SB448,3,2 2101.148 Contractor notices. (1) Definitions. In this section:
SB448,3,33 (a) "Claimant" has the meaning given in s. 895.07 (1) (c).
SB448,3,84 (b) "Contractor" means a person that enters into a contract with a potential
5claimant to construct a dwelling on the potential claimant's land, to complete a
6remodeling project on a dwelling on the potential claimant's land, or to complete a
7remodeling project on the potential claimant's manufactured home. "Contractor"
8includes a subcontractor.
SB448,3,119 (c) "Dwelling" means any structure or part of a structure that is intended for
10use as a home, residence, or sleeping place by one or more persons maintaining a
11common household, to the exclusion of all others.
SB448,3,1212 (d) "Manufactured home" has the meaning given in s. 101.91 (2).
SB448,3,1313 (e) "Remodel" does not include maintenance and repair work.
SB448,3,1514 (f) "Supplier" means a person that manufactures or supplies windows or doors
15for a dwelling.
SB448,3,20 16(2) Notice required at time of contracting. (a) Upon entering into a contract
17to construct a dwelling, to complete a remodeling project on a dwelling, or to complete
18a remodeling project on a manufactured home, the contractor shall give the potential
19claimant, if any, a copy of the brochure prepared under s. 895.07 (12) and a notice
20worded substantially as follows:
SB448,3,2221 NOTICE CONCERNING CONSTRUCTION
22 DEFECTS
SB448,4,823 Wisconsin law contains important requirements you must follow before you
24may file a lawsuit for defective construction against the contractor who constructed
25your dwelling or completed your remodeling project or against window or door

1suppliers. For example, section 895.07 (2) and (3) of the Wisconsin statutes requires
2you to deliver to the contractor a written notice of any construction conditions you
3allege are defective before you file your lawsuit, and you must provide your
4contractor or window or door suppliers the opportunity to make an offer to repair or
5pay for the construction defects. You are not obligated to accept any offer made by
6the contractor or window or door suppliers, but failure to accept a reasonable offer
7may limit your recoverable damages. All parties are bound by applicable warranty
8provisions.
SB448,4,119 (b) The notice required under par. (a) shall be conspicuous and in writing and
10may be included within the contract between the contractor and the potential
11claimant.
SB448, s. 2 12Section 2. 895.07 of the statutes is created to read:
SB448,4,14 13895.07 Claims against contractors and suppliers. (1) Definitions. In this
14section:
SB448,4,1515 (a) "Action" means a civil action or an arbitration under ch. 788.
SB448,4,1716 (b) "Claimant" means a homeowner, other than a developer or builder, who
17asserts a claim against a contractor or supplier concerning a construction defect.
SB448,4,2218 (c) "Construction defect" has the meaning assigned by a written, express
19warranty provided by the contractor or, if no such meaning is assigned by warranty,
20means a deficiency in the specifications, planning, supervision, construction, or
21remodeling of a dwelling or in the remodeling of a manufactured home that results
22from any of the following:
SB448,4,2323 1. Defective material.
SB448,4,2424 2. Violation of applicable codes.
SB448,4,2525 3. Failure to follow accepted trade standards for workmanlike construction.
SB448,5,3
1(d) "Contractor" means a person including a subcontractor, that enters into a
2contract with a potential claimant to construct a dwelling or to complete a
3remodeling project on a dwelling or manufactured home.
SB448,5,64 (e) "Dwelling" means any structure or part of a structure that is intended for
5use as a home, residence, or sleeping place by one or more persons maintaining a
6common household, to the exclusion of all others.
SB448,5,77 (f) "Manufactured home" has the meaning given in s. 101.91 (2).
SB448,5,98 (g) "Serve" or "service" means personal service or delivery by certified mail,
9return receipt requested, to the last-known address of the addressee.
SB448,5,1110 (h) "Supplier" means a person that manufactures or supplies windows or doors
11for a dwelling.
SB448,5,1312 (j) "Working day" means any day except Saturday, Sunday, and holidays
13designated in s. 230.35 (4) (a).
