196.485(5)(a)4.4. Notifies the commission in writing that the public utility affiliate has become a member of the Midwest independent system operator, has agreed to transfer its transmission facilities to the Midwest independent system operator and has committed not to withdraw its membership prior to the date on which the public utility affiliate contributes transmission facilities to the transmission company under par. (b).
196.485(5)(a)5.5. Petitions the commission and the federal energy regulatory commission to approve the contributions specified in subds. 2. and 3. and agrees in such a petition not to withdraw the petition in the event that the commission or the federal energy regulatory commission conditions its approval on changes that are consistent with state and federal law.
196.485(5)(b)(b) Contribution of transmission facilities.
196.485(5)(b)1.1. A public utility affiliate may not contribute a transmission facility to the transmission company until the commission has reviewed the terms and conditions of the transfer to determine whether the transfer satisfies the requirements of this subsection and has issued an order approving the terms and conditions of the transfer. The commission may modify the terms and conditions of the transfer and take any other action necessary to satisfy the requirements of this subsection. An order under this subdivision that approves or modifies the terms and conditions of a transfer may allow a public utility affiliate to recover in retail rates any adverse tax consequences of the transfer as a transition cost.
196.485(5)(b)2.2. The transmission company and a public utility affiliate that files a commitment to contribute transmission facilities under par. (a) 2. shall structure the transfer of the transmission facilities in a manner that satisfies each of the following:
196.485(5)(b)2.a.a. The structure of the transfer avoids or minimizes material adverse tax consequences to the public utility affiliate from the transfer and avoids or minimizes material adverse consequences on public utility rates that do not arise out of combining the transmission company’s facilities into a single zone in the Midwest independent system operator.
196.485(5)(b)2.b.b. To the extent practicable, the structure of the transfer satisfies the requirements of the Internal Revenue Service for a tax-free transfer.
196.485(5)(b)3.3. The requirements under subd. 2. b. shall, if practicable, be satisfied by the transmission company’s issuance of a preferred class of securities that provides the fixed-cost portion of the resulting capital structure of the transmission company. The transmission company shall issue preferred securities under this subdivision on a basis that does not dilute the voting rights of the initial security holders relative to the value of their initial contributions.
196.485(5)(b)4.4. If the transfer of transmission assets under this paragraph results in a capital structure of the transmission company in which the percentage of common equity is materially higher than that of the public utility affiliates who made the transfer, or if the cost of the fixed-cost portion of the capital structure of the transmission company is materially higher than that of the public utility affiliates who made the transfer, the public utility affiliates shall enter into a contract with the transmission company under which the public utility affiliates agree to accept from the transmission company a return on common equity based upon the equity rate of return approved by the federal energy regulatory commission and upon an imputed capital structure that assigns to a portion of the public utility affiliates’ common equity holdings an imputed debt return that is consistent with the requirements of this subdivision. A contract under this subdivision shall specify that the public utility affiliates shall be required to accept the return on common equity described in this subdivision only until such time that the federal energy regulatory commission determines that the actual capital structure and capital costs of the transmission company are appropriate and consistent with industry practice for a regulated public utility that provides electric transmission service in interstate commerce.
196.485(5)(b)5.5. If, at the time that a public utility affiliate files a commitment under par. (a) 2., the public utility affiliate has applied for or obtained a certificate of public convenience and necessity under s. 196.491 (3) or a certificate under s. 196.49 for the construction of transmission facilities, the public utility affiliate shall do each of the following:
196.485(5)(b)5.a.a. Proceed with diligence with respect to obtaining the certificate and, except as provided in subd. 6., constructing the transmission facilities.
196.485(5)(b)5.b.b. If the commission determines that the cost of the transmission facilities is reasonable and prudent, transfer the transmission facilities to the transmission company at net book value when construction is completed in exchange for additional securities of the transmission company on a basis that is consistent with the securities that were initially issued to the public utility affiliate.
