SB85,5,1817 5. The year in which the department expects to complete the project as of the
18date of preparation of the report.
SB85,5,2119 6. An explanation of any difference between the full project cost estimates
20under subds. 1. and 4. that has not been addressed in a previous report under this
21paragraph.
SB85,5,2322 7. The opinion of the department as to whether the project will be completed
23as originally scheduled without the allocation of additional funds.
SB85,6,3
1(b) The report under par. (a) shall treat separately and as described in the
2enumerating statute each project enumerated under s. 84.013 (3) or 84.0145 (3) (b)
3and shall treat separately each project approved under s. 84.013 (6).
SB85,7 4Section 7. 84.06 (1) (a) of the statutes is renumbered 84.06 (1) (am).
SB85,8 5Section 8. 84.06 (1) (ag) of the statutes is created to read:
SB85,6,96 84.06 (1) (ag) “Construction manager" means a person in the business of
7providing construction services that is also qualified to supervise, manage, or
8otherwise participate in the engineering, design, or construction work for an
9improvement project.
SB85,9 10Section 9. 84.06 (1) (aj) of the statutes is created to read:
SB85,6,1211 84.06 (1) (aj) “Construction manager-general contractor contract" means a
12contract for an improvement project awarded under sub. (2m).
SB85,10 13Section 10. 84.06 (2) (a) of the statutes is amended to read:
SB85,7,814 84.06 (2) (a) All such highway improvements shall be executed by contract
15based on bids unless the department finds that another method as provided in sub.
16(2m), (3), or (4) would be more feasible and advantageous. Bids shall be advertised
17for in the manner determined by the department. Except as provided in s. 84.075,
18the contract shall be awarded to the lowest competent and responsible bidder as
19determined by the department. If the bid of the lowest competent bidder is
20determined by the department to be in excess of the estimated reasonable value of
21the work or not in the public interest, all bids may be rejected. The department shall,
22so far as reasonable, follow uniform methods of advertising for bids and may
23prescribe and require uniform forms of bids and contracts. Except as provided in par.
24(b), the secretary shall enter into the contract on behalf of the state. Every such
25contract is exempted from ss. 16.70 to 16.75, 16.755 to 16.82, 16.87 and 16.89, but

1ss. 16.528, 16.752, 16.753, and 16.754 apply to the contract. Any such contract
2involving an expenditure of $1,000 or more shall not be valid until approved by the
3governor. The secretary may require the attorney general to examine any contract
4and any bond submitted in connection with the contract and report on its sufficiency
5of form and execution. The bond required by s. 779.14 (1m) is exempt from approval
6by the governor and shall be subject to approval by the secretary. This subsection
7also applies to contracts with private contractors based on bids for maintenance
8under s. 84.07.
SB85,11 9Section 11. 84.06 (2m) of the statutes is created to read:
SB85,7,1410 84.06 (2m) Construction manager-general contractor process. (a) If the
11department finds that it would be more feasible and advantageous, the department
12may, prior to July 1, 2021, award a 2-phase construction manager-general
13contractor contract to a construction manager for preconstruction and construction
14services for an improvement project.
SB85,7,1815 (b) For the design and engineering phase, the department may award a
16construction manager-general contractor contract to a construction manager based
17on qualifications, experience, best value, or any other combination of factors the
18department considers appropriate.
SB85,7,2219 (c) Before the project design is 90 percent complete, the construction manager
20shall provide to the department a proposal for the construction manager to construct
21the project. The proposal shall certify that at least 30 percent of the work for the
22construction phase shall be performed by the construction manager.
SB85,7,2423 (d) The department shall obtain an independent cost estimate for the
24construction of the project.
SB85,7,2525 (e) For the construction phase, the department may do any of the following:
SB85,8,2
11. Enter into a construction contract with the construction manager pursuant
2to a proposal under par. (c).
SB85,8,33 2. Award the construction contract in accordance with sub. (2).
SB85,8,54 (f) The department may utilize a construction manager-general contractor
5contract for no more than 3 highway improvement projects.
SB85,12 6Section 12. 779.14 (1) (b) of the statutes is amended to read:
SB85,8,107 779.14 (1) (b) With respect to contracts entered into under s. 84.06 (2) or (2m)
8for highway improvements, any person who has a direct contractual relationship,
9expressed or implied, with the prime contractor to perform, furnish, or procure labor,
10services, materials, plans, or specifications.
SB85,13 11Section 13. 779.14 (2) (a) 3. of the statutes is amended to read:
SB85,8,1712 779.14 (2) (a) 3. With respect to contracts entered into under s. 84.06 (2) or (2m)
13for highway improvements, failure of the prime contractor to comply with a contract,
14whether express or implied, with a subcontractor, supplier, or service provider of the
15prime contractor for performing, furnishing, or procuring labor, services, materials,
16plans, or specifications for the purpose of making the highway improvement that is
17the subject of the contract with the governmental entity.
SB85,14 18Section 14. 895.56 (2) (a) of the statutes is amended to read:
SB85,8,2319 895.56 (2) (a) The acts or omissions by the person occurred while performing
20a contract entered into under s. 84.06 (2) or (2m), including acts or omissions by any
21person who has a direct contractual relationship with the prime contractor, as
22defined in s. 779.01 (2) (d), under a contract entered into under s. 84.06 (2) or (2m)
23to perform labor or furnish materials.
SB85,15 24Section 15. 895.56 (2) (c) of the statutes is amended to read:
SB85,9,5
1895.56 (2) (c) The acts or omissions involving petroleum-contaminated soil on
2the property were required by reasonably precise specifications in the contract
3entered into under s. 84.06 (2) or (2m), and the acts or omissions conformed to those
4specifications, or were otherwise directed by the department of transportation or by
5the department of natural resources.
SB85,16 6Section 16. Initial applicability.
SB85,9,97 (1) The treatment of sections 84.06 (1) (a), (ag), and (aj), (2) (a), and (2m), 779.14
8(1) (b) and (2) (a) 3., and 895.56 (2) (a) and (c) of the statutes first applies to contracts
9entered into on the effective date of this subsection.
SB85,9,1010 (End)
Loading...
Loading...