SB554,4
13Section 4
. 13.48 (10) (a) of the statutes is amended to read:
SB554,4,2314
13.48
(10) (a) Except as provided in par. (c), no state board, agency, officer,
15department, commission, or body corporate may enter into a contract for the
16construction, reconstruction, remodeling of, or addition to any building, structure,
17or facility, in connection with any building project which involves a cost in excess of
18$185,000 $300,000 without completion of final plans and arrangement for
19supervision of construction and prior approval by the building commission. This
20section applies to the department of transportation only in respect to buildings,
21structures, and facilities to be used for administrative or operating functions,
22including buildings, land, and equipment to be used for the motor vehicle emission
23inspection and maintenance program under s. 110.20.
SB554,5
24Section 5
. 13.48 (10) (b) 5. of the statutes is amended to read:
SB554,5,2
113.48
(10) (b) 5. Contracts for construction of any building, structure or facility
2for the state fair park board involving a cost of not more than
$250,000 $300,000.
SB554,6
3Section 6
. 13.48 (29) of the statutes is amended to read:
SB554,5,94
13.48
(29) Small
Simplified policies and procedures for construction
5projects. Except as otherwise required under s. 16.855 (10m), the building
6commission may prescribe simplified policies and procedures to be used in lieu of the
7procedures provided in s. 16.855 for any
construction project
that does not require
8prior approval of the building commission under sub. (10) (a)
involving a cost of not
9more than $300,000, except projects specified in sub. (10) (c).
SB554,7
10Section 7
. 13.488 (7) (a) of the statutes is amended to read:
SB554,5,1411
13.488
(7) (a) The building commission, with advice from the state fair park
12board, shall examine and review detailed design requirements for all state-owned
13facilities involving a cost of more than
$250,000
$300,000 to be included in the
14development of state fair park.
SB554,8
15Section 8
. 16.855 (1g) (ec) of the statutes is created to read:
SB554,5,1716
16.855
(1g) (ec) “Single trade contractor” means a contractor whose primary
17business is the performance of a trade.
SB554,9
18Section 9
. 16.855 (1g) (em) of the statutes is created to read:
SB554,5,2019
16.855
(1g) (em) “Trade” means mechanical, electrical, plumbing, or fire
20protection work.
SB554,10
21Section 10
. 16.855 (14) (am) of the statutes is amended to read:
SB554,5,2522
16.855
(14) (am) Except as provided in
sub. (14s) and s. 13.48 (19), the
23department shall let all construction projects that exceed
$185,000 $300,000 through
24single prime contracting. The department may not request or accept any alternate
25bids when letting a construction project through single prime contracting.
SB554,11
1Section
11. 16.855 (14s) of the statutes is created to read:
SB554,6,52
16.855
(14s) (a) The department may let any construction project that exceeds
3$300,000 to a single trade contractor for all work on the project if at least 85 percent
4of the estimated construction cost of the project is for work that involves the trade
5that is the primary business of the single trade contractor.
SB554,6,106
(b) The department and the Board of Regents shall each develop and
7implement an open and public bidding process for purposes of contracting with single
8trade contractors who have submitted the lowest bid on a project and who are
9qualified responsible bidders. For purposes of this paragraph, the department and
10the board shall follow the requirements and procedures under sub. (2).
SB554,6,1511
(c) Within 48 hours after the deadline for a single trade contractor to submit
12a bid, the department or the Board of Regents shall post on its Internet site the
13tabulations of all bids that identify the names of the single trade contractors that bid
14and the amount of each bid and shall make the tabulations and amounts available
15at the department or board if they are unavailable on the Internet site.
SB554,6,1916
(d) Except as provided in sub. (10m) (am), the department or the Board of
17Regents shall award all contracts under this subsection to the lowest bidder who is
18a qualified responsible bidder that results in the lowest total construction cost for the
19project.
SB554,6,2220
(e) Within 30 days after the deadline for a single trade contractor to submit a
21bid, the department or the Board of Regents shall notify the single trade contractor
22bidder that was awarded the contract.
SB554,6,2423
(f) A contract awarded under this subsection is not subject to subs. (13) and
24(14m).