196.485(5)(b)6.6. If the construction of a transmission facility specified in subd. 5. a. is not completed within 3 years after a certificate is issued for the transmission facility under s. 196.49 or 196.491 (3), the transmission company may assume responsibility for completing construction of the transmission facility. If the transmission company assumes responsibility for completing construction under this subdivision, the transmission company shall carry out any obligation under any contract entered into by the public utility with respect to the construction until the contract is modified or rescinded by the transmission company to the extent allowed under the contract.
196.485(5)(b)7.7. Any transmission facilities that are contributed to the transmission company shall be valued at net book value determined on the basis of the regulated books of account at the time of the transfer.
196.485(5)(bm)(bm) Lease of transmission facilities. If a public utility affiliate is not able to contribute its transmission facilities to the transmission company as required under par. (b) due to merger-related accounting requirements, the public utility affiliate shall transfer the transmission facilities to the transmission company under a lease for the period of time during which the accounting requirements are in effect and, after such requirements are no longer in effect, contribute the transmission facilities to the transmission company under par. (b). A public utility affiliate that transfers transmission facilities under a lease under this paragraph does not qualify for the asset cap exception under par. (a) unless, during the term of the lease, the public utility affiliate does not receive any voting interest in the transmission company.
196.485(5)(c)(c) Contribution of land rights.
196.485(5)(c)1.1. A public utility affiliate that commits to contributing land rights to the transmission company under par. (a) 2. shall do each of the following:
196.485(5)(c)1.a.a. Except as provided in subd. 2., if the land right is assigned to a transmission account for rate-making purposes and is not jointly used for electric and gas distribution facilities by the public utility affiliate, the public utility affiliate shall convey or assign at book value all of its interest in the land right to the transmission company, except that any conveyance or assignment under this subd. 1. a. shall be subject to the rights of any joint user of the land right and to the right of the public utility affiliate to nondiscriminatory access to the real estate that is subject to the land right.
196.485(5)(c)1.b.b. If the land right is jointly used, or is intended to be jointly used, for electric and gas distribution facilities by the public utility affiliate, the public utility affiliate shall enter into a contract with the transmission company that grants the transmission company a right to place, maintain, modify or replace the transmission company’s transmission facilities on the real property that is subject to the land right during the life of the transmission facilities and the life of any replacements of the transmission facilities. A right granted in a contract under this subd. 1. b. shall be paramount to the right of any other user of the land right, except that a right granted in such a contract shall be on par with the right of the public utility affiliate to use the land right for electric or gas distribution facilities.
196.485(5)(c)2.2. If a public utility affiliate is prohibited from making a conveyance or assignment described in subd. 1. a., the public utility affiliate shall enter into a contract with the transmission company that grants the transmission company substantially the same rights as under such a conveyance or assignment. For purposes of a contract under this subdivision, a land right shall be valued at book value, not at market value.
196.485(5)(c)3.3. The commission shall resolve any dispute over the contribution of a land right under subd. 1. or 2., including a dispute over the valuation of such a land right, unless a federal agency exercises jurisdiction over the dispute. During the pendency of any dispute that is before the commission or a federal agency, the transmission company shall be entitled to use the land right that is the subject to the dispute and shall be required to pay any compensation that is in dispute into an escrow account.
196.485(5)(d)(d) Applicability. Notwithstanding sub. (1) (h), and subject to any approval required under federal law, for purposes of this subsection, a facility of a public utility affiliate is a transmission facility if any of the following applies:
196.485(5)(d)1.1. The facility is not a radial facility and the facility is designed for operation at a nominal voltage of more than 130 kilovolts.
196.485(5)(d)2.2. The facility is not a radial facility and the facility is designed for operation at a nominal voltage of more than 50 kilovolts but not more than 130 kilovolts, unless a person has demonstrated to the commission that the facility is not a transmission facility on the basis of factors for identifying a transmission facility that are specified in the orders of the federal energy regulatory commission under 16 USC 824d and 824e.
196.485(5)(d)3.3. The facility is a radial facility or is designed for operation at a nominal voltage of 50 kilovolts or less, and a person has demonstrated to the commission that the facility is a transmission facility on the basis of factors for identifying a transmission facility that are specified in the orders of the federal energy regulatory commission under 16 USC 824d and 824e.
