SB1,186,2422
4. The department ensures that any prohibition imposed is reasonably related
23in time and scope to maintaining compliance with the enforcement standard at the
24point of standards application.
SB1,187,8
15. If the substance involved is naturally occurring, unless the substance
2involved is carcinogenic, teratogenic, or mutagenic in humans, the department
3considers the existence of the background concentration of the substance in
4evaluating response options to the noncompliance with the enforcement standard or
5alternative concentration limit for that substance and determines that the proposed
6prohibition will result in the protection of or substantial improvement in
7groundwater quality notwithstanding the background concentrations of the
8substance.
SB1,187,149
(b) The department may only require a remedial action to be taken if the
10remedial action is reasonably related in time and scope to the substance, activity, or
11practice that caused the enforcement standard or alternative concentration limit to
12an enforcement standard to be attained or exceeded and the quality of groundwater
13to be statistically significantly different from either baseline water quality or
14background water quality at the point of standards application.
SB1,188,215
(c) If nitrates or any substance of welfare concern attains or exceeds an
16enforcement standard and if the analysis of samples indicates that the quality of
17groundwater is statistically significantly different from either baseline or
18background water quality, then the department shall evaluate whether the
19enforcement standard was attained or exceeded in whole or in part due to high
20background water quality concentrations of the substance and whether the
21additional concentrations represent a public welfare concern before it designates the
22appropriate response and, notwithstanding ss. 160.21 (3) and 160.25 (1) (a) and the
23rule-making authority under s. 160.21 (1), the department may not prohibit a
24practice or activity or require closure and abandonment of a mining waste site,
1including any wastewater and sludge storage or treatment lagoon, unless it has
2followed the procedures in s. 295.78 and par. (a) 1. to 4. apply.
SB1,188,43
(d) If compliance with an enforcement standard is achieved at a point of
4standards application, then sub. (5) applies.
SB1,188,12
5(6m) Mandatory intervention boundary for mining waste site and mine. (a)
6Except as provided under par. (am), the horizontal distance to the mandatory
7intervention boundary for a mining waste site is 300 feet from the outer waste
8boundary or the outer edge of the excavation, unless the boundary of the design
9management zone is within 600 feet of the outer waste boundary or the outer edge
10of the excavation, in which case the mandatory intervention boundary is one-half
11the distance from the outer waste boundary or the outer edge of the excavation to the
12boundary of the design management zone.
SB1,188,1613
(am) The department may reduce the mandatory intervention boundary under
14par. (a) by a horizontal distance of up to 150 feet if the department determines that
15the reduction is necessary to adequately identify and respond to potential
16groundwater quality issues.
SB1,188,2217
(b) An operator shall monitor groundwater quality at locations approved by the
18department along the mandatory intervention boundary, except for any portion of
19the mandatory intervention boundary that is within another mandatory
20intervention boundary, and within the mandatory intervention boundary. When
21approving locations for monitoring, the department shall ensure that duplicative
22monitoring is not required within overlapping mandatory intervention boundaries.
SB1,189,223
(c) 1. Notwithstanding sub. (5), if a preventive action limit or an enforcement
24standard has been exceeded beyond the mandatory intervention boundary, the
1department shall require a response in accordance with s. NR 140.24, Wis. Adm.
2Code, except that s. NR 140.24 (5), Wis. Adm. Code, does not apply.
SB1,189,93
2. If sampling results indicate that an enforcement standard or a preventive
4action limit has been exceeded within, but not beyond, the mandatory intervention
5boundary and a comparison of sampling results to the results of modeling indicates
6that the sampling results are consistent with the design and expected performance
7of the mining waste site, the operator may recommend a no response action, and the
8department may approve a no response action if that is authorized under s. NR
9140.24 (5), Wis. Adm. Code.
SB1,189,11
10(7) Environmental analysis not required. An action under sub. (5) or (6) with
11respect to a specific site does not constitute a major state action under s. 1.11 (2).
SB1,189,15
12(8) Exemptions to groundwater quality standards. When issuing or
13modifying a mining permit or issuing or reissuing any other approval, the
14department may grant an exemption from a groundwater quality standard and
15establish an alternative concentration limit to a groundwater quality standard.
