SB1,126,2118
2. The exemption will result in significant adverse environmental impacts, but
19the applicant will offset those impacts through a mitigation program, as provided in
20s. 295.60 (8), through the measures provided in s. 295.605, or through the
21conservation measures provided in s. 295.61.
SB1,126,2322
(d) 1. The department shall deny a request for an exemption if granting the
23exemption would violate federal law.
SB1,127,424
2. If federal law imposes a standard for an exemption that differs from the
25standard in par. (c) and that cannot be modified by state law, and if that standard has
1been approved by the federal government for use by the state through a delegation
2agreement, federally approved state implementation plan, or other program
3approval, then the department shall determine whether to grant the request for the
4exemption using the federal standard.
SB1,127,6
5295.57 Application procedure. (1) Submission. (a) An applicant shall
6submit the application for a mining permit as provided in s. 295.47.
SB1,127,127
(b) The department shall protect as confidential any information, other than
8effluent data, contained in an application for a mining permit, upon a showing that
9the information is entitled to protection as a trade secret, as defined in s. 134.90 (1)
10(c), and any information relating to production or sales figures or to processes or
11production unique to the applicant or that would tend to adversely affect the
12competitive position of the applicant if made public.
SB1,127,19
13(2) Determination of administrative completeness. (a) The department shall
14review an application for a mining permit and, within 30 days after the application
15is submitted, shall determine either that the application is complete or that
16additional information is needed. If the department determines that the application
17is complete, the department shall notify the applicant in writing of that fact within
18the 30-day period and the date on which the department sends the notice is the day
19on which the application is administratively complete.
SB1,128,220
(b) If the department determines under par. (a) that an application is
21incomplete, the department shall notify the applicant in writing and may make one
22request for additional information during the 30-day period specified in par. (a).
23Within 10 days after receiving additional requested information from the applicant,
24the department shall notify the applicant in writing as to whether it has received all
25of the requested information. The day on which the department sends the 2nd notice
1under this paragraph is the day on which the application is administratively
2complete.
SB1,128,53
(c) If the department fails to meet the 30-day time limit under par. (a) or the
410-day time limit under par. (b), the application is administratively complete on the
5last day of the 30-day time limit or 10-day time limit.
SB1,128,96
(d) The department may request additional information needed to process a
7mining application from the applicant after the application is administratively
8complete, but the department may not delay the determination of administrative
9completeness based on a request for additional information.
SB1,128,13
10(3) Notice of additional approvals. Within 30 days after the mining permit
11is administratively complete under sub. (2), the department shall notify the
12applicant in writing of any approval required for the construction or operation of the
13mining site that was not previously identified by the department.
SB1,128,18
14(3m) Receipt of certain approvals. If a storm water discharge permit under
15s. 283.33 (1) (a) or a water quality certification under rules promulgated under subch.
16II of ch. 281 to implement
33 USC 1341 (a) is needed for a mining operation, the
17person applying for the mining permit may apply for and be issued the permit or
18certification.
SB1,128,21
19(4) Public information and notice. (a) The department shall make available
20for review in the city, village, or town in which the proposed mining site is located,
21information concerning the proposed mining, including all of the following:
SB1,128,2322
1. The application for the mining permit, including the mining plan,
23reclamation plan, and mining waste site feasibility study and plan of operation.
SB1,128,2424
2. Any of the following relating to an approval other than the mining permit:
SB1,128,2525
a. The application.
SB1,129,1
1b. A draft approval.
SB1,129,22
c. Information or summaries relating to the approval.
SB1,129,53
3. The environmental impact statement, environmental impact report, and any
4additional supporting information used in the department's evaluation of the
5proposed mining.
SB1,129,76
4. The department's analyses and preliminary determinations relating to any
7approval.
SB1,129,188
(b) The department shall distribute a notice that describes the availability of
9the information under par. (a); the opportunity for written public comment, including
10an invitation for the submission of written comments by any person within 45 days
11after the date of the publication of the notice; and the date, time, and location of the
12public informational hearing and that includes any additional information that a law
13concerning any approval requires to be provided. The department shall publish the
14notice as a class 1 notice under ch. 985 and shall publish notice on the department's
15Internet site. The date on which the department first publishes the notice on its
16Internet site shall be considered the date of the publication of the notice required to
17be published under this paragraph. The department shall also send the notice to all
18of the following:
SB1,129,2019
1. The clerk of any city, village, town, or county with zoning jurisdiction over
20the proposed mining site.
SB1,129,2221
2. The clerk of any city, village, town, or county within whose boundaries any
22portion of the proposed mining site is located.
