3) Promote drainage and minimize erosion or abrasion of the cover.
4) Accommodate settling and subsidence so that the cover’s integrity is maintained.
5) Have a permeability less than or equal to the permeability of any bottom liner system or natural subsoils present.
NR 664.0552(5)(f)4.b.b. The department may determine that modifications to the cap requirements of subd. 4. a. are needed to facilitate treatment or the performance of the CAMU (e.g., to promote biodegradation).
NR 664.0552(5)(f)5.5. Long-term care requirements as necessary to protect human health and the environment, to include, for areas where wastes will remain in place, monitoring and maintenance activities and the frequency with which the activities shall be performed to ensure the integrity of any cap, final cover or other containment system.
NR 664.0552(6)(6)In this section, “CAMUs that are used for storage or treatment only” means CAMUs in which wastes will not remain after closure. Those CAMUs shall be designated in accordance with all of the requirements of this section, except as follows.
NR 664.0552(6)(a)(a) CAMUs that are used for storage or treatment only and that operate according to the time limits established in the staging pile rules at s. NR 664.0554 (4) (a) 3., (8) and (9) are subject to the requirements for staging piles at s. NR 664.0554 (4) (a) 1. and 2. and (b), (5), (6), (10) and (11) in lieu of the performance standards and requirements for CAMUs in subs. (3) and (5) (c) to (f).
NR 664.0552(6)(b)(b) CAMUs that are used for storage or treatment only and that do not operate according to the time limits established in the staging pile rules at s. NR 664.0554 (4) (a) 3., (8) and (9):
NR 664.0552(6)(b)1.1. Shall operate in accordance with a time limit, established by the department, that is no longer than necessary to achieve a timely remedy selected for the waste.
NR 664.0552(6)(b)2.2. Are subject to the requirements for staging piles at s. NR 664.0554 (4) (a) 1. and 2. and (b), (5), (6), (10) and (11) in lieu of the performance standards and requirements for CAMUs in subs. (3) and (5) (d) and (f).
NR 664.0552(7)(7)CAMUs into which wastes are placed where all wastes have constituent levels at or below remedial levels or goals applicable to the site do not have to comply with the requirements for liners at sub. (5) (c) 1., caps at sub. (5) (f) 4., groundwater monitoring requirements at sub. (5) (e) or, for treatment or storage-only CAMUs, the design standards at sub. (6).
NR 664.0552(8)(8)The department shall provide public notice and a reasonable opportunity for public comment before designating a CAMU. The notice shall include the rationale for any proposed adjustments under sub. (5) (d) 5. to the treatment standards in sub. (5) (d) 4.
NR 664.0552(9)(9)Notwithstanding any other provision of this section, the department may impose additional requirements as necessary to protect human health and the environment.
NR 664.0552(10)(10)Incorporation of a CAMU into an existing license shall be approved by the department according to the procedures for department-initiated license modifications under s. NR 670.041, or according to the license modification procedures of s. NR 670.042.
NR 664.0552(11)(11)The designation of a CAMU does not change the department’s existing authority to address clean-up levels, media-specific points of compliance to be applied to remediation at a facility or other remedy selection decisions.
NR 664.0552 HistoryHistory: CR 05-032: cr. Register July 2006 No. 607, eff. 8-1-06; correction in (1) (c) 2. to 4. made under s. 13.92 (4) (b) 7., Stats., Register July 2017 No. 739, eff. 8-1-17; CR 19-082: am. (1) Register August 2020 No 776, eff. 9-1-20.
NR 664.0553NR 664.0553Temporary units (TUs).
NR 664.0553(1)(1)For temporary tanks and container storage areas used to treat or store hazardous remediation wastes during remedial activities required under s. NR 664.0101, ss. 291.37 and 291.97 (1), Stats., or 42 USC 6928 (h) or at a licensed facility that is not subject to s. NR 664.0101, the department may designate a unit at the facility as a temporary unit. A temporary unit shall be located within the contiguous property under the control of the owner or operator where the wastes to be managed in the temporary unit originated. For temporary units, the department may replace the design, operating or closure standard applicable to these units under this chapter or ch. NR 665 with alternative requirements which protect human health and the environment.
NR 664.0553(2)(2)Any temporary unit to which alternative requirements are applied in accordance with sub. (1) shall be all of the following:
NR 664.0553(2)(a)(a) Located within the facility boundary.
NR 664.0553(2)(b)(b) Used only for treatment or storage of remediation wastes.
NR 664.0553(3)(3)In establishing standards to be applied to a temporary unit, the department shall consider all of the following factors:
NR 664.0553(3)(a)(a) Length of time the unit will be in operation.
NR 664.0553(3)(b)(b) Type of unit.
NR 664.0553(3)(c)(c) Volumes of wastes to be managed.
NR 664.0553(3)(d)(d) Physical and chemical characteristics of the wastes to be managed in the unit.
NR 664.0553(3)(e)(e) Potential for releases from the unit.
NR 664.0553(3)(f)(f) Hydrogeological and other relevant environmental conditions at the facility which may influence the migration of any potential releases.
