 2019 No. 766, eff. 11-1-19; correction in (5) (b) 2. made under s. 13.92 (4) (b) 14., Stats., and correction in (8) (c) 1. made under s. 35.17, Stats., Register October 2019 No. 766.
ATCP 93.410 ATCP 93.410Spill and overfill prevention.
ATCP 93.410(1)(a) (a) All aboveground storage tanks, whether new or existing, shall have a means of overfill prevention which consists of either a visual gauge, an audible or visual alarm, or a pump shutdown that activates at 90 percent of the tank's capacity, and which complies with any other applicable requirements in this section.
ATCP 93.410(1)(b) (b) Prior to delivery, the operator of the product delivery equipment that is transferring the product shall ensure that the volume available in the tank is greater than the volume of product to be transferred to the tank.
ATCP 93.410(2) (2) The transfer operation shall be monitored constantly by the operator of the delivery equipment so as to prevent overfilling and spilling.
ATCP 93.410(3) (3) Equipment shall be clearly marked so visual and audible warning signals are recognizable to the delivery person.
ATCP 93.410(4) (4) Spill and overflow prevention equipment shall be maintained to work as originally designed and installed.
ATCP 93.410(5) (5) The fill opening shall be separate from the vent opening.
ATCP 93.410(6)(a) (a) All aboveground storage tanks, whether new or existing, with the fill point not located within a diked area shall be provided with a catch basin or similar containment, except for tanks exempted by par. (d) and tanks that are exempted from secondary containment by s. ATCP 93.420 (1) (a) to (c).
ATCP 93.410(6)(b) (b) The catch basin or similar containment to contain spillage at the fill point shall have a minimum liquid capacity of 5 gallons, except where the catch basin or similar containment was installed before February 1, 2009.
ATCP 93.410(6)(c) (c) The basin shall be equipped with a method to remove product or a drain system that directs spilled product into the tank.
ATCP 93.410(6)(d) (d) The following tanks are exempt from par. (a):
ATCP 93.410(6)(d)1. 1. Tanks provided with controls before February 1, 2009, that comply with this subsection.
ATCP 93.410(6)(d)2. 2. Tanks filled with a manual-shutoff nozzle without a latch-open device.
ATCP 93.410 Note Note: The “controls” referred to in this subdivision may be something other than a mechanical device. In other words, they are anything that will reliably prevent a loss of product at the fill point from reaching the environment.
ATCP 93.410(6)(d)3. 3. Tanks filled with a tight-connect with either a dry break connection or a manual shutoff valve on the hose-end connection.
ATCP 93.410(7) (7) Aboveground tanks that are filled via handheld nozzles shall be constantly attended during product delivery and shall be provided with overfill prevention equipment which notifies the person filling the tank, with either an audible or a visual signal that the liquid level has reached 90 percent of the tank's capacity.
ATCP 93.410(8) (8) Tanks located remote from the fill point, that are filled only with a manual shutoff nozzle without a latching mechanism shall be provided with overfill prevention equipment which notifies the person filling the tank, with both an audible and a visual signal, that the liquid level has reached 90 percent of the tank's capacity.
ATCP 93.410(9)(a) (a) Any of the following new aboveground double-wall tanks storing Class IIIB products shall be provided with overfill prevention equipment which notifies the person filling the tank, with both an audible and a visual signal, that the liquid level has reached 90 percent of the tank's capacity:
ATCP 93.410(9)(a)1. 1. Tanks using tight-connect delivery.
ATCP 93.410(9)(a)2. 2. Tanks located remote from the fill point.
ATCP 93.410(9)(b) (b) Any of the following existing aboveground double-wall tanks storing Class IIIB products shall be provided with overfill prevention equipment which notifies the person filling the tank, with both an audible and a visual signal, that the liquid level has reached 90 percent of the tank's capacity:
ATCP 93.410(9)(b)1. 1. Tanks using tight-connect delivery.
ATCP 93.410(9)(b)2. 2. Tanks located remote from the fill point that use delivery nozzles with latch-open devices.
ATCP 93.410(10)(a) (a) Any of the following double-wall aboveground tanks that are installed on or after November 1, 2019, shall be provided with overfill prevention equipment which notifies the person filling the tank, with both an audible and a visual signal, that the liquid level has reached 90 percent of the tank's capacity, and which automatically shuts off flow when the quantity of liquid in the tank reaches 95 percent of the tank's capacity, except this requirement does not apply to the tanks addressed in sub. (9) (a):
ATCP 93.410(10)(a)1. 1. Tanks using tight-connect delivery.
ATCP 93.410(10)(a)2. 2. Tanks located remote from the fill point that use delivery nozzles with latch-open devices.
ATCP 93.410(10)(b) (b) Any of the following existing aboveground double-wall tanks shall be provided with overfill prevention equipment which notifies the person filling the tank, with both an audible and a visual signal, that the liquid level has reached 90 percent of the tank's capacity, and which automatically shuts off flow when the quantity of liquid in the tank reaches 95 percent of the tank's capacity, except this requirement does not apply to the tanks addressed in sub. (9) (b):
ATCP 93.410(10)(b)1. 1. Tanks using tight-connect delivery.
