Hearing Date:   May 19, 2004
*On June 24, 2004, the Joint Committee for Review of Administrative Rules suspended this emergency rule.
3.   Rules adopted revising ch. NR 328, relating to shore erosion control of inland lakes and impoundments.
Finding of emergency
The emergency rule procedure, pursuant to s. 227.24, Stats., is necessary and justified in establishing rules to protect the public health, safety and welfare. The Wisconsin Legislature recently enacted 2003 Wisconsin Act 118, to streamline the regulatory process for activities in public trust waters. The state has an affirmative duty to administer the new law in a manner consistent with the public trust responsibilities of the State of Wisconsin under Article IX, Section I of the Wisconsin Constitution.
2003 Act 118 identifies certain activities that may be undertaken in public trust waters exempt from a permit, or under a general permit. Certain activities may not be undertaken in waters that are defined as “areas of special natural resource interest" or at other locations where the activity would cause detrimental impacts on public rights and interests in navigable waters. Without emergency rules to aid in administering the new law, the following severe problems will occur:
Until general permits are created by rule, any activity which is not exempt requires an individual permit with an automatic 30-day public notice. The required 30-day comment period will unnecessarily delay hundreds of construction projects that otherwise could go ahead with specified conditions for protecting lakes and streams (for example, all new riprap and culvert applications currently require public notices).
Unclear wording of exemptions currently puts property owners, contractors and consultants at risk of violation. Without clear procedures and standards established by emergency rule, many more people may request exemption determinations, slowing the decisions on individual permit applications.
Wording of exemptions and temporary grading jurisdiction puts lakes and streams at risk. Without standards as intended and described in the new law, exempted activities and grading along shorelines will cause inadvertent but permanent destruction of fish and wildlife habitat, loss of natural scenic beauty and reduced water quality. Rights of neighboring property owners may also be harmed. Cumulatively over one or two construction seasons, these impacts will have immediate and permanent effects on Wisconsin's water-based recreation and tourism industry.
To carry out the intention of the Legislature that 2003 Act 118 to speed decision-making but not diminish the public trust in state waters, these emergency rules are required to establish definitions, procedures and substantive standards for exemptions, general permits and jurisdiction under the new law.
Publication Date:   August 24, 2004
Effective Date:   August 24, 2004
Expiration Date:   January 21, 2005
Hearing Date:   September 28, 2004
Extension Through:   March 21, 2005
4.   Rules adopted revising ch. NR 329, relating to miscellaneous structures in navigable waterways.
Finding of emergency
The emergency rule procedure, pursuant to s. 227.24, Stats., is necessary and justified in establishing rules to protect the public health, safety and welfare. The Wisconsin Legislature recently enacted 2003 Wisconsin Act 118, to streamline the regulatory process for activities in public trust waters. The state has an affirmative duty to administer the new law in a manner consistent with the public trust responsibilities of the State of Wisconsin under Article IX, Section I of the Wisconsin Constitution.
2003 Act 118 identifies certain activities that may be undertaken in public trust waters exempt from a permit , or under a general permit. Certain activities may not be undertaken in waters that are defined as “areas of special natural resource interest" or at other locations where the activity would cause detrimental impacts on public rights and interests in navigable waters. Without emergency rules to aid in administering the new law, the following severe problems will occur:
Until general permits are created by rule, any activity which is not exempt requires an individual permit with an automatic 30-day public notice. The required 30-day comment period will unnecessarily delay hundreds of construction projects that otherwise could go ahead with specified conditions for protecting lakes and streams (for example, all new riprap and culvert applications currently require public notices).
Unclear wording of exemptions currently puts property owners, contractors and consultants at risk of violation. Without clear procedures and standards established by emergency rule, many more people may request exemption determinations, slowing the decisions on individual permit applications.
Wording of exemptions and temporary grading jurisdiction puts lakes and streams at risk. Without standards as intended and described in the new law, exempted activities and grading along shorelines will cause inadvertent but permanent destruction of fish and wildlife habitat, loss of natural scenic beauty and reduced water quality. Rights of neighboring property owners may also be harmed. Cumulatively over one or two construction seasons, these impacts will have immediate and permanent effects on Wisconsin's water-based recreation and tourism industry.
To carry out the intention of the Legislature that 2003 Act 118 to speed decision-making but not diminish the public trust in state waters, these emergency rules are required to establish definitions, procedures and substantive standards for exemptions, general permits and jurisdiction under the new law.
Publication Date:   August 24, 2004
Effective Date:   August 24, 2004
Expiration Date:   January 21, 2005
Hearing Date:   September 28, 2004
Extension Through:   March 21, 2005
5.   Rules adopted revising ch. NR 340, and creating ch. NR 343, relating to regulation of construction, dredging, and enlargement of an artificial water body.