196.485(6)(6)Electric utilities, transmission dependent utilities and retail electric cooperatives.
196.485(6)(a)(a) No later than January 1, 2001:
196.485(6)(a)1.1. An electric utility, other than a public utility affiliate or an owner or operator of a wholesale merchant plant, as defined in s. 196.491 (1) (w), may transfer all of its transmission facilities that are specified in subd. 2. to the transmission company on the same terms and conditions as a contribution of transmission facilities and land rights by a public utility affiliate under sub. (5) (b) and (c).
196.485(6)(a)2.2. An electric utility may transfer transmission facilities under subd. 1. if the transmission facilities are located in the geographic area that is served by the Mid-America Interconnected Network, Inc., or the Mid-Continent Area Power Pool reliability council of the North American Electric Reliability Council.
196.485(6)(a)3.3. A transmission-dependent utility or retail electric cooperative may purchase equity interests in the transmission company at a price that is equivalent to net book value and on terms and conditions that are comparable to those for public utility affiliates that have contributed transmission facilities to the transmission company. A purchaser under this subdivision may contribute funds to the transmission company that are no more than the value of its prorated shares based on firm electric usage in this state in 1999.
196.485(6)(b)(b) Notwithstanding sub. (1) (h), and subject to any approval required under federal law, for purposes of this subsection, a facility of an electric utility is a transmission facility if the criteria specified in sub. (5) (d) 1., 2. or 3. are satisfied.
196.485(6m)(6m)Dividends, distributions, profits and gains. The commission may not treat any dividend or distribution received by a transmission utility from the transmission company or any gain or profit of a transmission utility from the sale or other disposition of securities issued by the transmission company as a credit against the retail revenue requirements of the transmission utility.
196.485(7)(7)Enforcement. A wholesale or retail customer of a public utility affiliate may petition the circuit court for Dane County for specific performance of a commitment filed under sub. (5) (a) 2. or 3.
196.485(8)(8)Penalties. A public utility affiliate that fails to complete the contribution of transmission facilities to the transmission company by the completion date specified in the filing under sub. (5) (a) 2. shall forfeit $25,000 for each day that completion of the contribution is delayed if the transmission company is legally able to accept the contribution.
196.487196.487Reliability of electric service.
196.487(1)(1)Definitions. In this section:
196.487(1)(a)(a) “Public utility affiliate” has the meaning given in s. 196.795 (1) (L).
196.487(1)(b)(b) “Transmission company” has the meaning given in s. 196.485 (1) (ge).
196.487(2)(2)Commission order. If the commission determines that a public utility affiliate or the transmission company is not making investments in the facilities under its control that are sufficient to ensure reliable electric service, the commission shall order the public utility affiliate or transmission company to make adequate investments in its facilities that are sufficient to ensure reliable electric service. An order under this subsection shall require the public utility affiliate or transmission company to provide security in an amount and form that, to the satisfaction of the commission, is sufficient to ensure that the public utility affiliate or transmission company expeditiously makes any investment that is ordered.
196.487(3)(3)Cost recovery. The commission shall allow a public utility affiliate that is subject to an order under sub. (2) to recover in its retail electric rates the costs that are prudently incurred in complying with the order.
196.487 HistoryHistory: 1999 a. 9.
196.49196.49Authorization from commission before transacting business; extensions and improvements to be approved; enforcement of orders; natural gas.
196.49(1)(1)
196.49(1)(am)(am) Except as provided in s. 196.50 (1) (am), no public utility not legally engaged in performing a utility service on August 1, 1931, in any municipality may commence the construction of any public utility plant, extension or facility, or render service in such municipality directly, or indirectly by serving any other public utility or agency engaged in public utility service or otherwise, unless the public utility has obtained a certificate from the commission authorizing it to transact public utility business.
196.49(1)(b)(b) This subsection applies only to a public utility which was not legally engaged in performing a public utility service on August 1, 1931, in a municipality and which proposes to commence construction or render service in the municipality. If there is a public utility engaged in similar service in operation under an indeterminate permit in the municipality, ss. 196.495 and 196.50 apply.