SB448,5,20 14(2) Action; dismissal without prejudice. Before filing an action against a
15contractor or supplier for a construction defect, the claimant shall serve the
16contractor with a written notice of the claim that describes the claim in sufficient
17detail to determine the general nature of the construction defect. If the claimant files
18an action but fails to serve the notice of claim, the circuit court shall dismiss the
19action without prejudice, and the action may not be refiled until the claimant has
20complied with the requirements of this subsection.
SB448,6,7 21(3) Notice and opportunity to repair. (a) No later than 90 working days before
22initiating an action against a contractor or supplier under this section, the claimant
23shall serve written notice of claim under sub. (2) on the contractor. The notice of
24claim shall state that the claimant asserts a construction defect claim or claims and
25is providing notice under this paragraph. The notice of claim shall describe the claim

1or claims in sufficient detail to explain the nature of the alleged construction defect
2and the results of the construction defect. The claimant shall provide to the
3contractor all evidence the claimant knows or possesses, including expert reports,
4photographs, electronic mail, and videotapes that depict the nature and cause of the
5alleged construction defect. In addition, the claimant shall provide to the contractor
6any evidence discoverable under ch. 804 that depicts the nature and cause of the
7construction defect, including expert reports, photographs, and videotapes.
SB448,6,158 (b) Within 15 working days after the claimant serves notice of claim under par.
9(a), or within 25 working days if the contractor makes a claim for contribution from
10a supplier under sub. (9) (a), each contractor that has received the notice of claim may
11serve on the claimant, and on any other contractor that has received the notice of
12claim and on any supplier that has received a claim for contribution under sub. (9)
13(a), a written response to the claim or claims that either offers to settle the claim by
14monetary payment, the making of repairs, or a combination of both, without
15inspection, or proposes to inspect the dwelling that is the subject of the claim.
SB448,6,2316 (c) Within 15 working days after a supplier has received notice that a contractor
17is seeking contribution under sub. (9) (a), the supplier may serve the contractor with
18a written response that offers to settle the contribution claim by payment, by repair,
19or by both payment and repair without inspection or that offers to inspect the
20dwelling that is the subject of the contribution claim. If a contribution claim is made,
21the contractor shall forward all responses from the supplier to the claimant. The
22supplier and contractor shall use their best efforts to coordinate their responses to
23claims and contribution claims.
SB448,7,224 (d) If the contractor wholly rejects the claim and will neither remedy the alleged
25construction defect nor settle the claim, or does not respond to the claimant's notice

1of claim within the time under par. (b), the claimant may bring an action against the
2contractor for the claims described in the notice of claim without further notice.
SB448,7,113 (e) If the claimant rejects a settlement offer made by the contractor, the
4claimant shall provide written notice of the claimant's rejection to the contractor.
5The notice shall include the specific factual and, if known, legal reasons for the
6claimant's rejection of the contractor's proposal or offer. If the claimant believes that
7the settlement offer omits reference to any portion of the claim, or was unreasonable,
8the claimant shall in its written notice include those items that the claimant believes
9were omitted and set forth in detail all reasons why the claimant believes the
10settlement offer is unreasonable. The contractor shall forward the claimant's
11response to a supplier upon whom a contribution claim has been made.
SB448,8,812 (f) If a proposal for inspection is made under par. (b), the claimant shall, within
1315 working days of receiving the contractor's proposal, provide the contractor and
14any supplier on whom a contribution claim has been made and its agents, experts,
15and consultants prompt and complete access to the dwelling to inspect the dwelling,
16document any alleged construction defects, and perform any testing required to
17evaluate fully the nature, extent, and cause of the claimed construction defects and
18the nature and extent of any repairs or replacements that may be necessary to
19remedy them. If destructive testing is required, the contractor shall give the
20claimant and all persons on whom a notice of claim or contribution claim has been
21served advance notice of the testing at least 5 working days before commencement
22of the testing and shall, after completion of the testing, return the dwelling to its
23pre-testing condition. If any inspection or testing reveals a condition that requires
24additional testing to allow the contractor to evaluate fully the nature, cause, and
25extent of the construction defect, the contractor shall provide notice to the claimant

1and all persons on whom a notice of claim or contribution claim has been served of
2the need for the additional testing and the claimant shall provide access under this
3paragraph. If a claim is asserted on behalf of the owners of multiple dwellings, or
4multiple owners of units within a multifamily complex, then the contractor shall be
5entitled to inspect each of the dwellings or units. The claimant shall either provide
6a specific day for the inspection upon reasonable notice for an inspection or require
7the contractor to request in writing a day, at least 3 working days before the
8inspection.
