AB499,8,62
20.370
(2) (gh)
Nonferrous metallic mining regulation and administration. 3The amounts in the schedule for the administration, regulation
, and enforcement of
4nonferrous metallic mining exploration,
bulk sampling, prospecting, mining and
5mine reclamation activities under ch. 293. All moneys received under ch. 293 shall
6be credited to this appropriation.
AB499,2
7Section 2
. 70.375 (4) (h) of the statutes is amended to read:
AB499,8,98
70.375
(4) (h) The cost of premiums for bonds required under s.
293.26 (9), 9293.51, 295.45 (5), or 295.59.
AB499,3
10Section 3
. 227.42 (4) of the statutes is repealed.
AB499,4
11Section 4
. 281.35 (5) (e) of the statutes is amended to read:
AB499,9,212
281.35
(5) (e)
Right to hearing.
Except as provided in s. 227.42 (4), any Any 13person who receives notice of a denial or modification requirement under par. (c) is
1entitled to a contested case hearing under ch. 227 if the person requests the hearing
2within 30 days after receiving the notice.
AB499,5
3Section 5
. 283.84 (3m) of the statutes is amended to read:
AB499,9,74
283.84
(3m) A person engaged in mining, as defined in s. 293.01 (9) or 295.41
5(26), prospecting, as defined in s. 293.01 (18), bulk sampling, as defined in s.
293.01
6(2m) or 295.41 (7), or nonmetallic mining, as defined in s. 295.11 (3), may not enter
7into an agreement under sub. (1).
AB499,6
8Section 6
. 293.01 (2m) of the statutes is created to read:
AB499,9,149
293.01
(2m) “Bulk sampling” means excavating in a potential mining site by
10removing less than 10,000 tons of material for the purposes of obtaining site-specific
11data to assess the quality and quantity of the nonferrous metallic mineral deposits
12and of collecting data from and analyzing the excavated materials in order to prepare
13the application for a mining permit or for any other approval. Bulk sampling does
14not constitute prospecting within the meaning of sub. (18).
AB499,7
15Section 7
. 293.01 (9) of the statutes is amended to read:
AB499,9,2016
293.01
(9) “Mining" or “mining operation" means all or part of the process
17involved in the mining of nonferrous metallic minerals, other than for exploration
,
18bulk sampling, or prospecting, including commercial extraction, agglomeration,
19beneficiation, construction of roads, removal of overburden and the production of
20refuse.
AB499,8
21Section 8
. 293.01 (18) of the statutes is amended to read:
AB499,9,2522
293.01
(18) “Prospecting" means engaging in the examination of an area for the
23purpose of determining the quality and quantity of nonferrous metallic minerals,
24other than for exploration
or bulk sampling but including the obtaining of a
25nonferrous metallic mineral sample, by such physical means as excavating,
1trenching, construction of shafts, ramps and tunnels and other means, other than for
2exploration
or bulk sampling, which the department, by rule, identifies, and the
3production of prospecting refuse and other associated activities. “Prospecting" shall
4not include such activities when the activities are, by themselves, intended for and
5capable of commercial exploitation of the underlying nonferrous ore body. However,
6the fact that prospecting activities and construction may have use ultimately in
7mining, if approved, shall not mean that prospecting activities and construction
8constitute mining within the meaning of sub. (9), provided such activities and
9construction are reasonably related to prospecting requirements.
AB499,9
10Section 9
. 293.13 (2) (b) (intro.) of the statutes is amended to read:
AB499,10,1211
293.13
(2) (b) (intro.) Minimum standards for exploration,
bulk sampling, 12prospecting
, and mining shall include the following:
AB499,10
13Section 10
. 293.13 (2) (b) 4. of the statutes is amended to read:
AB499,10,1514
293.13
(2) (b) 4. Adequate diversion and drainage of water from the
15exploration,
bulk sampling, prospecting
, or mining site.