SB1,189,18
16(9) Applicability of other law. Chapter NR 140, Wis Adm. Code, applies to
17mining operations and mining sites, including mining waste sites, only to the extent
18that it does not conflict with this section.
SB1,189,24
19295.65 Successors. (1) When one operator succeeds to the interest of another
20in an uncompleted mining operation by sale, assignment, lease, or otherwise, the
21department shall release the first operator from the duties imposed upon the first
22operator by this subchapter as to the mining operation and transfer the mining
23permit and any approvals under ss. 295.60, 295.605, and 295.61 to the successor
24operator if all of the following apply:
SB1,190,2
1(a) The successor operator agrees to comply with the requirements of this
2subchapter.
SB1,190,63
(b) The successor operator discloses whether it has forfeited any performance
4security because of noncompliance with any mining laws within the previous 10
5years, posts any bond or other security required under s. 295.59, and assumes all
6responsibilities of all applicable approvals granted to the predecessor operator.
SB1,190,8
7(2) The department is not required to prepare an environmental impact
8statement or an environmental assessment for the purposes of this section.
SB1,190,23
9295.66 Cessation of mining or reclamation. If there is a cessation of
10mining or reclamation for 30 days or more that is not set forth in either the mining
11plan or the reclamation plan, the operator shall notify the department of the
12cessation within 48 hours of the cessation of mining and shall begin stabilization of
13the mining site. The department may require the operator to provide technical,
14engineering, and any other information that the operator believes shows that its
15actions to stabilize the mining site are adequate. If the department determines, after
16reviewing the information provided by the operator, that the proposed stabilization
17of the mining site will result in a substantial adverse impact to the environment, the
18department shall order the operator to begin additional measures to protect the
19environment, including, if the cessation is reasonably anticipated to extend for a
20protracted period of time, reclamation according to the reclamation plan or part of
21the reclamation plan. Usual and regular shutdown of operations on weekends, for
22maintenance or repair of equipment or facilities, or for other customary reasons do
23not constitute a cessation of mining.
SB1,191,2
24295.67 Determination of abandonment of mining. (1) Except as provided
25in sub. (2), abandonment of mining occurs if there is a cessation of mining, not set
1forth in an operator's mining plan or reclamation plan or by any other sufficient
2written or constructive notice, extending for more than 6 consecutive months.
SB1,191,3
3(2) Abandonment of mining does not occur if all of the following apply:
SB1,191,54
(a) The cessation of mining is due either to labor strikes or to unforeseen
5developments such as adverse market conditions.
SB1,191,76
(b) The cessation of mining does not continue beyond the time, not to exceed
75 years, specified by the department.
SB1,191,98
(c) The mining site is maintained in an environmentally stable manner during
9the cessation of mining.
SB1,191,1110
(d) The reclamation of the mining site continues according to the reclamation
11plan during the cessation of mining to the extent practicable.
SB1,191,21
12295.68 Certificates of completion and release of security. (1) Upon the
13petition of the operator, but not less than 4 years after notification to the department
14by the operator of the completion of the reclamation plan or not less than one year
15after notification to the department by the operator of the completion of the
16reclamation plan as to a portion of the mining site, if the department finds that the
17operator has completed reclamation of any portion of the mining site in accordance
18with the reclamation plan and this subchapter, the department shall issue a
19certificate of completion setting forth a description of the area reclaimed and a
20statement that the operator has fulfilled its duties under the reclamation plan as to
21that area.
SB1,192,2
22(2) Upon the issuance of any certificate of completion under sub. (1) for any
23portion of the mining site, but not for the entire mining site, the department shall
24allow the operator to reduce the amount of the bond or other security provided under
25s. 295.59 (1) to an amount equal to the estimated cost of reclamation of the portion
1of the mining site that is disturbed or for which reclamation has been completed but
2no certificate of completion has been issued.
SB1,192,8
3(3) Upon issuance of a certificate or certificates of completion of reclamation
4for the entire mining site, the department shall require the operator to maintain a
5bond or other security under s. 295.59 (1) equal to at least 10 percent of the cost to
6the state of reclamation of the entire mining site, except that if the mining site in the
7mining plan is less than 10 acres, the department may release the bond or other
8security after issuance of the certificate of completion for the entire mining site.