SB448,8,119 (g) Within 10 working days following completion of the inspection and receipt
10of all testing results under par. (f), the contractor may serve on the claimant any of
11the following:
SB448,8,1512 1. A written offer to remedy fully or partially the construction defect at no cost
13to the claimant. The offer shall include a description of any additional construction
14necessary to remedy the construction defect and a timetable for the completion of the
15construction.
SB448,8,1616 2. A written offer to settle the claim by monetary payment.
SB448,8,1717 3. A written offer including a combination of repairs and monetary payment.
SB448,8,1918 4. A written statement that the contractor will not proceed further to remedy
19the construction defect.
SB448,9,320 (h) If a claimant accepts a contractor's offer made under par. (g) within 15
21working days after receipt of the offer, or if the offer is deemed accepted under par.
22(n), and the contractor does not proceed to make the monetary payment or remedy
23the construction defect within the agreed timetable, the claimant may bring an
24action against the contractor for the claim described in the notice of claim without
25further notice. The claimant may also file the contractor's offer and claimant's

1acceptance in the circuit court action, and the offer and acceptance creates a
2rebuttable presumption that a binding and valid settlement agreement has been
3created and should be enforced by the court.
SB448,9,74 (i) If a claimant receives a written statement that the contractor will not
5proceed further to remedy the construction defect, the claimant may bring an action
6against the contractor for the claim described in the notice of claim without further
7notice.
SB448,9,158 (j) If the claimant rejects the offer made by the contractor to remedy the
9construction defect or to settle the claim by monetary payment or a combination of
10each, the claimant shall serve written notice of the claimant's rejection on the
11contractor within 15 working days after receipt of the offer. The notice shall include
12the specific factual and, if known, legal reasons for the claimant's rejection of the
13contractor's offer. If the claimant believes the contractor's settlement offer is
14unreasonable, the claimant shall set forth in detail all reasons why the claimant
15believes the settlement offer is unreasonable.
SB448,9,1816 (k) Upon receipt of a claimant's rejection and the reasons for the rejection, the
17contractor may, within 5 working days after receiving the rejection, make a
18supplemental offer of repair or monetary payment to the claimant.
SB448,9,2519 (L) If the claimant rejects the supplemental offer made by the contractor under
20par. (k) to remedy the construction defect or to settle the claim by monetary payment
21or a combination of each, the claimant shall serve written notice of the claimant's
22rejection on the contractor within 15 working days after receipt of the supplemental
23offer. The notice shall include the specific factual and, if known, legal reasons for the
24claimant's rejection of the contractor's supplemental settlement offer. If the claimant
25believes the contractor's supplemental settlement offer is unreasonable, the

1claimant shall set forth in detail all reasons why the claimant believes the
2supplemental settlement offer is unreasonable. If the contractor declines to make
3a supplemental offer, or if the claimant rejects the supplemental offer, the claimant
4may bring an action against the contractor for the claim described in the notice of
5claim without further notice.
SB448,10,156 (m) If a claimant rejects a reasonable offer or reasonable supplemental offer
7made under this subsection, or does not permit the contractor to repair the
8construction defect pursuant to an accepted offer of settlement, the claimant may not
9recover an amount in excess of the fair market value of the offer of settlement, or the
10actual cost of the repairs made, whichever is less, or the amount of a monetary offer
11of settlement. For purposes of this paragraph, the trier of fact shall determine the
12reasonableness of an offer of settlement. If the claimant has rejected a reasonable
13offer or reasonable supplemental offer, and any other law allows the claimant to
14recover costs and attorney fees, then the claimant may recover no costs or attorney
15fees incurred after the date of its rejection.