AB499,11
16Section 11
. 293.13 (2) (b) 7. of the statutes is amended to read:
AB499,10,1817
293.13
(2) (b) 7. Removal and stockpiling, or other measures to protect topsoils
18prior to exploration,
bulk sampling, prospecting, or mining.
AB499,12
19Section 12
. 293.13 (2) (c) (intro.) of the statutes is amended to read:
AB499,10,2220
293.13
(2) (c) (intro.) Minimum standards for reclamation of exploration
and
21bulk sampling sites, where appropriate, and for prospecting and mining sites shall
22conform to s. 293.01 (23) and include provision for the following:
AB499,13
23Section 13
. 293.13 (2) (c) 7. of the statutes is amended to read:
AB499,11,224
293.13
(2) (c) 7. Revegetation to stabilize disturbed soils and prevent air and
25water pollution, with the objective of reestablishing a variety of populations of plants
1and animals indigenous to the area immediately prior to exploration,
bulk sampling, 2prospecting
, or mining.
AB499,14
3Section 14
. 293.15 (7m) of the statutes is created to read:
AB499,11,44
293.15
(7m) Issue approvals necessary for bulk sampling.
AB499,15
5Section 15
. 293.15 (8) of the statutes is amended to read:
AB499,11,126
293.15
(8) Promulgate rules regulating the production, storage and disposal
7of radioactive waste from exploration,
bulk sampling, prospecting
, or mining after
8seeking comments from the department of health services. At a minimum, rules
9promulgated under this subsection shall achieve the margin of safety provided in
10applicable federal statutes and regulations. If the department promulgates rules
11under this subsection, the department shall investigate the need for standards more
12restrictive than the applicable federal statutes and regulations.
AB499,16
13Section 16
. 293.26 of the statutes is created to read:
AB499,11,20
14293.26 Bulk sampling plan. (1) A person who intends to engage in bulk
15sampling may file a bulk sampling plan with the department. The collection of data
16under a bulk sampling plan may include sampling and analysis related to
17geophysical, geochemical, groundwater, and surface water conditions, as well as any
18other data or studies necessary to prepare an application for a mining permit,
19including the mining plan, reclamation plan, mining waste site feasibility study and
20plan of operation, or any other approval required for the proposed mining.
AB499,11,21
21(2) A person shall include all of the following in a bulk sampling plan:
AB499,11,2522
(a) A description and map of the bulk sampling site, including the number of
23acres in the site, the number of acres of land that will be disturbed, if any, associated
24with each bulk sampling location, and the locations and types of sampling or studies
25to be conducted at each bulk sampling location.
AB499,12,1
1(b) A description of the methods to be used for the bulk sampling.
AB499,12,42
(c) A site-specific plan for controlling surface erosion that conforms to
3requirements under ss. 281.33 (3) and 283.33 and that identifies how impacts to
4plant and wildlife habitats will be avoided or minimized to the extent practicable.
AB499,12,95
(d) A revegetation plan for each area where bulk sampling will be performed
6that describes how adverse impacts to the environment will be avoided or minimized
7to the extent practicable and how the site will be revegetated and stabilized and that
8identifies how adverse impacts to plant and wildlife habitats will be avoided or
9minimized to the extent practicable.
AB499,12,1110
(e) The estimated time for completing the bulk sampling and revegetation of
11the bulk sampling locations.
AB499,12,1412
(f) A description of any known adverse environmental impacts that are likely
13to be caused by the bulk sampling and how those impacts will be avoided or
14minimized to the extent practicable.
AB499,12,2015
(g) A description of any adverse effects, as defined in s. 44.31 (1), that the bulk
16sampling might have on any historic property, as defined in s. 44.31 (3), that is a
17listed property, as defined in s. 44.31 (4), that is on the Wisconsin inventory of historic
18places, as defined in s. 44.31 (12), or that is on the list of locally designated historic
19places under s. 44.45; or any scenic or recreational areas; and plans to avoid or
20minimize those adverse effects to the extent practicable.