SB1,129,2423
3. The clerk of any city, village, or town, contiguous to any city, village, or town
24within whose boundaries any portion of the proposed mining site is located.
SB1,130,3
14. The main public library of each city, village, town, or county with zoning
2jurisdiction over the proposed mining site or within whose boundaries any portion
3of the proposed mining site is located.
SB1,130,54
5. Any regional planning commission for the area within which the proposed
5mining site lies.
SB1,130,86
6. Any state agency that the department knows is required to grant a permit
7or other authorization necessary for the construction or operation of the proposed
8mining project.
SB1,130,129
7. The federal environmental protection agency, U.S. Army Corps of Engineers,
10and states potentially affected by the proposed discharge if a water discharge permit
11under ch. 283 or a wetland permit that constitutes a water quality certification as
12required by
33 USC 1341 (a) is to be considered at the public informational hearing.
SB1,130,1513
8. The federal environmental protection agency and appropriate agencies in
14other states that may be affected if an air pollution control permit under ch. 285 is
15to be considered at the public informational hearing.
SB1,130,1816
9. If a water withdrawal permit under s. 295.61 for a withdrawal of surface
17water is to be considered at the public informational hearing, the persons specified
18in s. 30.18 (4) (a).
SB1,130,2419
10. If an individual permit under s. 30.12 for a structure through which water
20transferred from the Great Lakes basin would be returned to the source watershed
21through a stream tributary to one of the Great Lakes is to be considered at the public
22informational hearing, the governing body of each city, village, and town through
23which the stream flows or that is adjacent to the stream downstream from the point
24at which the water would enter the stream.
SB1,131,3
111. Any person upon request. The department's notice under this subdivision
2may be given through an electronic notification system established by the
3department.
SB1,131,44
12. The applicant.
SB1,131,75
13. Any other person to whom the department is required to give notice of any
6proposed determination, application, or hearing concerning an approval under the
7laws relating to the issuance of any approval or under s. 1.11.
SB1,131,138
(c) The department shall coordinate the public comment period for the mining
9permit with the public comment period for any other approval for the mining
10operation, except that if an application for an approval is filed too late to allow public
11comment within the public comment period for the mining permit, the department
12shall issue separate notice, as described in par. (b), for the approval after the
13application is filed.
SB1,132,3
14(5) Informational hearing. The department shall hold a public informational
15hearing before it approves or denies an application for a mining permit and not less
16than 30 days after the date of the publication of the notice under sub. (4) (b). The
17department shall hold the public informational hearing in the county where the
18majority of the proposed mining site is located. The department shall hold a single
19public informational hearing covering the mining permit, all other approvals, and
20the environmental impact statement, except that if an application for an approval
21is filed too late to allow the application to be considered at the public informational
22hearing for the mining permit, the department shall hold a separate public
23informational hearing on the approval in the county where the majority of the
24proposed mining site is located not less than 30 days after the date of the publication
25of the notice under sub. (4) (b) for the approval. The public informational hearing
1under this subsection is not a contested case hearing under ch. 227. At the hearing,
2the department shall take testimony on all of the following with regard to any
3proposed withdrawal of groundwater or surface water:
SB1,132,54
(a) The public rights in any body of water and the related environment that may
5be injured by the proposed withdrawal of groundwater or surface water.
SB1,132,76
(b) The public benefits provided by increased employment, economic activity,
7and tax revenues from the proposed mining operation.
SB1,132,98
(c) The direct and indirect social and economic costs and benefits of the
9proposed mining operation.
SB1,132,1110
(d) Whether the proposed withdrawal of groundwater or surface water will
11consume nonsurplus water.
SB1,132,1212
(e) The rights of competing users of the groundwater or surface water.
SB1,132,1413
(f) Any other water withdrawal issues identified by the department as relevant
14to the decision of whether to issue or deny a permit.
SB1,132,18
15(6) Summary. After considering the comments received under subs. (4) and (5)
16and before acting on the application for the mining permit, the department shall
17prepare a summary of the comments and the department's response to the
18comments.
SB1,133,2
19(7) Deadline for acting on mining permit application. (a) No more than 420
20days after the day on which the application for a mining permit is administratively
21complete under sub. (2), the department shall approve the application, and issue a
22mining permit, or deny the application, in accordance with s. 295.58, unless the
23department and the applicant agree to extend the deadline. The department and the
24applicant may agree to not more than one extension and that extension may not
1exceed 60 days. The department and the applicant may enter into an extension only
2if one of the following applies:
SB1,133,43
1. An extension is necessary to enable the department and the U.S. Army Corps
4of Engineers to jointly prepare their environmental impact statements.
SB1,133,65
2. New information or a change to the mining proposal necessitates additional
6time to review the application.
