86.32(2)(a)(a) Cities, villages and towns shall be reimbursed for actual costs, as approved by the department, incurred in maintaining and operating lift bridges. Documentation of costs shall be submitted by each city, village and town by January 31 and reimbursement shall be made, starting in 1982-83, on the first Monday in July for costs incurred during the prior calendar year. If the amount appropriated under
s. 20.395 (1) (ft) is insufficient to pay the actual costs approved by the department for the maintenance and operation of lift bridges, the department shall prorate the amount appropriated in the manner it deems desirable.
86.32(2)(am)
(am) Reimbursement for maintenance of connecting highways shall be determined using the following rates per lane mile:
86.32(2)(am)7.
7. For 1995,1996 and 1997, $10,468 per lane mile for municipalities having a population over 500,000; $9,696 per lane mile for municipalities having a population of 150,001 to 500,000; $8,641 per lane mile for municipalities having a population of 35,001 to 150,000; $7,612 per lane mile for municipalities having a population of 10,000 to 35,000; and $6,558 per lane mile for municipalities having a population under 10,000.
86.32(2)(am)8.
8. For 1998 and thereafter, $11,724 per lane mile for municipalities having a population over 500,000; $10,860 per lane mile for municipalities having a population of 150,001 to 500,000; $9,678 per lane mile for municipalities having a population of 35,001 to 150,000; $8,525 per lane mile for municipalities having a population of 10,000 to 35,000; and $7,345 per lane mile for municipalities having a population under 10,000.
86.32(2)(b)1.1. For the first 2 lanes of a highway, the applicable rate per lane mile shall be paid in full. For the 2nd 2 lanes of a highway, the payable rate per lane mile shall be 75% of the appropriate rate per lane mile prescribed in this section. For the 3rd 2 lanes, and any additional lanes, of highway, the payable rate per lane mile shall be 50% of the appropriate rate per lane mile prescribed in this section.
86.32(2)(b)2.
2. For the purpose of this section, the term "lane miles" means miles of through traffic carrying lanes and does not include lanes on which parking is permitted. Lane miles on any section of connecting highway which have been certified by the department for payment purposes under this section shall not be increased unless they are needed for through traffic and approved by the department. The "lane miles" as of January 1, 1977, are the certified lane miles.
86.32(2)(b)3.
3. The amount appropriated under
s. 20.395 (1) (fq) shall be distributed according to the per lane mile rate established in this subsection.
86.32(2)(b)4.
4. Annual connecting highway aids shall be paid in 4 installments on the first Monday in July, October, January and April. Unless fiscal year adjustments are necessary, the July and October installments shall equal the January and April installments of the previous fiscal year. If fiscal year adjustments are necessary, the department shall make these fiscal year adjustments in the July installment. If a fiscal year adjustment is made in the July installment, the next subsequent October installment shall equal the average of the most recent January, April and July installments.
86.32(2)(b)5.
5. If the amount appropriated under
s. 20.395 (1) (fq) is insufficient to make the payments for lane mile reimbursement under this subsection, the department shall prorate the amount appropriated in the manner it deems desirable.
86.32(4)
(4) Municipalities may arrange to participate in the cost of improvement projects on connecting highways. When a connecting highway is reconstructed the municipality shall be required to pay to the department the construction cost of that part of the connecting highway on which parking is to be permitted. However, if lanes on which parking is permitted are required for through traffic and parking is no longer allowed, the department shall reimburse the municipality for the remaining life of those lanes based on a pavement life of 25 years and the original municipal cost for the lanes.
86.33
86.33
Population estimates. Population determination for the purpose of calculating aids under
ss. 86.30 and
86.32 shall be based on the final population estimates arrived at by the department of administration under
s. 16.96 as of November 30 of the preceding year.
86.33 History
History: 1973 c. 333 s.
201w;
1977 c. 29.
86.34
86.34
Disaster damage aids. 86.34(1g)(a)
(a) "Catastrophic highway failure" means the sudden failure of a major element or segment of the highway system due to a cause that is external to a highway, but does not include any failure primarily attributable to gradual and progressive deterioration or lack of proper maintenance of a highway.
86.34(1g)(b)1.
1. A severe storm, flood, fire, tornado, mudslide, or other natural event external to a highway or a catastrophic highway failure.
86.34(1g)(b)2.
2. An event or recurring damage caused by any governmental unit or person acting under the direction or approval of, or permit issued by, any governmental unit and in response to an event described in
subd. 1.
86.34(1g)(c)
(c) "Governmental unit" means the state or any state agency, as defined in
s. 20.001 (1); any county, city, village, town, or other political subdivision of the state; or the federal government or any of its agencies.