SB448,10,2416 (n) A claimant accepting the offer of the contractor to remedy a construction
17defect shall do so by serving the contractor with a written notice of acceptance within
18a reasonable period of time after receipt of the contractor's settlement offer, but no
19later than 15 working days after receipt of the offer. If no response is served upon the
20contractor within the 15-working day period, then the offer shall be deemed
21accepted. If all requirements under this section have been fulfilled, and if the
22claimant has rejected any outstanding offers, the claimant may bring an action
23against the contractor for the claim described in the notice of claim without further
24notice.
SB448,11,5
1(o) If a claimant accepts a contractor's offer to repair a construction defect
2described in a notice of claim, the claimant shall provide the contractor and its
3agents, experts, and consultants prompt and unfettered access to the dwelling to
4perform and complete the construction by the timetable stated in the settlement
5offer.
SB448,11,116 (p) If, during the pendency of the notice, inspection, offer, acceptance, or repair
7process, an applicable limitation period would otherwise expire, the limitation
8period is tolled pending completion of the notice of claim process described in this
9section. This paragraph shall not be construed to revive a limitation period that has
10expired before the date on which a claimant's written notice of claim is served or
11extend any applicable statute of repose.
SB448,11,1412 (q) After the sending of the initial notice of claim and initial contribution claim,
13a claimant, a contractor, and a supplier may, by written mutual agreement, alter the
14procedure for the notice of claim process described in this section.
SB448,11,17 15(4) Contractor or supplier not liable for certain damages. In an action
16relating to a dwelling involving a construction defect, a contractor or supplier shall
17not be liable for damages involving or caused by any of the following:
SB448,11,1918 (a) Normal shrinkage due to drying or settlement of construction components
19within the tolerance of construction standards.
SB448,11,2220 (b) The contractor's or supplier's reliance on written information relating to the
21dwelling that was obtained from official government records or provided by a
22government entity.
SB448,11,2423 (c) Any construction defect known by or disclosed to a claimant in writing before
24his or her purchase of the dwelling.
SB448,11,2525 (d) Any construction defect in a dwelling that is purchased in "as is" condition.
SB448,12,3
1(e) If the claimant is not the first owner of the dwelling, any construction defect
2known by the claimant or that could have been discovered by the claimant through
3the exercise of reasonable diligence before the claimant's purchase of the dwelling.
SB448,12,54 (f) Refusal of anyone to allow the contractor or supplier or the contractor's or
5supplier's agents to perform their warranty service work.
SB448,12,8 6(5) Warranty terms. The claimant and contractor or supplier are bound by any
7contractor or supplier warranty terms pertaining to products or services supplied for
8the dwelling.
SB448,12,17 9(6) Additional construction defects and notice and opportunity to repair.
10A construction defect that is discovered after an initial claim or contribution claim
11notice has been provided may not be alleged in an action until the claimant or
12contractor has given the contractor or supplier who performed the original
13construction work or provided supplies written notice of the new claim or
14contribution claim regarding the alleged new construction defect based on the
15claimant's or contractor's most current records. The contractor or supplier shall have
16an opportunity to resolve the notice of the new claim or contribution claim in the
17manner provided in subs. (3) and (9).
SB448,12,25 18(7) Release; insurance. If a claimant or contractor accepts an offer made in
19compliance with this section and the contractor or supplier fulfills the offer in
20compliance with this section, an action brought by the claimant or contractor for the
21claim described in the notice of claim shall be dismissed with prejudice and the
22contractor or supplier is, for insurance purposes, legally obligated to make the
23repairs or the monetary payment as if the claimant or contractor had recovered a
24judgment against the contractor or supplier in the amount of the cost of the repairs
25or the amount of the monetary payment.
SB448,13,5
1(8) Action of associations. (a) In this subsection, "association" means a
2homeowner's association, condominium association under s. 703.02 (1m), unit
3owner's association, or a nonprofit corporation created to own and operate portions
4of a planned community that may assess unit owners for the costs incurred in the
5performance of the association's obligations.