SB1,192,12
9(4) After 10 years after the issuance of a certificate or certificates of completion
10for the entire mining site, the department shall release the remaining bond or other
11security provided under s. 295.59 (1) if the department finds that the reclamation
12plan has been complied with.
SB1,193,2
13295.69 Termination of proof of financial responsibility for long-term
14care of mining waste site. (1) One year after closure, and annually thereafter
15until the department terminates the obligation to maintain proof of financial
16responsibility for long-term care of a mining waste site under sub. (2) (c), an operator
17who has carried out all necessary long-term care during the preceding year, may
18apply to the department for a reduction in the amount of the proof of financial
19responsibility provided under s. 295.59 (2m) equal to the costs of long-term care for
20that year. The operator shall provide an itemized list of costs incurred. If the
21department determines that the costs incurred are in accordance with the long-term
22care requirements in the approved waste site feasibility study and plan of operation
23and that adequate funds exist to complete required long-term care for the remainder
24of the 40-year period on which the amount of the proof of financial responsibility was
25originally determined, the department shall authorize in writing a reduction in the
1amount of proof of financial responsibility provided. The department shall make its
2determinations within 90 days of an application.
SB1,193,12
3(2) (a) An operator may apply to the department for termination of its
4obligation to maintain proof of financial responsibility for long-term care of the
5mining waste site under s. 295.59 (2m) at any time after the mining waste site has
6been closed for 20 years by submitting an application that demonstrates that
7continuation of the obligation to maintain proof of financial responsibility for
8long-term care is not necessary for adequate protection of public health or the
9environment. The burden is on the operator to prove by a preponderance of the
10evidence that continuation of the obligation to maintain proof of financial
11responsibility for long-term care is not necessary for adequate protection of public
12health or the environment.
SB1,193,2413
(b) Within 30 days of receiving an application under par. (a), the department
14shall provide notice to the public of the application for termination of the obligation
15to maintain proof of financial responsibility for long-term care. In the notice, the
16department shall invite the submission of written comments by any person on the
17application within 30 days of the date of the publication of the notice. The
18department shall provide the notice by publishing a class 1 notice under ch. 985 in
19the official newspaper designated under s. 985.04 or 985.05 or, if none exists, in a
20newspaper likely to give notice in the area of the mining waste site, and shall publish
21notice on the department's Internet site. The date on which the department first
22publishes the notice on its Internet site shall be considered the date of the publication
23of the notice required to be published under this paragraph. The department shall
24also send the notice to the operator.
SB1,194,8
1(c) Within 120 days of the date of the publication of the notice under par. (b),
2the department shall determine either that proof of financial responsibility for
3long-term care of the mining waste site is no longer required, in which case the
4applicant is relieved of the responsibility of providing proof of financial responsibility
5for long-term care, or that proof of financial responsibility for long-term care of the
6mining waste site is still required, in which case the applicant may not submit
7another application under par. (a) until at least 5 years have elapsed since the
8previous application.
SB1,194,18
9295.695 Inspections by the department.
(1) Any duly authorized officer,
10employee, or representative of the department who has received the safety training
11under
30 CFR 48.31 may enter and inspect any property, premises, or place on or at
12which any mining operation or facility is located or is being constructed or installed
13at any reasonable time for the purpose of ascertaining the state of compliance with
14this subchapter and the provisions of chs. 281, 283, 285, 289, 291, 292, and 299 and
15rules promulgated under those chapters that are applicable to the mining operation.
16No person may refuse entry or access to any authorized representative of the
17department who requests entry for purposes of inspection, and who presents
18appropriate credentials.
SB1,194,20
19(2) No person may obstruct, hamper, or interfere with any inspection
20authorized in sub. (1).
SB1,194,23
21(3) The department shall furnish to the operator a written report on any
22inspection setting forth all observations, relevant information, and data that relate
23to compliance status.
SB1,195,2
24295.73 Fees. (1) (a) Except as provided in par. (b), an applicant for a mining
25permit is not required to pay any application or filing fee for any approval other than
1a mining permit, notwithstanding any fee required under ch. 23, 29, 30, 31, 169, 281,
2283, 285, 289, or 291, or rules promulgated under those chapters.