86.34(1g)(d)
(d) "Highway" means a highway, as defined in
s. 340.01 (22), that is not on the state trunk highway system.
86.34(1m)(a)(a) When any highway is damaged by a disaster, the county highway committee, or the governing body of the municipality having jurisdiction over the maintenance of the highway, may adopt a petition for aid under this section and file a certified copy of the petition with the department. To be eligible for aid the petition shall be filed not later than 2 months after the occurrence of the disaster damage, except as provided in
par. (b). All such petitions shall state the dates on which the disaster damage occurred and as nearly as practical state the location, nature, and extent of the damage.
86.34(1m)(b)
(b) The department may extend the filing deadline under
par. (a) if it appears reasonably likely that federal disaster aid may be forthcoming or when widespread or continuous disaster damage makes an evaluation of damage difficult.
86.34(1m)(c)
(c) A county or municipality having jurisdiction over the facilities damaged may apply for both state and federal aid for damage to the facilities pending a determination of eligibility. If federal aid is granted for damage to a particular facility, the federal aid shall be in lieu of aid otherwise available for such damage under this section.
86.34(2)
(2) The department shall make such investigation as it deems necessary and within 6 months from the date of filing the petition shall make its determination as to the granting of aid, the amount thereof, and the conditions under which it is granted. In making its determination the department shall cause an estimate to be made of the cost of repairing or replacing the facilities damaged or destroyed to standards and efficiency similar to those existing immediately before the damage or destruction, and also an estimate of the cost of reconstructing the facilities to a higher type or improving any such facilities if determined to be warranted and advisable. Except as provided in
subs. (2m) and
(6), the amount of aid payable for damage caused by a disaster described in
sub. (1g) (b) 1. shall be 75 percent of the cost of repair or replacement to standards similar to those existing immediately before the damage or destruction, plus 50% of the increased cost of the reconstruction to a higher type or the improvement of any of the facilities. Except as provided in
subs. (2m) and
(6), the amount of aid payable for damage caused by a disaster described in
sub. (1g) (b) 2. shall be 70 percent of the cost of repair or replacement to standards similar to those existing immediately before the damage or destruction. The department may revise estimates on the basis of additional facts. The county, town, village, or city shall pay the remainder of the cost not allowed as aid, but this shall not invalidate any other provision of the statutes whereby the cost may be shared by the county and the town, village, or city.
86.34(2m)
(2m) Subject to
sub. (6), if the department's estimate under
sub. (2) of the cost of repair or improvement of the facilities determined by the department to be eligible for aid is $15,000 or less, the department shall offer the petitioner an amount of aid equal to 75% of the total amount of the department's estimate for damage caused by a disaster described in
sub. (1g) (b) 1. or 70 percent of the total amount of the department's estimate for damage caused by a disaster described in
sub. (1g) (b) 2. If the petitioner accepts aid under this subsection, the aid shall be paid to the petitioner or, subject to
sub. (5), the county, and no other form of aid is available under this section for the repair or improvement of such facilities.
86.34(3)
(3) Aid allotted under
sub. (2) shall be held to the credit of the county, town, city or village for not more than 2 years or for such other period as the department may grant, and, except as otherwise provided in this section, shall be paid to the treasurer thereof upon presentation to and approval by the department of certified statements setting forth the cost of the construction, reconstruction, repair or improvement of the facilities determined by the department to be eligible for aid. The certified statement shall set forth separately the amount expended on each such facility. The aid to be paid shall be the summation of the amounts determined or revised under
sub. (2), as adjusted by the certified statements approved by the department. This subsection does not apply to aid awarded under
sub. (2m).
86.34(5)
(5) Any town, city or village may, and at the discretion of the department shall, arrange to have such work for which aid is granted performed by the county, and in such case, on order of the town, city or village, the aid from the state for such work shall be paid to the county.
86.34(6)
(6) The department may not pay aid under this section in excess of $1,000,000, in connection with disaster damage resulting from a single disaster, unless the payment of aid is approved by the governor.
86.34(7)
(7) Beginning in the 2nd fiscal year of the 2013-15 fiscal biennium, and in the 2nd fiscal year of each fiscal biennium thereafter, the department shall calculate the amount of aid paid under this section, during the biennium, in excess of $1,000,000, in connection with disaster damage resulting from a single disaster. The amount calculated under this subsection shall be transferred under
s. 20.855 (4) (fr) from the general fund to the transportation fund in the 2nd fiscal year of each fiscal biennium.