Finding of emergency
The emergency rule procedure, pursuant to s. 227.24, Stats., is necessary and justified in establishing rules to protect the public health, safety and welfare. The Wisconsin Legislature recently enacted 2003 Wisconsin Act 118, to streamline the regulatory process for activities in public trust waters. The state has an affirmative duty to administer the new law in a manner consistent with the public trust responsibilities of the State of Wisconsin under Article IX, Section I of the Wisconsin Constitution.
2003 Act 118 identifies certain activities that may be undertaken in public trust waters exempt from a permit , or under a general permit. Certain activities may not be undertaken in waters that are defined as “areas of special natural resource interest" or at other locations where the activity would cause detrimental impacts on public rights and interests in navigable waters. Without emergency rules to aid in administering the new law, the following severe problems will occur:
Until general permits are created by rule, any activity which is not exempt requires an individual permit with an automatic 30-day public notice. The required 30-day comment period will unnecessarily delay hundreds of construction projects that otherwise could go ahead with specified conditions for protecting lakes and streams (for example, all new riprap and culvert applications currently require public notices).
Unclear wording of exemptions currently puts property owners, contractors and consultants at risk of violation. Without clear procedures and standards established by emergency rule, many more people may request exemption determinations, slowing the decisions on individual permit applications.
Wording of exemptions and temporary grading jurisdiction puts lakes and streams at risk. Without standards as intended and described in the new law, exempted activities and grading along shorelines will cause inadvertent but permanent destruction of fish and wildlife habitat, loss of natural scenic beauty and reduced water quality. Rights of neighboring property owners may also be harmed. Cumulatively over one or two construction seasons, these impacts will have immediate and permanent effects on Wisconsin's water-based recreation and tourism industry.
To carry out the intention of the Legislature that 2003 Act 118 to speed decision-making but not diminish the public trust in state waters, these emergency rules are required to establish definitions, procedures and substantive standards for exemptions, general permits and jurisdiction under the new law.
Publication Date:   August 24, 2004
Effective Date:   August 24, 2004
Expiration Date:   January 21, 2005
Hearing Date:   September 28, 2004
Extension Through:   March 21, 2005
6.   Rules adopted revising ch. NR 345, relating to dredging in navigable waterways.
Finding of emergency
The emergency rule procedure, pursuant to s. 227.24, Stats., is necessary and justified in establishing rules to protect the public health, safety and welfare. The Wisconsin Legislature recently enacted 2003 Wisconsin Act 118, to streamline the regulatory process for activities in public trust waters. The state has an affirmative duty to administer the new law in a manner consistent with the public trust responsibilities of the State of Wisconsin under Article IX, Section I of the Wisconsin Constitution.
2003 Act 118 identifies certain activities that may be undertaken in public trust waters exempt from a permit, or under a general permit. Certain activities may not be undertaken in waters that are defined as “areas of special natural resource interest" or at other locations where the activity would cause detrimental impacts on public rights and interests in navigable waters. Without emergency rules to aid in administering the new law, the following severe problems will occur:
Until general permits are created by rule, any activity which is not exempt requires an individual permit with an automatic 30-day public notice. The required 30-day comment period will unnecessarily delay hundreds of construction projects that otherwise could go ahead with specified conditions for protecting lakes and streams (for example, all new riprap and culvert applications currently require public notices).
Unclear wording of exemptions currently puts property owners, contractors and consultants at risk of violation. Without clear procedures and standards established by emergency rule, many more people may request exemption determinations, slowing the decisions on individual permit applications.
Wording of exemptions and temporary grading jurisdiction puts lakes and streams at risk. Without standards as intended and described in the new law, exempted activities and grading along shorelines will cause inadvertent but permanent destruction of fish and wildlife habitat, loss of natural scenic beauty and reduced water quality. Rights of neighboring property owners may also be harmed. Cumulatively over one or two construction seasons, these impacts will have immediate and permanent effects on Wisconsin's water-based recreation and tourism industry.
To carry out the intention of the Legislature that 2003 Act 118 to speed decision-making but not diminish the public trust in state waters, these emergency rules are required to establish definitions, procedures and substantive standards for exemptions, general permits and jurisdiction under the new law.
Publication Date:   August 24, 2004
Effective Date:   August 24, 2004
Expiration Date:   January 21, 2005
Hearing Date:   September 28, 2004
Extension Through:   March 21, 2005
7.   Rules adopted creating ch. NR 310, relating to procedures for exemptions, general permits and individual permits for activities in navigable waterways.
Finding of emergency
The emergency rule procedure, pursuant to s. 227.24, Stats., is necessary and justified in establishing rules to protect the public health, safety and welfare. The Wisconsin Legislature recently enacted 2003 Wisconsin Act 118, to streamline the regulatory process for activities in public trust waters. The state has an affirmative duty to administer the new law in a manner consistent with the public trust responsibilities of the State of Wisconsin under Article IX, Section I of the Wisconsin Constitution.
