196.491(3)(h) (h) The commission may waive compliance with any requirement of this section to the extent necessary to restore service which has been substantially interrupted by a natural catastrophe, accident, sabotage or act of God.
196.491(3)(i) (i) If installation or utilization of a facility for which a certificate of convenience and necessity has been granted is precluded or inhibited by a local ordinance, the installation and utilization of the facility may nevertheless proceed.
196.491(3)(j) (j) Any person whose substantial rights may be adversely affected or any county, municipality or town having jurisdiction over land affected by a certificate of public convenience and necessity may petition for judicial review, under ch. 227, of any decision of the commission regarding the certificate.
196.491(3)(k) (k) No person may purchase, or acquire an option to purchase, any interest in real property knowing that such property is being purchased to be used for the construction of a high-voltage transmission line unless the person gives written notice to the prospective seller of the size, maximum voltage and structure type of any transmission line planned to be constructed thereon and the person by whom it will be operated. Contracts made in violation of this paragraph are subject to rescission by the seller at any time prior to the issuance of a certificate of public convenience and necessity for the high-voltage transmission line by the commission.
196.491(3c) (3c)Commencement of construction of large electric generating facilities.
196.491(3c)(a)(a) Except as provided in par. (b), an electric utility that has received a certificate of public convenience and necessity under sub. (3) for constructing a large electric generating facility shall commence construction no later than one year after the latest of the following:
196.491(3c)(a)1. 1. The date on which the commission issues the certificate of public convenience and necessity.
196.491(3c)(a)2. 2. The date on which the electric utility has been issued every federal and state permit, approval, and license that is required prior to commencement of construction.
196.491(3c)(a)3. 3. The date on which every deadline has expired for requesting administrative review or reconsideration of every federal and state permit, approval, and license that is required prior to commencement of construction.
196.491(3c)(a)4. 4. The date on which the electric utility has received the final decision, after exhaustion of judicial review, in every proceeding for judicial review described in sub. (3) (j).
196.491(3c)(b) (b) Upon showing of good cause, the commission may grant an extension to the deadline specified in par. (a).
196.491(3c)(c) (c) If an electric utility does not commence construction of a large electric generating facility within the deadline specified in par. (a) or extended under par. (b), the certificate of public convenience and necessity is void, and the electric utility may not commence construction of the large electric generating facility.
196.491(3g) (3g)Fees for certain high-voltage transmission lines.
196.491(3g)(a)(a) A person who receives a certificate of public convenience and necessity for a high-voltage transmission line that is designed for operation at a nominal voltage of 345 kilovolts or more under sub. (3) shall pay the department of administration an annual impact fee as specified in the rules promulgated by the department of administration under s. 16.969 (2) (a) and shall pay the department of administration a one-time environmental impact fee as specified in the rules promulgated by the department of administration under s. 16.969 (2) (b).
196.491(3g)(b) (b) A person that pays a fee under par. (a) may not use the payment to offset any other mitigation measure that is required in an order by the commission under sub. (3) regarding the certificate of public convenience and necessity specified in par. (a).
196.491(3m) (3m)Wholesale merchant plants.
196.491(3m)(a)(a) Commission approval required. Except as provided in par. (e), an affiliated interest of a public utility may not own, control or operate a wholesale merchant plant without the approval of the commission. The commission shall grant its approval only if each of the following is satisfied:
196.491(3m)(a)1. 1. The public utility has transferred control over its transmission facilities, as defined in s. 196.485 (1) (h), to an independent system operator, as defined in s. 196.485 (1) (d), that is approved by the federal energy regulatory commission or the public utility has divested its interest in the transmission facilities to an independent transmission owner, as defined in s. 196.485 (1) (dm).
196.491(3m)(a)2. 2. The commission finds that the ownership, control or operation will not have a substantial anticompetitive effect on electricity markets for any classes of customers.
196.491(3m)(b) (b) Duty to promulgate rules.
196.491(3m)(b)1.1. The commission shall promulgate rules that establish requirements and procedures for an affiliated interest to apply for an approval under par. (a). The rules shall do each of the following:
196.491(3m)(b)1.a. a. Describe the showing that an applicant is required to make for the commission to grant an approval under par. (a).
196.491(3m)(b)1.am. am. Establish screening tests and safe harbors for proposed wholesale merchant plant projects, including projects in which an affiliated interest is a passive investor and over which the affiliated interest is not able to exercise control or influence and projects in which an affiliated interest's ownership interest is less than 5%.
196.491(3m)(b)1.b. b. Describe the analytical process that the commission shall use in determining whether to make a finding under par. (a) 2. and describe the factors specified in subd. 3.
