SB468,4,22
79.04
(5) (a) 1m. (intro.) For property decommissioned before January 1, 2021:
SB468,7
3Section 7
. 79.04 (5) (a) 2m. of the statutes is created to read:
SB468,4,44
79.04
(5) (a) 2m. For property decommissioned after December 31, 2020:
SB468,4,55
a. In the first year that the property is taxable, 100 percent.
SB468,4,66
b. In the 2nd year that the property is taxable, 90 percent.
SB468,4,77
c. In the 3rd year that the property is taxable, 80 percent.
SB468,4,88
d. In the 4th year that the property is taxable, 70 percent.
SB468,4,99
e. In the 5th year that the property is taxable, 60 percent.
SB468,4,1010
f. In the 6th year that the property is taxable, 50 percent.
SB468,4,1111
g. In the 7th year that the property is taxable, 40 percent.
SB468,4,1212
h. In the 8th year that the property is taxable, 30 percent.
SB468,4,1313
i. In the 9th year that the property is taxable, 20 percent.
SB468,4,1414
j. In the 10th year that the property is taxable, 10 percent.
SB468,8
15Section
8. 79.04 (5) (b) (intro) of the statutes is amended to read:
SB468,4,2316
79.04
(5) (b) (intro.) If property that was exempt from the property tax under
17s. 70.112 (4) and that was used to generate power by a light, heat, or power company,
18except property under s. 66.0813, unless the production plant is owned or operated
19by a local governmental unit located outside of the municipality, or by an electric
20cooperative, or by a municipal electric company under s. 66.0825, is decommissioned
21or closed, the county shall be paid, from the public utility account, an amount equal
22to the following percentages of the payment the county received under this section
23during the last year that the property was exempt from the property tax:
SB468,9
24Section 9
. 79.04 (5) (b) 1. to 5. of the statutes are renumbered 79.04 (5) (b) 1m.
25a. to e.
SB468,10
1Section
10. 79.04 (5) (b) 1m. (intro.) of the statutes is created to read:
SB468,5,22
79.04
(5) (b) 1m. (intro.) For property decommissioned before January 1, 2021:
SB468,11
3Section 11
. 79.04 (5) (b) 2m. of the statutes is created to read:
SB468,5,44
79.04
(5) (b) 2m. For property decommissioned after December 31, 2020:
SB468,5,55
a. In the first year that the property is taxable, 100 percent.
SB468,5,66
b. In the 2nd year that the property is taxable, 90 percent.
SB468,5,77
c. In the 3rd year that the property is taxable, 80 percent.
SB468,5,88
d. In the 4th year that the property is taxable, 70 percent.
SB468,5,99
e. In the 5th year that the property is taxable, 60 percent.
SB468,5,1010
f. In the 6th year that the property is taxable, 50 percent.
SB468,5,1111
g. In the 7th year that the property is taxable, 40 percent.
SB468,5,1212
h. In the 8th year that the property is taxable, 30 percent.
SB468,5,1313
i. In the 9th year that the property is taxable, 20 percent.
SB468,5,1414
j. In the 10th year that the property is taxable, 10 percent.
SB468,12
15Section
12. 79.04 (8) of the statutes is created to read:
SB468,5,1916
79.04
(8) All of the following apply to the payments for property of a production
17plant that includes multiple power generation units, except that this subsection
18applies only if the production plant's first power generation unit stops generating
19electricity after the effective date of this subsection .... [LRB inserts date]:
SB468,5,2420
(a) No payment received by a municipality or county under sub. (1), (2), (6), or
21(7) shall be reduced on the basis that one or more, but not all, of the power generation
22units are no longer generating electricity, and the amount of the payment shall be
23the amount that the municipality or county received in the year before the year in
24which the first power generation unit stopped generating electricity.
SB468,6,5
1(b) The payments under sub. (5) (a) 2m. or (b) 2m. shall not be made until the
2production plant is decommissioned, and then the payments shall be determined on
3the basis of the amount of the payment received by the municipality or county under
4sub. (1), (2), (6), or (7) in the year before the year in which the first power generation
5unit stopped generating electricity.