SB448,13,106 (b) A person may not provide or offer to provide anything of value, directly or
7indirectly, to a property manager of an association or to a member or officer of an
8association to induce the property manager, member, or officer to encourage the
9association to file or discourage the association from filing a claim for damages
10arising from a construction defect.
SB448,13,1411 (c) A property manager retained by an association or a member or officer of an
12association may not accept anything of value, directly or indirectly, in exchange for
13encouraging to file or discouraging from filing a claim for damages on behalf of the
14association arising from a construction defect.
SB448,13,1615 (d) A person who knowingly violates par. (b) or (c) may be fined not more than
16$500 or imprisoned not more than 30 days, or both.
SB448,13,2017 (e) An association may bring an action against a contractor to recover damages
18resulting from construction defects in any of the common elements or limited
19common elements of a condominium, as defined in s. 703.02 (2) and (10). Such an
20action may be maintained only after all of the following occur:
SB448,13,2321 1. The association first obtains the written approval of each unit's owner whose
22interest in the common elements or limited common elements will be subject of the
23action.
SB448,13,2524 2. A vote is held of the units' owners to which at least a majority of the votes
25of the members of the association are allocated.
SB448,14,4
13. The full board of directors of the association and the contractor have met in
2person and conferred in a good faith attempt to resolve the association's claim, or the
3contractor has definitively declined or ignored the requests to meet with the board
4of directors of the association.
SB448,14,65 4. The association has otherwise satisfied all of the pre-action requirements
6for a claimant to commence an action under this section.
SB448,14,117 (f) At least 3 working days in advance of any vote to commence an action by an
8association to recover damages resulting from construction defects in any of the
9common elements or limited common elements of a condominium, the attorney
10representing the association shall provide to each unit's owner a written statement
11that includes, in reasonable detail all of the following:
SB448,14,1312 1. The construction defects and damages or injuries to the common elements
13or limited common elements.
SB448,14,1414 2. The cause of the construction defects, if the cause is known.
SB448,14,1615 3. The nature and the extent that is known of the damage or injury resulting
16from the construction defects.
SB448,14,1817 4. The location of each construction defect within the common elements or
18limited common elements, if known.
SB448,14,2019 5. A reasonable estimate of the cost of the action, including reasonable attorney
20fees and costs, expert fees, and the costs of testing.
SB448,14,2221 6. All disclosure that the unit owner is required to make upon the sale of the
22unit.
SB448,15,223 (g) An association or an attorney for an association may not employ a person
24to perform destructive tests to determine any damage or injury to a unit, common

1element, or limited common element caused by a construction defect unless all of the
2following are true:
SB448,15,33 1. The person has expertise in the testing.
SB448,15,64 2. The association has obtained the prior written approval of each unit's owner
5whose unit or interest in the common element or limited common element will be
6affected by the testing.
SB448,15,77 3. The person performing the tests has provided a written schedule for repairs.
SB448,15,98 4. The person performing the tests is required to repair all damage resulting
9from the tests in accordance with state laws and applicable local ordinances.
SB448,15,1110 5. The association or the person so employed obtains all permits required to
11conduct the tests and to repair any damage resulting from the tests.
SB448,15,1312 6. Reasonable prior notice and opportunity to observe the tests is given to the
13contractor against whom an action may be brought as a result of the tests.
SB448,15,1914 (h) An association may commence an action only upon a vote or written
15agreement of the owners of the units to which at least a majority of the votes of the
16members of the association are allocated. In such a case, the association shall
17provide written notice to the owner of each unit of the meeting at which the
18commencement of an action is to be considered or action is to be taken at least 15
19working days before the meeting.
SB448,15,2320 (i) The board of directors of an association may, without giving notice to the
21units' owners, employ a contractor and other persons necessary to make immediate
22repairs to a unit or common element within the condominium as are required to
23protect the health and safety of the units' owners.
SB448,16,12 24(9) Contribution. (a) A contractor may not seek contribution from a supplier
25for a claim that a claimant makes against the contractor unless the contractor

1provides the supplier with a written notice of the claimant's claim and the
2contribution claim within 5 working days after the contractor's receipt of the claim.