SB1,133,97
(b) If the department does not comply with the deadline under par. (a),
8including any extension agreed to by the applicant, the department shall refund the
9fees under s. 295.73 (3) (a) and (d) that were paid by the applicant.
SB1,133,1610
(c) If the department does not comply with the deadline under par. (a),
11including any extension agreed to by the applicant, the applicant may bring an action
12for mandamus in the circuit court for the county in which the majority of the proposed
13mining site is located to compel the department to approve or deny the application.
14Notwithstanding s. 814.04 (1), in an action under this paragraph the court shall
15award the applicant its costs, including reasonable attorney fees, if it determines
16that the department did not comply with the deadline under par. (a).
SB1,133,22
17(8) Deadline for acting on other approvals. (a) Except as provided in par.
18(c), if an applicant files an application for an approval other than a mining permit
19no later than 60 days after the day on which the application for the mining permit
20is administratively complete under sub. (2), the department shall approve the
21application, and issue the approval, or deny the application no later than the
22deadline under sub. (7) (a), including any extension agreed to by the applicant.
SB1,134,423
(b) Except as provided in par. (c) if an applicant files an application for an
24approval other than a mining permit more than 60 days after the day on which the
25application for the mining permit is administratively complete under sub. (2), the
1deadline for acting on the application is extended beyond the deadline under sub. (7)
2(a), including any extension agreed to by the applicant, by the number of days beyond
3the 60th day after the day on which the application for the mining permit is
4administratively complete that the applicant files the application for the approval.
SB1,134,75
(c) The deadlines in pars. (a) and (b) do not apply to the application for an air
6pollution control permit under s. 285.62 for which the department receives an
7objection from the federal environmental protection agency under s. 285.62 (6).
SB1,134,118
(d) The department shall incorporate an approval other than a mining permit
9into a single document with the mining permit, unless the application for the
10approval was filed more than 60 days after the day on which the application for the
11mining permit is administratively complete under sub. (2).
SB1,134,17
12(8m) Submission of technical review to Great Lakes regional body. If an
13applicant files an application under s. 281.346 for an approval for a withdrawal of
14surface water or groundwater that is subject to regional review or council approval,
15the department shall provide its technical review, as defined in s. 281.346 (1) (u), to
16the regional body, as defined in s. 281.346 (1) (q), no later than 90 days after the
17applicant files the application for the approval.
SB1,135,2
18(9) Applicable procedure. The provisions of this section and ss. 295.58 (5) and
19(6) and 295.77 concerning public notice, comment, and hearing; issuance of
20department decisions; effective date of department decisions; and review of
21department decisions; and the duration of approvals apply to any approval,
22notwithstanding any provisions related to those matters in s. 44.40 or 169.25, subch.
23I or VI of ch. 77, ch. 23, 29, 30, 31, 169, 281, 283, 285, 289, or 291, or rules promulgated
24under those provisions, except as provided in s. 281.343 (7r) and except that if a
25withdrawal of surface water or groundwater is subject to regional review or council
1approval under s. 281.346, the applicable provisions related to regional review or
2council approval apply.
SB1,135,6
3295.58 Mining; department grant or denial of permit. (1) Criteria for
4approval. (a) Except as provided in sub. (2) and except with respect to property
5specified in s. 41.41 (11), the department shall issue a mining permit if it finds all of
6the following:
SB1,135,87
1. That the mining plan and reclamation plan are reasonably certain to result
8in reclamation of the mining site consistent with this subchapter.
SB1,135,109
2. That the waste site feasibility study and plan of operation complies with s.
10295.51.
SB1,135,1211
3. That the applicant has committed to conducting the proposed mining in
12compliance with the mining permit and any other approvals issued for the mining.
SB1,135,1613
3m. That the proposed mining is likely to meet or exceed the regulations that
14apply to municipal floodplain zoning ordinances contained in the uniform rules
15promulgated by the department for preparation and implementation of municipal
16floodplain zoning ordinances.
SB1,135,1817
4. That the proposed mining is not likely to result in substantial adverse
18impacts to public health, safety, or welfare.
SB1,135,2019
5. That the proposed mining will result in a net positive economic impact in the
20area reasonably expected to be most impacted by the mining.
SB1,135,2221
6. That the applicant has applied for all necessary zoning approvals applicable
22to the proposed mining.
SB1,136,723
(b) The department shall approve or deny an application for a mining permit
24in writing and shall include the reasons for its decision with clarity and in detail.
25The department may modify the applicant's proposed mining plan, reclamation plan,
1or mining waste site feasibility study and plan of operation in order to meet the
2requirements of this subchapter, and, as modified, approve the application. The
3approval of the application for a mining permit constitutes the approval of the
4mining plan, reclamation plan, and waste site feasibility study and plan of operation.