AB499,13,3
21(3) The department shall protect as confidential any information, other than
22effluent data, contained in a bulk sampling plan and in any application for an
23approval that is required before the bulk sampling may be implemented, upon a
24showing that the information is entitled to protection as a trade secret, as defined in
25s. 134.90 (1) (c), and any information relating to the location, quality, or quantity of
1a nonferrous metallic mineral deposit, to production or sales figures, or to processes
2or production unique to the applicant or that would tend to adversely affect the
3competitive position of the applicant if made public.
AB499,13,11
4(4) Within 14 days of receipt of a bulk sampling plan, the department shall
5identify for the applicant, in writing, all approvals that are required before the bulk
6sampling may be implemented, any waivers, exemptions, or exceptions to those
7approvals that are potentially available, and any information that the department
8needs to issue the approvals or to issue a decision on any waiver, exemption, or
9exception. If no approvals are required, the department shall notify the applicant
10that no approvals are required and that the applicant may proceed with the bulk
11sampling.
AB499,13,15
12(5) If a storm water discharge permit under s. 283.33 (1) (a) or a water quality
13certification under rules promulgated under subch. II of ch. 281 to implement
33
14USC 1341 (a) is required before bulk sampling may be implemented, the person filing
15the bulk sampling plan may apply for and be issued the permit or certification.
AB499,13,19
16(6) The department shall act on any required construction site erosion control
17and storm water management approval, notwithstanding any authorization by the
18department of a local program to administer construction site erosion control and
19storm water management requirements.
AB499,13,20
20(7) An applicant shall submit all of the following at the same time:
AB499,13,2121
(a) Applications for individual approvals identified under sub. (4).
AB499,13,2322
(b) Applications for coverage under general permits or registration permits
23identified under sub. (4).
AB499,13,2524
(c) Applications for waivers, exemptions, or exceptions identified under sub.
25(4).
AB499,14,1
1(d) A bond, as provided in sub. (9).
AB499,14,10
2(8) (a) Notwithstanding any provision in ch. 23, 29, 30, 31, 169, 281, 283, 285,
3289, or 291 or in a rule promulgated under those chapters that is applicable to an
4approval identified under sub. (4), the application for any approval, for a waiver,
5exemption, or exception to an approval, or for a determination that the proposed bulk
6sampling activity is below the threshold that requires an approval, is considered to
7be complete on the 30th day after the department receives the application, unless,
8before that day, the department provides the applicant with written notification that
9the application is not complete, stating the reason for the determination and
10describing the specific information necessary to make the application complete.
AB499,14,1311
(b) If the department provides a notice under par. (a), the applicant shall
12supplement the application by providing the specified information. The application
13is complete when the applicant provides the information.
AB499,14,1814
(c) If the department determines that the issuance of an approval is contingent
15upon the issuance of a permit under s. 29.604 (6m), and if the application for the
16permit under s. 29.604 (6m) is filed with the approval application, the department
17may not determine that the approval application is incomplete on the basis that the
18department has not yet issued the permit under s. 29.604 (6m).
AB499,14,24
19(9) (a) A person who intends to engage in bulk sampling shall submit with the
20bulk sampling plan a bond in the amount of $5,000 that is conditioned on faithful
21performance of the requirements of this section, that is issued by a surety company
22licensed to do business in this state, and that provides that the bond may not be
23canceled by the surety, except after not less than 90 days' notice to the department
24in writing by registered or certified mail.
AB499,15,5
1(b) If the surety for a bond submitted under par. (a) issues a cancellation notice,
2the person who filed the bulk sampling plan shall deliver a replacement bond at least
330 days before the expiration of the 90-day notice period. If the person fails to submit
4a replacement bond, the person may not engage in bulk sampling until the person
5submits a replacement bond.
AB499,15,106
(c) If the license of the surety company for a bond submitted under par. (a) is
7revoked or suspended, the person who filed the bulk sampling plan, within 30 days
8after receiving written notice from the department, shall deliver a replacement bond.
9If the person fails to submit a replacement bond, the person may not engage in bulk
10sampling until the person submits a replacement bond.