SB554,12
25Section 12
. 16.855 (22) of the statutes is amended to read:
SB554,7,10
116.855
(22) The provisions of this section, except sub. (10m), do not apply to
2construction work for any project
that does not require the prior approval of the
3building commission under s. 13.48 (10) (a) involving a cost of not more than
4$300,000 if the project is constructed in accordance with policies and procedures
5prescribed by the building commission under s. 13.48 (29). If the estimated
6construction cost of any project, other than a project exempted under sub. (12m) or
7(24), is at least $50,000, and the building commission elects to utilize the procedures
8prescribed under s. 13.48 (29) to construct the project, the department shall provide
9adequate public notice of the project and the procedures to be utilized to construct
10the project on a publicly accessible computer site.
SB554,13
11Section 13
. 16.867 of the statutes is created to read:
SB554,7,15
1216.867 Selection of architects and engineers. (1) The secretary shall
13establish a committee under s. 15.04 (1) (c) for each construction project under the
14department's supervision, except an emergency project approved under s. 16.855
15(16) (b) 2., for the purpose of selecting an architect or engineer for the project.
SB554,7,19
16(2) If the estimated cost of a construction project under the department's
17supervision is $7,400,000 or more, the selection committee appointed under sub. (1)
18shall use a request-for-proposal process established by the department to select an
19architect or engineer for the project based on qualifications.
SB554,14
20Section 14
. 16.87 (3) of the statutes is amended to read:
SB554,8,1121
16.87
(3) Except as provided in sub. (4), a contract under sub. (2) is not valid
22or effectual for any purpose until it is endorsed in writing and approved by the
23secretary or the secretary's
designated assistant
designee and, if the contract
24involves an expenditure over
$60,000 $300,000, approved by the governor.
The
25governor may delegate the authority to approve any contract requiring his or her
1approval under this subsection that involves an expenditure of less than $150,000 2to the secretary or the secretary's designee. Except as provided in sub. (4), no
3payment or compensation for work done under any contract involving $2,500 or
4more, except a highway contract, may be made unless the written claim is audited
5and approved by the secretary or the secretary's designee. Any change order to a
6contract requiring approval under this subsection requires the prior approval by the
7secretary or the secretary's
designated assistant
designee and, if the change order
8involves an expenditure over
$60,000 $300,000, the approval of the governor
or, if the
9governor delegates his or her authority to approve contracts under this subsection
10and the change order involves an expenditure of less than $150,000, the approval of
11the secretary or the secretary's designee.
SB554,15
12Section 15
. 20.924 (1) (a) of the statutes is amended to read:
SB554,8,1513
20.924
(1) (a) Shall authorize the design and construction of any building,
14structure or facility costing in excess of
$760,000
$1,000,000 regardless of funding
15source, only if that project is enumerated in the authorized state building program.
SB554,16
16Section 16
. 20.924 (1) (b) of the statutes is amended to read:
SB554,8,2317
20.924
(1) (b) Shall authorize the acquisition of land, or the repair, remodeling
18or improvement to any existing building, structure or facility costing in excess of
19$760,000 $1,000,000, regardless of funding source, only if that project is enumerated
20in the authorized state building program. This paragraph does not apply to the
21acquisition of land by the building commission in the city of Madison within a block
22number specified in s. 13.48 (18). This paragraph does not apply to projects
23authorized under s. 16.858.
SB554,17
24Section
17.
Initial applicability.
SB554,8,2525
(1)
State building program thresholds.
SB554,9,2
1(a) The treatment of sections 13.48 (3) and 20.924 (1) (a) and (b) of the statutes
2first applies to authorizations occurring on the effective date of this paragraph.
SB554,9,53
(b) The treatment of sections 13.48 (10) (a) and (b) 5., 16.855 (22), and 16.87 (3)
4of the statutes first applies to contracts entered into, or extended, modified, or
5renewed, on the effective date of this paragraph.
SB554,9,96
(2)
Bidding and contracting. The treatment of sections 13.48 (29) and 16.855
7(14) (am) and (14s) of the statutes first applies to an advertisement that is published,
8or a solicitation that occurs, under section 16.855 (2) (a) of the statutes on the first
9day of the 3rd month beginning after publication.
SB554,9,1310
(3)
Selection of architects and engineers. The treatment of section 16.867
11of the statutes first applies to a construction project under the department of
12administration's supervision for which an advertisement is published or solicitation
13occurs on the effective date of this subsection.