196.49(2)(2)No public utility may begin the construction, installation or operation of any new plant, equipment, property or facility, nor the construction or installation of any extension, improvement or addition to its existing plant, equipment, property, apparatus or facilities unless the public utility has complied with any applicable rule or order of the commission. If a cooperative association has been incorporated under ch. 185 for the production, transmission, delivery or furnishing of light or power and has filed with the commission a map of the territory to be served by the association and a statement showing that a majority of the prospective consumers in the area are included in the project, no public utility may begin any such construction, installation or operation within the territory until after the expiration of 6 months from the date of filing the map and notice. If the cooperative association has entered into a loan agreement with any federal agency for the financing of its proposed system and has given written notice of the agreement to the commission, no public utility may begin any construction, installation or operation within the territory until 12 months after the date of the loan agreement.
196.49(3)(3)
196.49(3)(a)(a) In this subsection, “project” means construction of any new plant, equipment, property or facility, or extension, improvement or addition to its existing plant, equipment, property, apparatus or facilities. The commission may require by rule or special order that a public utility submit, periodically or at such times as the commission specifies and in such detail as the commission requires, plans, specifications and estimated costs of any proposed project which the commission finds will materially affect the public interest.
196.49(3)(b)(b) The commission may require by rule or special order under par. (a) that no project may proceed until the commission has certified that public convenience and necessity require the project. The commission may refuse to certify a project if it appears that the completion of the project will do any of the following:
196.49(3)(b)1.1. Substantially impair the efficiency of the service of the public utility.
196.49(3)(b)2.2. Provide facilities unreasonably in excess of the probable future requirements.
196.49(3)(b)3.3. When placed in operation, add to the cost of service without proportionately increasing the value or available quantity of service unless the public utility waives consideration by the commission, in the fixation of rates, of such consequent increase of cost of service.
196.49(3)(c)(c) The commission may issue a certificate for the project or for any part of the project which complies with the requirements of this section, or the commission may attach to the issuance of its certificate such terms and conditions as will ensure that the project meets the requirements of this section. The issuance of a certificate under this section shall not be a condition precedent to the exercise of eminent domain under ch. 32.
196.49(4)(4)The commission may not issue a certificate under sub. (1), (2), or (3) for the construction of electric generating equipment and associated facilities unless the commission determines that brownfields, as defined in s. 238.13 (1) (a) or s. 560.13 (1) (a), 2009 stats., are used to the extent practicable.
196.49(5)(5)
196.49(5)(a)(a) No public utility furnishing gas to the public in this state may construct, install or place in operation any new plant, equipment, property or facility, or construct or install any extension, improvement, addition or alteration to its existing plant, equipment, property or facilities for the purpose of connecting its properties and system to a source of supply of gaseous fuel for sale to the public which is different from that which has been sold previously, or for the purpose of adapting its facilities to use the different kind of gaseous fuel unless the commission certifies that the general public interest and public convenience and necessity require the connection to or use of the different fuel. No public utility may substitute natural gas or a mixture of natural and manufactured gas in lieu of manufactured gas for distribution and sale to the public unless it has obtained from the commission a certificate that the general public interest and public convenience and necessity require the substitution.
196.49(5)(b)(b) Proceedings for a certificate under par. (a) shall be commenced by petition to the commission in a form prescribed by the commission, furnishing such information as the commission by rule or order prescribes. The commission shall prescribe the form of notice, to whom the notice shall be given, and how notice shall be given.
196.49(5)(c)(c) A petition under par. (b) may include one or more municipalities, may be made by one or more public utilities as a joint petition, by any other interested person or by a public utility and any other interested person. The commission may direct the consolidation, separation or consideration of separate petitions as it deems necessary or expedient to a prompt hearing and disposition of the issue.
196.49(5)(d)(d) Upon the filing of a petition under par. (b), notice of hearing on the petition shall be given by the person filing the petition by publication of a class 2 notice, under ch. 985, or by mailing or personal service, as the commission directs by the order under par. (b). Notice under this paragraph shall be given at least 2 weeks prior to hearing on the petition. Proof of notice shall be filed as directed by the commission.