SB1,195,43
(b) An applicant for a mining permit shall pay any fee required under s. 281.343
4(3) (c) 1.
SB1,195,9
5(3) (a) The department shall assess an applicant a fee equal to its costs, other
6than costs of a contract under par. (d), for evaluating the mining project, including
7the costs for consultants retained by the department to evaluate the application for
8the mining permit and the application for any other approval, or $2,000,000,
9whichever is less.
SB1,195,1010
(b) The applicant shall pay the fees under par. (a) as follows:
SB1,195,1311
1. One hundred thousand dollars shall be paid at the time that the bulk
12sampling plan is filed under s. 295.45 or at the time that the notice of the intention
13to file a mining permit application is filed, whichever is first.
SB1,195,1614
2. Two hundred fifty thousand dollars when the department provides cost
15information demonstrating that the payment under subd. 1. has been fully allocated
16against actual costs.
SB1,195,1917
3. Two hundred fifty thousand dollars when the department provides cost
18information demonstrating that the payment under subd. 2. has been fully allocated
19against actual costs.
SB1,195,2220
4. Two hundred fifty thousand dollars when the department provides cost
21information demonstrating that the payment under subd. 3. has been fully allocated
22against actual costs.
SB1,195,2523
5. Two hundred fifty thousand dollars when the department provides cost
24information demonstrating that the payment under subd. 4. has been fully allocated
25against actual costs.
SB1,196,3
16. Two hundred fifty thousand dollars when the department provides cost
2information demonstrating that the payment under subd. 5. has been fully allocated
3against actual costs.
SB1,196,64
7. Two hundred fifty thousand dollars when the department provides cost
5information demonstrating that the payment under subd. 6. has been fully allocated
6against actual costs.
SB1,196,97
8. Two hundred fifty thousand dollars when the department provides cost
8information demonstrating that the payment under subd. 7. has been fully allocated
9against actual costs.
SB1,196,1210
9. One hundred fifty thousand dollars when the department provides cost
11information demonstrating that the payment under subd. 8. has been fully allocated
12against actual costs.
SB1,196,1713
(c) After the department approves or denies the application for a mining permit
14or, if the applicant withdraws the application for a mining permit, after the applicant
15withdraws the application, the department shall refund to the applicant any amount
16paid by the applicant under par. (a) but not fully allocated against the department's
17actual costs.
SB1,196,2118
(d) In addition to the fees under par. (a), if the department contracts under s.
19295.53 (1) with a consultant to assist in preparation of an environmental impact
20statement and awards the contract on the basis of competitive bids, the applicant
21shall pay the full costs as provided in the contract.
SB1,196,24
22(4) Subchapter VI of ch. 289 does not apply to mining waste disposed of in a
23mining waste site covered by a mining permit, except that an operator shall pay the
24fees specified in ss. 289.63 (4), 289.64 (3), and 289.67 (1) (d).
SB1,197,4
1295.75 Effect of other laws.
(1) Except as provided in sub. (2), if there is a
2conflict between a provision in this subchapter and a provision in ch. 23, 29, 30, 31,
3160, 169, 281, 283, 285, 289, or 291 or in a rule promulgated under one of those
4chapters, the provision in this subchapter controls.
SB1,197,6
5(2) (a) If there is a conflict between a provision in this subchapter and a
6provision in s. 281.343, the provision in s. 281.343 controls.
SB1,197,87
(b) If there is a conflict between a provision in this subchapter and a provision
8in s. 281.346, the provision in s. 281.346 controls, except as provided in s. 295.57 (9).
SB1,197,13
9295.77 Review. (1) Limits on contested case hearings. No person is entitled
10to a contested case hearing on a decision by the department on an exploration license
11or an approval that is required before bulk sampling may be implemented. No person
12is entitled to a contested case hearing on a decision by the department on a mining
13permit application or any other approval, except as provided in subs. (2) and (3).