5In its decision on the application for a mining permit, the department shall include
6a final decision on compliance with s. 1.11 and the requirements of s. 295.53,
7discussing all of the following:
SB1,136,98
1. Whether the department has considered the environmental impact
9statement and comments received on it.
SB1,136,1010
2. Whether the department has complied with ss. 1.11 and 295.53.
SB1,136,1311
3. Whether, consistent with social, economic, and other essential
12considerations, the department has adopted all practicable means within its
13authority to avoid or minimize any harm to the environment and, if not, why not.
SB1,136,15
14(2) Criteria for denial. The department shall deny the mining permit if it
15finds any of the following:
SB1,136,1616
(a) That the site is unsuitable for mining.
SB1,136,1817
(b) That the proposed mining may reasonably be expected to create any of the
18following situations:
SB1,136,2219
1. Hazards resulting in irreparable, substantial physical damage to any of the
20following that cannot be prevented under the requirements of this subchapter,
21avoided to the extent practicable by removal from the area of hazard, or offset by
22purchase or by obtaining the consent of the owner:
SB1,136,2323
a. A dwelling house.
SB1,136,2424
b. A public building.
SB1,136,2525
c. A school.
SB1,137,22
e. A cemetery.
SB1,137,33
f. A commercial or institutional building.
SB1,137,44
g. A public road.
SB1,137,95
2. Irreparable substantial environmental damage to lake or stream bodies
6despite adherence to the requirements of this subchapter. This subdivision does not
7apply to an activity that the department has authorized under statute, except that
8the destruction or filling in of a lake bed may not be authorized unless it is authorized
9under s. 295.60, 295.605, or 295.61.
SB1,137,1210
3. Landslides or substantial deposition from the proposed mining operation in
11stream or lake beds which cannot feasibly be prevented and which have not been
12authorized under s. 295.60 or 295.605.
SB1,137,1413
(c) That the applicant has violated, and continues to fail to comply with, this
14subchapter.
SB1,137,2015
(d) Subject to sub. (3), that the applicant, principal shareholder of the
16applicant, or a related person has within 10 years before the application is submitted
17forfeited a mining reclamation bond that was posted in accordance with a permit or
18other authorization for a mining operation in the United States, unless the forfeiture
19was by agreement with the entity for whose benefit the bond was posted and the
20amount of the bond was sufficient to cover all costs of reclamation.
SB1,137,2521
(e) Subject to sub. (3), that the applicant, a related person, or an officer or
22director of the applicant has, within 10 years before the application is submitted,
23been convicted of more than one felony for violations of laws for the protection of the
24natural environment arising out of the operation of a mining site in the United
25States, unless one of the following applies:
SB1,138,1
11. The person convicted has been pardoned for all of the felonies.
SB1,138,32
2. The person convicted is a related person or an officer or director of the
3applicant with whom the applicant terminates its relationship.
SB1,138,64
3. The applicant included in its permit application under s. 295.47 a plan to
5prevent the occurrence in this state of events similar to the events that directly
6resulted in the convictions.
SB1,138,117
(f) Subject to sub. (3), that the applicant or a related person has, within 10 years
8before the application is submitted, declared bankruptcy or undergone dissolution
9that resulted in the failure to reclaim a mining site in the United States in violation
10of a state or federal law and that failure has not been remedied and is not being
11remedied.
SB1,138,1612
(g) Subject to sub. (3), that, within 10 years before the application is submitted,
13a mining permit or other authorization for mining issued to the applicant or a related
14person was permanently revoked because of a failure to reclaim a mining site in the
15United States in violation of state or federal law and that failure has not been and
16is not being remedied.
SB1,138,24
17(3) Exception from denial criteria. The department may not deny a mining
18permit under sub. (2) (d) to (g) if the person subject to the convictions, forfeiture,
19permanent revocation, bankruptcy, or dissolution is a related person but the
20applicant shows that the person was not the parent corporation of the applicant, a
21person that holds more than a 30 percent ownership in the applicant, or a subsidiary
22or affiliate of the applicant in which the applicant holds more than a 30 percent
23interest at the time of the convictions, forfeiture, permanent revocation, bankruptcy,
24or dissolution.
SB1,139,3
1(4) Statement. The department shall send a statement as to whether the
2applicant has satisfied the requirements of this subchapter to the applicant and to
3the other persons specified in s. 295.57 (4) (b) 1. to 9.
SB1,139,5
4(5) Duration of approvals. (a) A mining permit is valid for the life of the
5mining project, subject to the enforcement provisions under s. 295.79.