196.491(3m)(b)1.c. c. Allow an interested person to request a hearing on an application under s. 227.42.
196.491(3m)(b)2. 2. The analytical process specified in subd. 1. b. shall, to the extent practicable, be consistent with the analytical process described in the merger enforcement policy, as defined in s. 196.485 (1) (dr).
196.491(3m)(b)3. 3. The commission shall use the following factors in determining whether to make a finding under par. (a) 2.:
196.491(3m)(b)3.a. a. The degree of market concentration resulting from the affiliated interest's proposed ownership, operation or control.
196.491(3m)(b)3.b. b. The extent of control that the affiliated interest proposes to exercise over the wholesale merchant plant.
196.491(3m)(b)3.d. d. Any other factor that the commission determines is necessary to determine whether to make a finding under par. (a) 2.
196.491(3m)(c) (c) Sales by affiliated interests.
196.491(3m)(c)1.1. In this paragraph:
196.491(3m)(c)1.a. a. "Electric sale" means a sale of electricity that is generated at a wholesale merchant plant that is owned, operated or controlled by an affiliated interest.
196.491(3m)(c)1.b. b. "Firm sale" means an electric sale in which electricity is intended to be available to a purchaser at all times during a specified period on an uninterruptible basis.
196.491(3m)(c)2. 2. The commission shall review any electric sale by an affiliated interest to a public utility with which the affiliated interest is affiliated. If the commission finds that an electric sale is not in the public interest, the commission shall do any of the following:
196.491(3m)(c)2.a. a. Disallow the public utility's costs related to the sale in a rate-setting proceeding.
196.491(3m)(c)2.b. b. Order the public utility to provide a refund, in an amount determined by the commission, to its customers.
196.491(3m)(c)2.c. c. Order the public utility or affiliated interest to take any action that the commission determines is in the public interest, except that the commission may not order the public utility or affiliated interest to void the sale.
196.491(3m)(c)3. 3. An affiliated interest may not make any firm sale to a public utility with which the affiliated interest is affiliated if the firm sale satisfies any of the following:
196.491(3m)(c)3.a. a. The period of the firm sale is 3 years or more.
196.491(3m)(c)3.b. b. The period of the firm sale is less than 3 years and either the public utility or the affiliated interest has an option to extend the period to 3 years or more.
196.491(3m)(d) (d) Retail sales outside this state. The commission may not promulgate rules or issue orders that prohibit owners or operators of wholesale merchant plants from providing electric service to retail customers in another state.
196.491(3m)(e) (e) Exemption. An approval under par. (a) is not required for an affiliated interest to own, operate or control a wholesale merchant plant in Grant County if the affiliated interest owned, operated or controlled the wholesale merchant plant before January 1, 1998.
196.491 Cross-reference Cross Reference: See also s. PSC 100.11, Wis. adm. code.
196.491(4) (4)Exemptions.
196.491(4)(b)(b) Subsection (3) does not apply to a person that constructs electric generating equipment and associated facilities if the person satisfies each of the following:
196.491(4)(b)1. 1. The person is not a public utility or a cooperative association organized under ch. 185 for the purpose of generating, distributing or furnishing electric energy at retail or wholesale to its members only.
196.491(4)(b)2. 2. The person shows to the satisfaction of the commission that the person reasonably anticipates, at the time that construction of the equipment or facilities commences, that on each day that the equipment and facilities are in operation the person will consume no less than 70% of the aggregate kilowatt hours output from the equipment and facilities in manufacturing processes at the site where the equipment and facilities are located.
196.491(4)(c) (c) A certificate under sub. (3) is not required for a person to construct a high-voltage transmission line designed for operation at a nominal voltage of less than 230 kilovolts if all related construction activity takes place entirely within the area of an existing electric transmission line right-of-way.
196.491(5) (5)Service standards for electric generation, transmission and distribution facilities. The commission shall promulgate rules that establish all of the following:
196.491(5)(a) (a) Standards for inspecting, maintaining and repairing each of the following:
196.491(5)(a)1. 1. Electric generation facilities in this state that are owned by public utilities or provide service to public utilities under contracts with terms of 5 years or more.
196.491(5)(a)2. 2. Electric transmission or distribution facilities in this state that are owned by public utilities.
196.491(5)(b) (b) Standards that the commission determines are necessary for the safe and reliable operation of each of the following:
196.491(5)(b)1. 1. Electric generation facilities in this state that are owned by public utilities or provide service to public utilities under contracts with terms of 5 years or more.
196.491(5)(b)2. 2. Electric transmission or distribution facilities in this state that are owned by public utilities.