SB1,197,23
14(2) C
ontested case hearings; after initial mining permit decision or decision
15on amended plan. (a)
Entitlement. 1. A person is entitled to a contested case hearing
16on a decision by the department related to a mining permit for a proposed mining
17operation, including a decision related to the environmental impact statement for
18the proposed mining operation, or on any decision that is related to an approval
19associated with the proposed mining operation and that is issued no later than the
20day on which the department issues its decision on the application for the mining
21permit, only if the person is entitled to a contested case hearing on the decision under
22s. 227.42 and the person requests the hearing within 30 days after the department
23issues the decision to approve or deny the application for the mining permit.
SB1,198,724
2. A person is entitled to a contested case hearing on a decision by the
25department related to an amended mining plan, reclamation plan, or mining waste
1site feasibility study and plan of operation required under s. 295.63 (3) or to any
2amendment to an approval associated with the amended mining plan, reclamation
3plan, or mining waste site feasibility study and plan of operation only if the person
4is entitled to a contested case hearing on the decision under s. 227.42 and the person
5requests the hearing within 30 days after the department issues the decision to
6approve or deny the amended mining plan, reclamation plan, or mining waste site
7feasibility study and plan of operation.
SB1,198,108
3. All issues raised by all persons requesting a contested case hearing in
9accordance with subd. 1. or 2. in connection with the same mining operation shall be
10considered in one contested case hearing.
SB1,198,1511
(b)
Deadline for decision. 1. The hearing examiner presiding over a contested
12case hearing under this subsection shall issue a final decision on the case no more
13than 150 days after the department issues the decision to grant or deny the mining
14permit or to approve or deny the amended mining plan, reclamation plan, or mining
15waste site feasibility study and plan of operation.
SB1,198,1816
2. If the hearing examiner does not issue a final decision by the deadline under
17subd. 1., the decision of the department being reviewed by the hearing examiner is
18affirmed.
SB1,198,2219
(c)
Restriction on orders. The hearing examiner presiding over a contested case
20hearing under this subsection may not issue an order prohibiting activity authorized
21under a decision of the department that is being reviewed in the contested case
22hearing.
SB1,199,423
(d)
Judicial review. A person seeking judicial review of the decision in a
24contested case hearing under this subsection shall comply with the requirements for
25service and filing in s. 227.53 (1) (a) and shall commence the action, in the circuit
1court for the county in which the majority of the proposed mining site is located, no
2more than 30 days after service of the decision or, if the hearing examiner does not
3issue a final decision by the deadline under par. (b) 1., no more than 30 days after that
4deadline.
SB1,199,10
5(3) Contested case hearings on other decisions A person is entitled to a
6contested case hearing on a decision by the department related to a mining operation
7that is issued after the department issues the decision to approve the application for
8the mining permit for the mining operation, other than a decision described in sub.
9(2) (a) 2., if the person is entitled to a contested case hearing under s. 227.42 and
10complies with the requirements for service and filing in s. 227.53 (1) (a).
SB1,199,14
11295.78 Mining and reclamation; orders.
(1) (a) If the department finds a
12violation of law or any unapproved deviation from the mining plan, reclamation plan,
13or mining waste site feasibility study and plan of operation at a mining site under
14a mining permit, the department shall do one of the following:
SB1,199,1715
1. Issue an order requiring the operator to comply with the law, mining plan,
16reclamation plan, or mining waste site feasibility study and plan of operation within
17a specified time.
SB1,199,1918
2. Require the alleged violator to appear before the department for a hearing
19and answer the department's charges.
SB1,199,2020
3. Request the department of justice to initiate action under s. 295.79.
SB1,199,2421
(b) Any order issued under par. (a) 1. following a hearing takes effect
22immediately. Any other order takes effect 10 days after the date the order is served,
23unless the person named in the order requests in writing a hearing before the
24department within the 10-day period.
SB1,200,4
1(c) If no hearing on an order issued under par. (a) 1. was held and if the
2department receives a request for a hearing within 10 days after the date the order
3is served, the department shall provide due notice and hold a hearing. If after the
4hearing the department finds that no violation has occurred, it shall rescind its order.
SB1,200,95
(d) If an operator fails to comply with an order issued under par. (a) 1. within
6the time for compliance specified in the order, the department shall suspend the
7mining permit until the operator fully complies with the order, except that if the
8operator seeks review of the order under s. 295.77 (3), mining may continue until the
9final disposition of the action, except as provided under sub. (4).