196.49(5)(e)(e) The commission, with or without an order, prior to or during any hearing under this subsection, may frame and prescribe special issues and limit the issues or the nature and extent of proof so as to avoid unnecessary duplication. The commission, with or without an order, may proceed with the hearing as to part of a petition under par. (b) as it may find desirable to a full but speedy hearing upon the petition.
196.49(5)(f)(f) The commission may accept as presumptive evidence in a commission proceeding the facts found in findings and orders of the federal energy regulatory commission or any federal agency having jurisdiction as to the availability of adequate supplies of natural gas, the adequacy or sufficiency of equipment and facilities to be employed in the delivery or storage of natural gas for any public utility, and any similar findings or determinations affecting the seller or person furnishing natural gas to any public utility and material to the ultimate determination of the issues in the proceeding. The commission may accept and take judicial notice of its own files and records, including all proceedings and the evidence therein which it finds to be material and relevant. The commission shall give notice of the taking of judicial notice under this paragraph prior to the conclusion of final hearings upon any proceeding so as to give interested parties the right to object to acceptance of the evidence or to contradict the evidence by other competent evidence.
196.49(5)(g)(g) A certificate granted under par. (a) shall be authorized by an order following a hearing. The order shall contain any condition or limitation which the commission deems necessary or practicable, including, but not limited to, exceptions or regulations as to specific communities or public utilities, provision for protection of employees under existing labor contracts, as well as other employees, so as to avoid unemployment, regulations for accounting for expenses for change-over to the use of natural gas where necessary and to the extent necessary, provision for amortization of any expenditure or other items, and any other regulation, condition and limitation which the commission considers necessary in the public interest.
196.49(5)(h)(h) The commission by order may extend a certificate under par. (a) to more than one public utility or municipality. The commission may prescribe different conditions and regulations for each public utility or municipality if the commission deems the different conditions and regulations necessary to carry out the purposes of this section.
196.49(5)(i)(i) In making a determination under this section, the commission shall consider all appropriate factors affecting the public interest, including, but not limited to, when the substitution of natural or a mixture of natural and manufactured gas is involved, the likelihood of substantial rate reduction from the substitution and the effect of the substitution upon employment, existing business and industries, railroads and other transportation agencies and facilities, upon conveniences, economies and savings to consumers, upon existing gas utilities and their ability to continue to serve the public and upon the state, any of its political subdivisions or any citizen or resident of the state.
196.49(5g)(5g)
196.49(5g)(ag)(ag) In this subsection, “rebuild” means the replacement of all or part of an existing electric transmission line and associated facilities, including conductors, insulators, transformers, or structures, for operation at the same voltage.
196.49(5g)(ar)(ar) A public utility is exempt from the requirement to obtain a certification or approval of the commission under sub. (2) or (3) before beginning a proposed project if any of the following applies:
196.49(5g)(ar)1m.1m. The estimated gross cost of the proposed project is not more than one of the following cost thresholds:
196.49(5g)(ar)1m.a.a. For an electric public utility whose electric operating revenues in the prior year were less than $5,000,000, the cost threshold is $250,000.
196.49(5g)(ar)1m.b.b. For an electric public utility whose electric operating revenues in the prior year were $5,000,000 or more and less than $250,000,000, the cost threshold is 4 percent of those operating revenues.
196.49(5g)(ar)1m.c.c. For an electric public utility whose electric operating revenues in the prior year were $250,000,000 or more, the cost threshold is $10,000,000.
196.49(5g)(ar)1m.d.d. For a natural gas public utility, the cost threshold is $5,000,000 or 4 percent of the public utility’s natural gas operating revenues in the prior year, whichever is less.
196.49(5g)(ar)1m.e.e. For a water public utility or combined water and sewer public utility, the cost threshold is $250,000 or 25 percent of the utility’s operating revenues in the prior year, whichever is less.
196.49(5g)(ar)1s.1s. The project is to be completed by a water public utility, a combined water and sewer public utility, or an entity contracted by a water public utility or a combined water and sewer public utility and is for the purpose of installing, repairing, or replacing meters to measure service to customers.