196.491 Cross-reference Cross Reference: See also ch. PSC 112, Wis. adm. code.
196.491 Annotation It was reasonable for the PSC to issue a certificate conditioned on the issuance of DNR permits when legislatively imposed time constraints could not have been met if sub. (3) (e) had been strictly followed and all permits required before the issuance of the certificate. Responsible Use of Rural & Agricultural Land v. PSC, 2000 WI 129, 239 Wis. 2d 660, 619 N.W.2d 888.
196.493 196.493 Construction of nuclear power plants limited.
196.493(1)(1)Definition. In this section, "nuclear power plant" means a nuclear-fired large electric generating facility as defined under s. 196.491 (1) (g).
196.493(2) (2)Limits on certification. The commission may not certify under s. 196.49 (3) (b) or 196.491 (3) any nuclear power plant unless the commission finds that:
196.493(2)(a) (a) A federally licensed facility, or a facility outside of the United States which the commission determines will satisfy the public welfare requirements of the people of this state, with adequate capacity to dispose of high-level nuclear waste from all nuclear power plants operating in this state will be available, as necessary, for disposal of the waste; and
196.493(2)(b) (b) The proposed nuclear power plant, in comparison with feasible alternatives, is economically advantageous to ratepayers, based upon:
196.493(2)(b)1. 1. The existence of a reliable and adequate nuclear fuel supply;
196.493(2)(b)2. 2. The costs for construction, operation and decommissioning of nuclear power plants and for nuclear waste disposal; and
196.493(2)(b)3. 3. Any other factor having an impact on the economics of nuclear power plants, as determined by the commission.
196.493 History History: 1983 a. 401; 1997 a. 204.
196.493 Cross-reference Cross Reference: See also ch. PSC 111, Wis. adm. code.
196.494 196.494 Regional transmission planning.
196.494(1) (1) In this section:
196.494(1)(a) (a) "Electric utility" means a public utility, other than a municipal utility, as defined in s. 196.377 (2) (a) 3., that provides retail electric service to customers in this state.
196.494(1)(b) (b) "Transmission facility" means any pipe, pipeline, duct, wire, line, conduit, pole, tower, equipment or other structure used for the transmission of electric power as determined by the commission.
196.494(2) (2) The commission shall conduct a study on identifying and relieving any constraint on an intrastate or interstate electric transmission system that adversely affects the reliability of transmission service provided to electric customers in this state and shall, no later than September 1, 1998, submit a report on the results of the study to the legislature in the manner provided under s. 13.172 (2).
196.494(3) (3) The commission shall, under this subsection, issue an order requiring the transmission company, as defined in s. 196.485 (1) (ge), or an electric utility to construct or procure, on a competitive basis, the construction of transmission facilities specified by the commission in its order if the commission determines that such construction is necessary to relieve a constraint on a transmission system and the construction will materially benefit the customers of the transmission company or electric utility or other electric utilities or of an independent system operator, as defined in s. 196.485 (1) (d), or independent transmission owner, as defined in s. 196.485 (1) (dm).
196.494(4) (4) The commission shall allow an electric utility to recover in its retail electric rates any costs that are prudently incurred by the utility in complying with an order under sub. (3).
196.494(5) (5) The governor may, on behalf of this state, enter into an interstate compact that establishes a joint process for the states in the upper midwest region of the United States to determine the need for and siting of regional electric transmission facilities that may affect electric service in this state. The governor may not enter into a compact under this subsection unless the compact includes requirements and procedures for establishing each of the following:
196.494(5)(a) (a) Compliance with each state's environmental and siting standards for transmission facilities.
196.494(5)(b) (b) A regional need determination for transmission facilities.
196.494(5)(c) (c) A mechanism for resolving conflicts between the states regarding the siting of transmission facilities.
196.494 History History: 1997 a. 204; 1999 a. 9.
196.495 196.495 Avoidance of duplication in electric facilities.
196.495(1)(1)
196.495(1)(a)(a) In this section:
196.495(1)(a)1. 1. "Primary voltage extension" means an extension of 500 feet or more.
196.495(1)(a)2. 2. "Secondary voltage extension" means an extension that is less than 500 feet.
196.495(1)(b) (b) The length of an extension shall be measured as the air line distance between an existing local service distribution line that normally operates at less than 35 kilovolts and the nearest point on the principal building or facility to be served by a primary voltage extension or a secondary voltage extension.
196.495(1m) (1m) No public utility, and no cooperative association organized under ch. 185 for the purpose of furnishing electric service to its members only, may:
196.495(1m)(a) (a) Extend or render electric service directly or indirectly to the premises of any person already receiving electric service directly or indirectly from another public utility or another cooperative association.
Loading...
Loading...
This is an archival version of the Wis. Stats. database for 2001. See Are the Statutes on this Website Official?