2003 Act 118 identifies certain activities that may be undertaken in public trust waters exempt from a permit, or under a general permit. Certain activities may not be undertaken in waters that are defined as “areas of special natural resource interest" or at other locations where the activity would cause detrimental impacts on public rights and interests in navigable waters. Without emergency rules to aid in administering the new law, the following severe problems will occur:
Until general permits are created by rule, any activity which is not exempt requires an individual permit with an automatic 30-day public notice. The required 30-day comment period will unnecessarily delay hundreds of construction projects that otherwise could go ahead with specified conditions for protecting lakes and streams (for example, all new riprap and culvert applications currently require public notices).
Unclear wording of exemptions currently puts property owners, contractors and consultants at risk of violation. Without clear procedures and standards established by emergency rule, many more people may request exemption determinations, slowing the decisions on individual permit applications.
Wording of exemptions and temporary grading jurisdiction puts lakes and streams at risk. Without standards as intended and described in the new law, exempted activities and grading along shorelines will cause inadvertent but permanent destruction of fish and wildlife habitat, loss of natural scenic beauty and reduced water quality. Rights of neighboring property owners may also be harmed. Cumulatively over one or two construction seasons, these impacts will have immediate and permanent effects on Wisconsin's water-based recreation and tourism industry.
Publication Date:   August 24, 2004
Effective Date:   August 24, 2004
Expiration Date:   January 21, 2005
Hearing Date:   September 28, 2004
Extension Through:   March 21, 2005
Public Instruction
Rules adopted repealing s. PI 24.02 (3) and repealing and recreating subchapter II of chapter PI 24, relating to the payment of state aid under the student achievement guarantee in education (SAGE) program.
Finding of emergency
The Department of Public Instruction finds an emergency exists and that a rule is necessary for the immediate preservation of the public welfare. A statement of the facts constituting the emergency is:
Section 118.43 (6m), Stats., requires the department to promulgate rules to implement and administer the payment of state aid under s. 118.43 (6), Stats. Because the next deadline for pupil reporting requirements occurs in January 2005, the rule must take effect as soon as possible to give eligible schools enough notice to meet such requirements.
Publication Date:   December 20, 2004
Effective Date:   December 20, 2004
Expiration Date:   May 19, 2005
Regulation and Licensing
Rules adopted creating ch. RL 150 to 154, relating to the licensure and regulation of athlete agents.
Exemption from finding of emergency
SECTION 4. Nonstatutory provisions of 2003 Wisconsin Act 150 states in part:
(2) The department of regulation and licensing may, using the procedure under section 227.24 of the statutes, promulgate the rules under section 440.9935 of the statutes, as created by this act, for the period before permanent rules become effective, but not to exceed the period authorized under section 227.24 (1) (c) and (2) of the statutes. Notwithstanding section 227.24 (1) (a), (2) (b), and (3) of the statutes, the department is not required to provide evidence that promulgating rules under this subsection as emergency rules is necessary for the preservation of the public peace, health, safety, or welfare and is not required to provide findings of emergency for rules promulgated under this subsection.
Analysis prepared by the Department of Regulation and Licensing
Statutes authorizing promulgation: s. 227.11 (2), Stats., and ss. 440.99, 440.991, 440.915, 440.992, 440.9925, 440.993, 440.9935, 440.994, 440.9945, 440.995, 440.9955, 440.996, 440.9975, 440.998 and 440.999, Stats., as created by 2003 Wisconsin Act 150.
Statutes interpreted: Chapter 440, Subchapter XII.
This emergency rule is promulgated pursuant to 2003 Wisconsin Act 150. This Act grants the Department of Regulation and Licensing the authority to create rules relating to the licensure and regulation of athlete agents.
In this order adopting emergency rules the Department of Regulation and Licensing creates rules relating to the licensure of athlete agents. These rules are as a result of 2003 Wisconsin Act 150 which enacted the Uniform Athlete Agents Act. Chapters RL 150 to 154 establish requirements and standards for registration and the practice of registered athlete agents. The rules specify the registration requirements for temporary and permanent registration, renewal requirements, and prohibited conduct for athlete agents.
SECTION 1 creates Chapter RL 150 which sets forth the statutory authority and the definitions for the proposed rules.
SECTION 2 creates Chapter RL 151 which sets forth the application process and requirements for an initial certificate of registration, including the application process for a temporary certificate of registration.
SECTION 3 creates Chapter RL 152 which sets forth the application process and requirements for renewal of a certificate of registration.
SECTION 4 creates Chapter RL 153 which outlines the standards of practice which apply to a credential holder.
SECTION 5 creates Chapter RL 154 which defines unprofessional conduct.
Loading...
Loading...
Links to Admin. Code and Statutes in this Register are to current versions, which may not be the version that was referred to in the original published document.