AB499,15,1411
(d) The department may require that the amount of the bond submitted under
12this subsection be increased at any time, if the department determines that it is
13unlikely that the bond would be adequate to fund the cost to this state of completing
14the revegetation plan.
AB499,15,1815
(e) The department shall release a bond submitted under this subsection one
16year after the time for completing the bulk sampling and the revegetation set forth
17in the bulk sampling plan if the department determines that the person who engaged
18in bulk sampling has complied with this section.
AB499,15,23
19(10) Notwithstanding any provision in ch. 23, 29, 30, 31, 169, 281, 283, 285,
20289, or 291 or a rule promulgated under those chapters applicable to an approval
21identified under sub. (4), the department shall require the bulk sampling activity for
22which the approval is issued to be conducted at locations that result in the fewest
23overall adverse environmental impacts.
AB499,16,3
1(11) (a) In determining whether to approve or deny an application for an
2approval identified under sub. (4), the department shall consider the site-specific
3erosion control plan, the revegetation plan, and any wetland mitigation program.
AB499,16,64
(b) The department may modify the application for an approval identified
5under sub. (4) in order to meet the requirements applicable to the approval, and, as
6modified, approve the application.
AB499,16,11
7(12) Notwithstanding any inconsistent period in ch. 23, 29, 30, 31, 169, 281,
8283, 285, 289, or 291 or in a rule promulgated under those chapters that is applicable
9to an approval identified under sub. (4), the department shall approve or deny an
10application within 30 days after the day on which the application is considered to be
11complete under sub. (8) if any of the following applies:
AB499,16,1412
(a) The application is for a waiver, exemption, or exception to an approval for
13a bulk sampling activity or for a determination that the proposed bulk sampling
14activity is below the threshold that requires an approval.
AB499,16,1615
(b) The application is for a determination of eligibility for coverage or
16authorization to proceed under a general permit or a registration permit.
AB499,16,24
17(13) (a) Notwithstanding any inconsistent period in ch. 23, 29, 30, 31, 169, 281,
18283, 285, 289, or 291 or in a rule promulgated under those chapters that is applicable
19to an approval identified under sub. (4), the department shall approve or deny any
20application for an approval identified under sub. (4) to which sub. (12) does not apply
21within 60 days after the date on which the application is considered to be complete
22under sub. (8), unless the application is for an individual permit for which federal law
23requires the opportunity for public comment or the ability to request a public hearing
24prior to issuance of the approval.
AB499,17,10
1(b) The department shall publish a class 1 notice, under ch. 985, and shall
2publish notice on the department's Internet site, that describes the availability of
3information concerning the activity for which an approval described in par. (a) is
4required, its proposed decision, its draft approval, information or summaries related
5to the approval, the department's analyses and preliminary determinations relating
6to the approval, any additional information that a law concerning the approval
7requires to be made available, and the opportunity to submit written comments
8within 30 days after the date of the publication of the notice. The date on which the
9department first publishes the notice on its Internet site shall be considered the date
10of the publication of the notice required to be published under this paragraph.
AB499,17,1811
(c) In the notice under par. (b), the department shall also specify the date, time,
12and location of the public informational hearing under par. (e). The department shall
13send the notice to any person to whom the department is required to give notice of
14any proposed determination, application, or hearing concerning an approval
15described in par. (a) under the laws relating to the issuance of the approval and to
16any person who has requested notice. The department's notice to interested persons
17under this paragraph may be given through an electronic notification system
18established by the department.
AB499,17,2519
(d) If there is more than one approval described in par. (a), the department shall
20issue one notice and coordinate the public comment period for all of the approvals.
21If possible, the department shall coordinate the notice and the public comment
22period for an approval that is an individual permit for which federal law requires the
23opportunity for public comment or the ability to request a public hearing prior to
24issuance of the approval with notice and the public comment period for the approvals
25described in par. (a).