ATCP 93.410(10)(b)2. 2. Tanks located remote from the fill point that use delivery nozzles with latch-open devices.
ATCP 93.410(11) (11) Any single-wall aboveground tank which is not addressed in subch. III and which either is existing by November 1, 2019, or is installed on or after that date shall be provided with overfill prevention equipment which notifies the person filling the tank, with both an audible and a visual signal, that the liquid level has reached 90 percent of the tank's capacity.
ATCP 93.410(12) (12) Overfill prevention equipment shall be tested before it is placed into service to ensure it is set to activate at the levels specified in this section and that it will activate when the contained liquid reaches those levels. This testing shall be performed in accordance with one of the following:
ATCP 93.410(12)(a) (a) Requirements developed by the manufacturer, if the manufacturer has developed testing requirements.
ATCP 93.410(12)(b) (b) An approved standard developed by a nationally recognized association or independent testing laboratory.
ATCP 93.410(12)(c) (c) Requirements determined by the department to be no less protective of human health and the environment than the requirements listed in this subsection.
ATCP 93.410(13)(a) (a) Operators shall utilize the procedures and equipment as specified in PEI RP600 for preventing overfilling of new and existing shop-built aboveground tanks.
ATCP 93.410(13)(b) (b) Fuel-delivery persons shall utilize the procedures in PEI RP600 for preventing overfilling of new and existing shop-built aboveground tanks, and may not interfere with equipment that is intended to prevent overfilling.
ATCP 93.410 Note Note: PEI RP600 does not mandate installation of equipment, but instead addresses how to effectively use the equipment that is provided, as required by other sections and referenced standards in this chapter.
ATCP 93.410 Note Note: Under ss. ATCP 93.470 and ATCP 93.585 (2) (b), fuel-delivery persons must immediately inform the owner or operator of any spilling or overfilling which occurs during the delivery procedure and which may result in or be a release. Requirements for the owner or operator to report, investigate, and clean up any spills and overfills are contained in ss. ATCP 93.575 to 93.585.
ATCP 93.410 Note Note: Overfill-prevention requirements for bulk plant tanks are in PEI RP800, and corresponding requirements for hazardous liquid tanks containing substances that are not flammable or combustible are in s. ATCP 93.350.
ATCP 93.410 Note Note: API RP 1007, Loading and Unloading of MC 306/DOT 406 Cargo Tank Motor Vehicles, is a guideline for use by truck drivers and other personnel that includes specific steps for unloading tank trucks into aboveground and underground tanks in a safe and efficient manner which protects the environment. It is available at http://publications.api.org.
ATCP 93.410 History History: CR 17-092: cr. Register October 2019 No. 766, eff. 11-1-19; correction in (6) (a) made under s. 35.17, Stats., and correction in (10) (a), (11) made under s. 13.92 (4) (b) 14., Stats., Register October 2019.
ATCP 93.420 ATCP 93.420Secondary containment.
ATCP 93.420(1)(1)Application. Aboveground storage tanks using secondary containment as a method of spill control shall comply with the secondary containment requirements in NFPA 30 section 22.11 and this section, except this requirement does not apply to any of the following tanks:
ATCP 93.420(1)(a) (a) Tanks covered in ss. ATCP 93.610 (1) to (3) and 93.630.
ATCP 93.420 Note Note: Sections ATCP 93.610 (1) to (3) and 93.630 cover tank wagons, movable tanks, tank vehicles, and aboveground farm tanks.
ATCP 93.420(1)(b) (b) Tanks storing Class IIIB liquids other than used oil.
ATCP 93.420 Note Note: Federal regulations, such as the Spill Prevention Control and Countermeasure requirements in 40 CFR part 112, may also apply to these tanks and be more restrictive but are not enforced by the department.
ATCP 93.420(1)(c) (c) Tanks storing Class IIIB liquids that are not in the same diked area as a tank containing Class I, II, or IIIA liquids.
ATCP 93.420(2) (2)Dike systems for tanks.
ATCP 93.420(2)(a) (a) Weather exposure. Where a dike system is used to provide secondary containment for a tank system that is exposed to the weather, the dike system shall be constructed in accordance with NFPA 30 section 22.11; ACI 350.2R, if concrete is used; and this subsection.
ATCP 93.420(2)(b) (b) Capacity. The capacity of a dike system open to the weather shall be 25 percent larger than required under NFPA 30 section 22.11.1.2 or 22.11.2.2.
ATCP 93.420(2)(c) (c) Construction. The walls and floor of the dike system shall be constructed of earth, solid masonry, steel, precast concrete, engineered poured concrete, or other materials approved by the department.
ATCP 93.420(2)(d) (d) Sealing. Dike systems with the walls and floor made of steel or poured or precast concrete shall have all cracks, seams, and joints sealed to be liquid-tight.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.