NR 664.0553(3)(g)(g) Potential for exposure of humans and environmental receptors if releases were to occur from the unit.
NR 664.0553(4)(4)The department shall specify in the license or order the length of time a temporary unit will be allowed to operate, to be no longer than a period of one year. The department shall also specify the design, operating and closure requirements for the unit.
NR 664.0553(5)(5)The department may extend the operational period of a temporary unit once for no longer than a period of one year beyond that originally specified in the license or order, if the department determines that all of the following apply:
NR 664.0553(5)(a)(a) Continued operation of the unit will not pose a threat to human health and the environment.
NR 664.0553(5)(b)(b) Continued operation of the unit is necessary to ensure timely and efficient implementation of remedial actions at the facility.
NR 664.0553(6)(6)Incorporation of a temporary unit or a time extension for a temporary unit into an existing license shall be any of the following:
NR 664.0553(6)(a)(a) Approved in accordance with the procedures for department-initiated license modifications under s. NR 670.041.
NR 664.0553(6)(b)(b) Requested by the owner or operator as a class II modification according to the procedures under s. NR 670.042.
NR 664.0553(7)(7)The department shall document the rationale for designating a temporary unit and for granting time extensions for temporary units and shall make the documentation available to the public.
NR 664.0553 HistoryHistory: CR 05-032: cr. Register July 2006 No. 607, eff. 8-1-06; CR 19-082: am. (1) Register August 2020 No 776, eff. 9-1-20.
NR 664.0554NR 664.0554Staging piles. This section is written in a special format to make it easier to understand the rule requirements. Like other department rules, this section establishes enforceable legal requirements. In this section, “I” and “you” refer to the owner or operator.
NR 664.0554(1)(1)What is a staging pile? A staging pile is an accumulation of solid, non-flowing remediation waste (as defined in s. NR 660.10) that is not a containment building and is used only during remedial operations for temporary storage at a facility. A staging pile shall be located within the contiguous property under the control of the owner or operator where the wastes to be managed in the staging pile originated. The department shall designate staging piles according to the requirements in this section. For the purposes of this section, “storage” includes mixing, sizing, blending or other similar physical operations as long as they are intended to prepare the wastes for subsequent management or treatment.
NR 664.0554(2)(2)When may i use a staging pile? You may use a staging pile to store hazardous remediation waste (or remediation waste otherwise subject to land disposal restrictions) only if you follow the standards and design criteria the department has designated for that staging pile. The department shall designate the staging pile in a license or, at an interim license facility, in a license, closure plan or order (consistent with s. NR 670.072 (1) (e) and (2) (e)). The department shall establish conditions in the license, closure plan or order that comply with subs. (4) to (11).
NR 664.0554(3)(3)What information must i provide to get a staging pile designated? When seeking a staging pile designation, you shall provide all of the following:
NR 664.0554(3)(a)(a) Sufficient and accurate information to enable the department to impose standards and design criteria for your staging pile according to subs. (4) to (11).
NR 664.0554(3)(b)(b) Certification by a qualified professional engineer for technical data, such as design drawings and specifications, and engineering studies, unless the department determines, based on information that you provide, that this certification is not necessary to ensure that a staging pile will protect human health and the environment.
NR 664.0554(3)(c)(c) Any additional information the department determines is necessary to protect human health and the environment.
NR 664.0554(4)(4)What performance criteria must a staging pile satisfy? The department shall establish the standards and design criteria for the staging pile in the license, closure plan or order.
NR 664.0554(4)(a)(a) The standards and design criteria shall comply with all of the following:
NR 664.0554(4)(a)1.1. The staging pile shall facilitate a reliable, effective and protective remedy.
NR 664.0554(4)(a)2.2. The staging pile shall be designed so as to prevent or minimize releases of hazardous wastes and hazardous constituents into the environment, and minimize or adequately control cross-media transfer, as necessary to protect human health and the environment (for example, through the use of liners, covers, run-off or run-on controls, as appropriate).
NR 664.0554(4)(a)3.3. The staging pile may not operate for more than 2 years, except when the department grants an operating term extension under sub. (9). You shall measure the 2-year limit, or other operating term specified by the department in the license, closure plan or order, from the first time you place remediation waste into a staging pile. You shall maintain a record of the date when you first placed remediation waste into the staging pile for the life of the license, closure plan, or order, or for 3 years, whichever is longer.
NR 664.0554(4)(b)(b) In setting the standards and design criteria, the department shall consider all of the following factors:
NR 664.0554(4)(b)1.1. Length of time the pile will be in operation.
NR 664.0554(4)(b)2.2. Volumes of wastes you intend to store in the pile.
NR 664.0554(4)(b)3.3. Physical and chemical characteristics of the wastes to be stored in the unit.
NR 664.0554(4)(b)4.4. Potential for releases from the unit.
NR 664.0554(4)(b)5.5. Hydrogeological and other relevant environmental conditions at the facility that may influence the migration of any potential releases.
NR 664.0554(4)(b)6.6. Potential for human and environmental exposure to potential releases from the unit.