SB1,200,1210
(e) The department shall inform the department of justice of a suspension
11under par. (d) within 14 days. After receiving notice of a suspension, the department
12of justice may commence an action under s. 295.79.
SB1,200,22
13(2) If reclamation of a mining site is not proceeding in accordance with the
14reclamation plan and the operator has not begun to rectify deficiencies within the
15time specified in an order, or if the reclamation is not properly completed in
16conformance with the reclamation plan within one year after completion or
17abandonment of mining on any portion of the mining site, unless because of acts of
18God, such as adverse weather affecting grading, planting, and growing conditions,
19the department, with the staff, equipment, and material under its control, or by
20contract with others, shall take the actions that are necessary for the reclamation of
21mined areas. The operator is liable for the cost to the state of reclamation conducted
22under this subsection.
SB1,201,3
23(3) The department shall cancel all other mining permits held by an operator
24who refuses to reclaim a mining site in compliance with the reclamation plan after
25the completion of mining or after the cancellation of a mining permit. The
1department may not issue any mining permit for that mining site or any other
2mining site in this state to an operator who refused to reclaim the mining site in
3compliance with the reclamation plan.
SB1,201,9
4(4) At any time that the department determines that the continuance of mining
5constitutes an immediate and substantial threat to public health and safety or the
6environment, the department may request the department of justice to institute an
7action in circuit court of the county in which the mine is located for a restraining
8order or injunction or other appropriate remedy to stop mining until the immediate
9and substantial threat is eliminated.
SB1,201,11
10(5) Section 281.346 (7m) does not apply to a water withdrawal associated with
11a mining operation for which a mining permit has been issued.
SB1,201,15
12295.79 Enforcement; penalties. (1) The department of justice shall enforce
13this subchapter and any order issued under this subchapter. The circuit court of the
14county where the violation occurred has jurisdiction to enforce this subchapter or any
15orders issued under this subchapter, by injunction or other appropriate relief.
SB1,201,19
16(2) (a) Any person who authorizes or engages in mining without a mining
17permit and written authorization to mine under s. 295.59 (3) shall forfeit all profits
18obtained from those illegal activities and not more than $5,000 for each day during
19which the mine was in operation.
SB1,201,2120
(b) A person to whom par. (a) applies is also liable to the department for the full
21cost of reclaiming the affected area of land and any damages caused by the mining.
SB1,201,2522
(c) If the violator of par. (a) is a corporation, limited liability company,
23partnership, or association, any officer, director, member, manager, or partner who
24knowingly authorizes, supervises, or contracts for mining is also subject to the
25penalties in this subsection.
SB1,202,8
1(3) Any person who makes or causes to be made in an application or report
2required by this subchapter a statement known to the person to be false or
3misleading in any material respect or who refuses to submit information required by
4a mining permit or by this subchapter may be fined not less than $1,000 nor more
5than $5,000. If the false or misleading statement is material to the issuance of the
6mining permit and the mining permit would not have been issued had the false or
7misleading statement not been made, the court may revoke the mining permit. If any
8violation under this subsection is repeated the court may revoke the mining permit.
SB1,202,14
9(4) (a) Any person who commits a violation of this subchapter or any permit or
10order issued under this subchapter, except for the violations enumerated in subs. (2)
11and (3), shall forfeit not less than $10 nor more than $5,000 for each violation. Each
12day of continued violation is a separate offense, except that no forfeiture may be
13imposed during the time that continued mining is authorized under s. 295.63 (3).
14While an order is suspended, stayed, or enjoined, this penalty does not accrue.
SB1,202,2015
(b) In addition to the penalties provided under par. (a), the court may award
16the department of justice the reasonable and necessary expenses of the investigation
17and prosecution of the violation, including attorney fees. The department of justice
18shall deposit in the state treasury for deposit into the general fund all moneys that
19the court awards to the department or the state under this paragraph. These moneys
20shall be credited to the appropriation account under s. 20.455 (1) (gh).
SB1,202,22
21(5) Any person having an interest that is or may be adversely affected may
22intervene as a matter of right, in any enforcement action brought under this section.