196.49(5g)(ar)2m.2m. The project is a rebuild and all of the following apply:
196.49(5g)(ar)2m.a.a. The existing electric transmission line and associated facilities are designed for operation at a nominal voltage of less than 345 kilovolts.
196.49(5g)(ar)2m.b.b. Not more than one-half mile of the centerline of the rebuilt electric transmission line is located more than 60 feet on either side of the centerline of an existing electric transmission line operating at a nominal voltage of 69 kilovolts or more. In this subd. 2m. b., “centerline” has the meaning given in s. 196.491 (4) (c) 1e.
196.49(5g)(ar)2m.c.c. The project requires the acquisition in total of one-half mile or less of rights-of-way from landowners from which rights-of-way would not be required to be acquired for the existing electric transmission line specified in subd. 2m. b.
196.49(5g)(ar)2m.d.d. The project will not have undue adverse environmental impacts on any new rights-of-way required for the rebuild.
196.49(5g)(ar)3.3. The project is primarily to provide service to a new customer within an electronics and information technology manufacturing zone designated under s. 238.396 (1m).
196.49(5g)(b)(b) Beginning on May 1, 2014, and on May 1 of each successive even-numbered year thereafter, the commission shall adjust the cost thresholds specified in par. (ar) 1m. to reflect changes to the cost of utility construction based on the applicable industry cost index numbers published in the Handy-Whitman Index of Public Utility Construction Costs, or an equivalent successor index, and publicize the adjusted cost thresholds on the commission’s website.
196.49(5r)(5r)
196.49(5r)(am)(am) If a hearing is held on an application filed under sub. (1), (2), (3), or (5), the commission shall take final action on the application within 180 days after the commission issues a notice of hearing on the application. The chairperson of the commission may extend the time period for an additional 180 days for good cause. If the commission fails to take final action within the initial 180-day period, or the extended 180-day time period, the commission is considered to have issued a certificate of authority with respect to the application.
196.49(5r)(b)(b) If a hearing is not held on an application filed under sub. (1), (2), (3), or (5), the commission shall take final action on the application within 90 days after the commission issues a notice opening a docket on the application. The chairperson of the commission may extend the time period for an additional 90 days for good cause. If the commission fails to take final action within the initial 90-day period, or the extended 90-day time period, the commission is considered to have issued a certificate of authority with respect to the application.
196.49(5r)(c)1.1. With respect to an application for a certificate or approval for construction required under this section and filed by a water public utility or a combined water and sewer public utility, the commission shall determine whether the application is complete and, no later than 45 days after the application is filed the first time and no later than 30 days after the application is refiled a 2nd or subsequent time, notify the applicant in writing about the determination. If the commission determines that the application is incomplete, the notice shall identify all parts of the application the commission has determined to be incomplete and state the reasons for the determination. An applicant may supplement and refile an application that the commission has determined to be incomplete. There is no limit on the number of times that an applicant may refile an application under this paragraph. If the commission fails to determine whether an application is complete within 45 days after the application is filed or 30 days after the application is refiled, the application shall be considered to be complete.
196.49(5r)(c)2.2. If a hearing is held on an application under subd. 1., the commission shall take final action on the application within 180 days after the application is determined to be complete. The chairperson of the commission may extend the time period for an additional 180 days for good cause. If the commission fails to take final action within the initial 180-day period, or the extended 180-day time period, the commission is considered to have issued the certificate or approval for construction with respect to the application.
196.49(5r)(c)3.3. If a hearing is not held on an application under subd. 1., the commission shall take final action on the application within 90 days after the application is determined to be complete. The chairperson of the commission may extend the time period for an additional 90 days for good cause. If the commission fails to take final action within the initial 90-day period, or the extended 90-day time period, the commission is considered to have issued the certificate or approval for construction with respect to the application.
Loading...
Loading...
2021-22 Wisconsin Statutes updated through 2023 Wis. Act 272 and through all Supreme Court and Controlled Substances Board Orders filed before and in effect on October 4, 2024. Published and certified under s. 35.18. Changes effective after October 4, 2024, are designated by NOTES. (Published 10-4-24)