NR 664.0554(5)(5)May a staging pile receive ignitable or reactive remediation waste? You may not place ignitable or reactive remediation waste in a staging pile unless par. (a) or (b) applies:
NR 664.0554(5)(a)(a) You have treated, rendered or mixed the remediation waste before you placed it in the staging pile so that both of the following apply:
NR 664.0554(5)(a)1.1. The remediation waste no longer meets the definition of ignitable or reactive under s. NR 661.0021 or 661.0023.
NR 664.0554(5)(a)2.2. You have complied with s. NR 664.0017 (2).
NR 664.0554(5)(b)(b) You manage the remediation waste to protect it from exposure to any material or condition that may cause it to ignite or react.
NR 664.0554(6)(6)How do i handle incompatible remediation wastes in a staging pile? The term “incompatible waste” is defined in s. NR 660.10. You shall comply with all of the following requirements for incompatible wastes in staging piles:
NR 664.0554(6)(a)(a) You may not place incompatible remediation wastes in the same staging pile unless you have complied with s. NR 664.0017 (2).
NR 664.0554(6)(b)(b) If remediation waste in a staging pile is incompatible with any waste or material stored nearby in containers, other piles, open tanks or land disposal units (for example, surface impoundments), you shall separate the incompatible materials, or protect them from one another by using a dike, berm, wall or other device.
NR 664.0554(6)(c)(c) You may not pile remediation waste on the same base where incompatible wastes or materials were previously piled, unless the base has been decontaminated sufficiently to comply with s. NR 664.0017 (2).
NR 664.0554(7)(7)Are staging piles subject to the land disposal restrictions in ch. NR 668 and the minimum technological requirements? No. Placing hazardous remediation wastes into a staging pile does not constitute land disposal of hazardous wastes or create a unit that is subject to the minimum technological requirements in s. NR 664.0221, 664.0251, 664.0301, 665.0221, 665.0254 or 665.0301.
NR 664.0554 NoteNote: The original source for the minimum technological requirements is 42 USC 6924(o).
NR 664.0554(8)(8)How long may i operate a staging pile? The department may allow a staging pile to operate for up to 2 years after hazardous remediation waste is first placed into the pile. You shall use a staging pile no longer than the length of time designated by the department in the license, closure plan or order (the “operating term”), except as provided in sub. (9).
NR 664.0554(9)(9)May i receive an operating extension for a staging pile?
NR 664.0554(9)(a)(a) The department may grant one operating term extension of up to 180 days beyond the operating term limit contained in the license, closure plan or order (see sub. (12) for modification procedures). To justify to the department the need for an extension, you shall provide sufficient and accurate information to enable the department to determine that continued operation of the staging pile will do all of the following:
NR 664.0554(9)(a)1.1. Will not pose a threat to human health and the environment.
NR 664.0554(9)(a)2.2. Is necessary to ensure timely and efficient implementation of remedial actions at the facility.
NR 664.0554(9)(b)(b) The department may, as a condition of the extension, specify further standards and design criteria in the license, closure plan or order, as necessary, to ensure protection of human health and the environment.
NR 664.0554(10)(10)What is the closure requirement for a staging pile located in a previously contaminated area?
NR 664.0554(10)(a)(a) Within 180 days after the operating term of the staging pile expires, you shall close a staging pile located in a previously contaminated area of the site by removing or decontaminating all of the following:
NR 664.0554(10)(a)1.1. Remediation waste.
NR 664.0554(10)(a)2.2. Contaminated containment system components.
NR 664.0554(10)(a)3.3. Structures and equipment contaminated with waste and leachate.
NR 664.0554(10)(b)(b) You shall also decontaminate contaminated subsoils in a manner and according to a schedule that the department determines will protect human health and the environment.
NR 664.0554(10)(c)(c) The department shall include the requirements of pars. (a) and (b) in the license, closure plan or order in which the staging pile is designated.
NR 664.0554(11)(11)What is the closure requirement for a staging pile located in an uncontaminated area?
NR 664.0554(11)(a)(a) Within 180 days after the operating term of the staging pile expires, you shall close a staging pile located in an uncontaminated area of the site according to ss. NR 664.0258 (1) and 664.0111, or according to ss. NR 665.0258 (1) and 665.0111.
NR 664.0554(11)(b)(b) The department shall include the requirement of par. (a) in the license, closure plan or order in which the staging pile is designated.
NR 664.0554(12)(12)How may my existing license (for example, remediation variance), closure plan or order be modified to allow me to use a staging pile?
NR 664.0554(12)(a)(a) To modify a license, other than a remediation variance, to incorporate a staging pile or staging pile operating term extension, either:
NR 664.0554(12)(a)1.1. The department shall approve the modification under the procedures for department-initiated license modifications in s. NR 670.041.
NR 664.0554(12)(a)2.2. You shall request a class 2 modification under s. NR 670.042.
NR 664.0554(12)(b)(b) To modify a remediation variance to incorporate a staging pile or staging pile operating term extension, you shall resubmit the remediation variance application required under s. NR 670.079.