3The contractor shall explain the contribution claim in sufficient detail to explain the
4nature and results of the alleged construction defect. The contractor shall provide
5the supplier all evidence the contractor knows or possesses, including expert reports,
6photographs, electronic mail, and videotapes that depict the nature and cause of the
7alleged construction defect. In addition, the contractor shall provide to the supplier
8any evidence discoverable under ch. 804 that depicts the nature and cause of the
9alleged construction defect, including expert reports, photographs, and videotapes.
10The evidence provided to the supplier shall include all of the evidence provided to the
11contractor by the claimant. The contractor may not later use evidence in an action
12under this section that the contractor withholds or fails to produce.
SB448,16,1913 (b) Within 15 working days after a supplier has received notice that a contractor
14is seeking contribution under par. (a), the supplier may serve the contractor with a
15written response that offers to settle the contribution claim by payment, by repair,
16or by both payment and repair without inspection or that offers to inspect the
17dwelling that is the subject of the contribution claim. The contractor shall forward
18the supplier's response to the claimant. The supplier and contractor shall use their
19best efforts to coordinate their responses to claims and contribution claims.
SB448,16,2420 (c) If the supplier wholly rejects the contribution claim and will neither remedy
21the alleged construction defect nor settle the claim, or does not respond to the
22contractor's notice of contribution claim within the time under par. (b), the contractor
23may bring an action against the supplier for the claims described in the notice of
24contribution claim without further notice.
SB448,17,11
1(d) If the contractor rejects a settlement offer made by the supplier, the
2contractor shall provide written notice of the contractor's rejection to the supplier
3and, if the supplier is represented by legal counsel, the supplier's attorney. The
4notice shall include the specific factual and, if known, legal reasons for the
5contractor's rejection of the supplier's proposal or offer. If the contractor believes that
6the settlement offer omits reference to any portion of the claim, or was unreasonable,
7the contractor shall in its written notice include those items that the contractor
8believes were omitted and set forth in detail all reasons why the contractor believes
9the settlement offer is unreasonable. In any subsequent action in which the
10contractor asserts that the settlement offer was unreasonable, the contractor may
11not raise any reasons that were not included in its response to the supplier.
SB448,18,812 (e) If a supplier proposes to inspect the dwelling that is the subject of the
13contribution claim, the contractor and claimant shall, within 15 working days after
14receiving the supplier's proposal, provide the supplier and its agents, experts, and
15consultants prompt and complete access to the dwelling to inspect the dwelling,
16document any alleged construction defects, and perform any testing required to
17evaluate fully the nature, extent, and cause of the claimed construction defects and
18the nature and extent of any repairs or replacements that may be necessary to
19remedy them. If destructive testing is required, the supplier shall give the contractor
20and claimant and all persons on whom a notice of claim or contribution claim has
21been served advance notice of the testing at least 5 working days before
22commencement of the testing and shall, after completion of the testing, return the
23dwelling to its pre-testing condition. If any inspection or testing reveals a condition
24that requires additional testing to allow the supplier to evaluate fully the nature,
25cause, and extent of the construction defect, the supplier shall provide notice to the

1contractor and claimant and all persons on whom a notice of claim or contribution
2claim has been served of the need for the additional testing and the contractor and
3claimant shall provide access under this paragraph. If a claim is asserted on behalf
4of the contractor of multiple dwellings, or multiple owners of units within a
5multifamily complex, then the supplier shall be entitled to inspect each of the
6dwellings or units. The contractor and claimant shall either provide a specific day
7for the inspection upon reasonable notice for an inspection or require the supplier to
8request in writing a day, at least 3 working days before the inspection.
SB448,18,119 (f) Within 10 working days following completion of the inspection and receipt
10of all testing results under par. (e), the supplier may serve on the contractor any of
11the following:
SB448,18,1512 1. A written offer to remedy fully or partially the construction defect at no cost
13to the contractor. The offer shall include a description of any additional construction
14necessary to remedy the construction defect and an anticipated timetable for the
15completion of the construction.