AB499,18,11
1(e) The department shall hold a public informational hearing within 30 days
2after the date of the publication of the notice under par. (b). The department shall
3hold the public informational hearing in the county where the majority of the
4proposed bulk sampling site is located. If there is more than one approval described
5in par. (a), the department shall hold a single public informational hearing covering
6all of the approvals. If possible, the department shall include consideration of an
7approval that is an individual permit for which federal law requires the opportunity
8for public comment or the ability to request a public hearing prior to issuance of the
9approval in the public informational hearing under this paragraph. The public
10informational hearing under this paragraph is not a contested case hearing under
11ch. 227.
AB499,18,18
12(14) (a) If it is not possible to coordinate the public comment period and public
13informational hearing for an approval that is an individual permit for which federal
14law requires the opportunity for public comment or the ability to request a public
15hearing prior to issuance of the approval with the public comment period and public
16informational hearing under sub. (13), the department shall issue a separate public
17notice and hold a separate public informational hearing for the approval in
18accordance with the law governing the approval.
AB499,18,2319
(b) The department shall approve or deny the application for an approval that
20is an individual permit for which federal law requires the opportunity for public
21comment or the ability to request a public hearing prior to issuance of the approval
22within 180 days after the date on which the application is considered to be complete
23under sub. (8).
AB499,18,25
24(15) An approval identified under sub. (4) is issued upon mailing and is final
25and effective upon issuance.
AB499,19,3
1(16) The department is not required to prepare an environmental impact
2statement or an environmental assessment for an approval required for bulk
3sampling.
AB499,17
4Section 17
. 293.31 (title) of the statutes is amended to read:
AB499,19,5
5293.31 (title)
Data
Preapplication notification; data collection.
AB499,18
6Section 18
. 293.31 (1) of the statutes is amended to read:
AB499,20,157
293.31
(1) Any At least 12 months before filing an application for a prospecting
8permit under s. 293.35 or a mining permit under s. 293.37, a person proposing to
9engage in a prospecting or mining project shall notify the department in writing of
10the intention to apply for a prospecting or mining permit. A person who intends to
11give notice of intent to apply for a prospecting or mining permit may, prior to
12obtaining, collecting, or generating environmental data intended to be used to
13support the permit application, submit to the department the methodology that the
14person intends to use in obtaining, collecting, or generating the data. The
15department shall review the proposed methodology and shall either inform the
16person that the proposed methodology will be accepted by the department or provide
17the person with the methodology that the department requires to be used. The
18department may assess the person submitting the proposed methodology a fee equal
19to the department's costs for reviewing the proposed methodology. If a person
20intending to submit an application for a prospecting or mining permit shall notify the
21department prior to the collection of obtains, collects, or generates data or
22information intended to be used to support
the
a prospecting or mining permit
23application
. Specific environmental data which would be pertinent to a specific
24prospecting or mining application, but which was obtained or collected or generated
25prior to the notice of intent to apply for a prospecting or mining permit, shall be
1submitted in writing to the department together with any substantiating
2background information which would assist the department in establishing the
3validity of the data. The department shall review the data and, if it concludes that
4the benefits of permitting the admission of the data outweigh the policy reasons for
5excluding it, and if the data is otherwise admissible, inform the person giving the
6notice of intent to prospect or mine that the data will be accepted by the department.
7Such exclusion shall not relate to without obtaining department approval of the
8person's methodology under sub. (4), the department may not exclude any of the data
9or information that consists of general environmental information such as soil
10characteristics, hydrologic conditions
, and air and water data contained in
11publications, maps, documents, studies, reports
, and similar sources, whether public
12or private, not prepared by or for the applicant.
Such exclusion shall likewise not
13relate to data which is otherwise admissible that is collected prior to notification
14under this subsection for purposes of evaluating another site or sites and which is
15not collected with intent to evade the provisions of this section.
AB499,19
16Section 19
. 293.31 (2) of the statutes is amended to read:
AB499,20,1917
293.31
(2) Upon receipt of notification under sub. (1), the department shall give
18public notice of the notification in the same manner as provided under s. 293.43
(3) 19(2m) (b).
AB499,20
20Section 20
. 293.31 (3) of the statutes is amended to read:
AB499,21,321
293.31
(3) The department shall also receive and consider any comments from
22interested persons received within 45 days after public notice is given under sub. (2)
23as to the information which they believe should be requested from the person giving
24notice of intent to apply for a prospecting or mining permit and the information
25which they believe the department should seek through independent studies.
If the
1department holds a public informational hearing to receive comments from
2interested persons under this section, the hearing shall be completed within 45 days
3after public notice is given under sub. (2).
AB499,21
4Section 21
. 293.31 (4) of the statutes is amended to read:
AB499,21,215
293.31
(4) After No later than 90 days after the
receipt period for receiving and
6consideration of considering comments from interested persons
under sub. (3), the
7department shall inform the person giving notice of intent to apply for a prospecting
8or mining permit of the type and quantity of information that it then believes to be
9needed to support an application
, and
, where applicable, the methodology to be used
10in gathering information. The department shall specifically inform the person giving
11notice of intent to apply for a prospecting or mining permit of the type and quantity
12of information on the characteristics of groundwater resources in the area in which
13prospecting or mining is anticipated to occur which the department believes is
14needed to support an application
, including the information that the department
15believes should be included in the applicant's environmental impact report and the
16information that the department will need to prepare an environmental impact
17statement. The department shall also
begin informing inform the person giving
18notice of intent to apply for a prospecting or mining permit
as to of the
timely 19application date
and other filing requirements for
all other approvals, licenses
, and
20permits
, so as to facilitate the consideration of all other matters at the hearing on the
21prospecting or mining permit relating to the proposed prospecting or mining project.
AB499,22
22Section 22
. 293.31 (4m) of the statutes is created to read:
AB499,22,923
293.31
(4m) Before providing the information required under sub. (4), the
24department shall seek to enter into a memorandum of understanding with the
25applicant, the U.S. army corps of engineers, and any other federal regulatory agency
1with responsibilities related to the potential prospecting or mining operation to
2address sampling methodology and any other issue of mutual concern related to
3processing an application for a prospecting or mining permit. The memorandum
4may include an agreement between the department and the applicant relating to
5timelines, including timelines for the parties to conduct environmental studies and
6for granting or denying the prospecting or mining permit. The U.S. army corps of
7engineers, and any other federal agency that is a party to the memorandum, is not
8required to be a party to any agreement relating to timelines between the
9department and the applicant.
AB499,23
10Section 23
. 293.32 (4) of the statutes is created to read:
AB499,22,1311
293.32
(4) Subchapter VI of ch. 289 does not apply to mining waste disposed
12of in a mining waste site covered by a mining permit, except that an operator shall
13pay the fees specified in ss. 289.63 (4), 289.64 (3), and 289.67 (1) (d).
AB499,24
14Section 24
. 293.37 (5) of the statutes is created to read:
AB499,22,2015
293.37
(5) If the department requires an applicant for a mining permit to
16conduct engineering and hydrologic modeling to assess a mining waste site's
17performance relative to compliance with applicable groundwater quality standards
18and surface water quality standards, the department may not require the applicant
19to examine a period longer than the period in which the mining waste site is proposed
20to operate plus 250 years after closure of the mining waste site.
AB499,25
21Section 25
. 293.40 of the statutes is created to read:
AB499,23,3
22293.40 Timeline for review. (1) Subject to subs. (4) and (5), within 180 days
23after an applicant submits an application for a prospecting or mining permit, an
24environmental impact report, if required, and any applications for other approvals,
25licenses, or permits relating to the prospecting or mining operation the department
1shall review the information submitted and, if necessary, provide comments to the
2applicant and request additional information from the applicant relating to the
3proposed prospecting or mining project.
AB499,23,9
4(2) Subject to subs. (4) and (5), if the department requests additional
5information from an applicant under sub. (1), within 90 days after the applicant
6provides additional information the department shall review the information
7submitted and, if necessary, provide comments to the applicant and request
8additional information from the applicant relating to the proposed prospecting or
9mining project.