SB1,97
23Section
97. 299.85 (7) (a) 2. and 4. of the statutes are amended to read:
SB1,203,1224
299.85
(7) (a) 2. Notwithstanding minimum or maximum forfeitures specified
25in ss. 29.314 (7), 29.334 (2), 29.604 (5) (a), 29.611 (11), 29.889 (10) (c) 2., 29.969,
129.971 (1) (a), (1m) (a), (3), (3m), (11g) (b), (11m) (b), and (11r) (b), 30.298 (1), (2), and
2(3), 30.49 (1) (a) and (c), 31.23 (2), 281.75 (19), 281.98 (1), 281.99 (2) (a) 1., 283.91 (2),
3285.41 (7), 285.57 (5), 285.59 (8), 285.87 (1), 287.95 (1), (2) (b), and (3) (b), 287.97,
4289.96 (2) and (3) (a), 291.97 (1), 292.99 (1) and (1m), 293.81, 293.87 (3) and (4) (a),
5295.19 (3) (a) and (b) 1., 295.37 (2),
295.79 (2) and (4), 299.15 (4), 299.51 (5), 299.53
6(4) (c) 1., 299.62 (3) (a) and (c), and 299.97 (1), if a regulated entity that qualifies
7under sub. (2) for participation in the Environmental Compliance Audit Program
8corrects violations that it discloses in a report that meets the requirements of sub.
9(3) within 90 days after the department receives the report that meets the
10requirements of sub. (3), the regulated entity may not be required to forfeit more than
11$500 for each violation, regardless of the number of days during which the violation
12continues.
SB1,203,2313
4. Notwithstanding minimum or maximum forfeitures specified in ss. 29.314
14(7), 29.334 (2), 29.604 (5) (a), 29.611 (11), 29.889 (10) (c) 2., 29.969, 29.971 (1) (a), (1m)
15(a), (3), (3m), (11g) (b), (11m) (b), and (11r) (b), 30.298 (1), (2), and (3), 30.49 (1) (a) and
16(c), 31.23 (2), 281.75 (19), 281.98 (1), 281.99 (2) (a) 1., 283.91 (2), 285.41 (7), 285.57
17(5), 285.59 (8), 285.87 (1), 287.95 (1), (2) (b), and (3) (b), 287.97, 289.96 (2) and (3) (a),
18291.97 (1), 292.99 (1) and (1m), 293.81, 293.87 (3) and (4) (a), 295.19 (3) (a) and (b)
191., 295.37 (2),
295.79 (2) and (4), 299.15 (4), 299.51 (5), 299.53 (4) (c) 1., 299.62 (3) (a)
20and (c), and 299.97 (1), if the department approves a compliance schedule under sub.
21(6) and the regulated entity corrects the violations according to the compliance
22schedule, the regulated entity may not be required to forfeit more than $500 for each
23violation, regardless of the number of days during which the violation continues.
SB1,98
24Section
98. 299.95 of the statutes is amended to read:
SB1,204,17
1299.95 Enforcement; duty of department of justice; expenses. The
2attorney general shall enforce chs. 281 to 285 and 289 to 295 and this chapter, except
3ss. 285.57, 285.59, and 299.64, and all rules, special orders, licenses, plan approvals,
4permits, and water quality certifications of the department, except those
5promulgated or issued under ss. 285.57, 285.59, and 299.64 and except as provided
6in ss. 285.86 and 299.85 (7) (am).
The Except as provided in s. 295.79 (1), the circuit
7court for Dane county or for any other county where a violation occurred in whole or
8in part has jurisdiction to enforce chs. 281 to 285 and 289 to 295 or this chapter or
9the rule, special order, license, plan approval, permit, or certification by injunctional
10and other relief appropriate for enforcement. For purposes of this proceeding where
11chs. 281 to 285 and 289 to 295 or this chapter or the rule, special order, license, plan
12approval, permit or certification prohibits in whole or in part any pollution, a
13violation is considered a public nuisance. The department of natural resources may
14enter into agreements with the department of justice to assist with the
15administration of chs. 281 to 285 and 289 to 295 and this chapter. Any funds paid
16to the department of justice under these agreements shall be credited to the
17appropriation account under s. 20.455 (1) (k).
SB1,99
18Section
99. 323.60 (1) (gm) of the statutes is created to read: